In this аppeal we examine the sufficiency of a complaint to state a claim regarding two issues: (1) whether a contractor who *489 alleges it satisfactorily completed the construction project is entitled to equitable relief in order to reach the balance of loan funds withheld by a construction lender, and (2) whether officers and directors of the owner. corporation with which he contracted to build the project tortiously interfered with that contract by thwarting final payment. In accord with the attitude of liberal construction that notice pleading inspires, we hold plaintiff alleged facts sufficient to state both claims.
I.
In a complaint filed 17 November 1988, plaintiff, a construction contractor, alleges it entered into a contract with defendant Rafcor on 20 October 1987 to supply labor and materials for the construction of a restaurant in Mecklenburg County. Plaintiff alleges its work was completed according to the plans and specifications prescribed by the contract and that Rafcor owes plaintiff a balance of $110,383, including $32,973 for extra work and delay claims. Plaintiff alleges Rafcor has refused its demand to pay this amount.
Plaintiff further alleges Rafcor entered into a construction loan agreement with United Carolina Bank (UCB) in which UCB was “obliged to advance to Rafcor the sum of $942,500 to be used specifically for the construction of the project.” Rafcor’s note to this effect was secured by a deed of trust on the project. Throughout construction plaintiff periodically submitted applications for progress payments to Rаfcor, which UCB paid directly to plaintiff from Rafcor’s construction loan. Rafcor occupied the building in February 1988, and plaintiff completed its work in March 1988. Plaintiff’s last two applications for payment after completion of the restaurant in March were not paid. By letter dated 8 July 1988 plaintiff notified UCB of the sum due and requested that the funds remaining in the construction loan be disbursed to plaintiff. Plaintiff alleges Rafcor’s loan was not in default when plaintiff notified UCB as to the outstanding debt and requested that the remainder of the fund be disbursed. UCB nevertheless retained and refused to disburse the $70,000 remaining in the loan fund to plaintiff. Plaintiff alleges UCB has received all the security for which it bargained with Rafcor —a completely constructed building — and because it has refused to pay the $70,000 remaining in the loan fund, UCB has been unjustly enriched at plaintiff’s expense.
*490 Plaintiff alleges in addition that defendants Tedesco and Occhino, officers and directors of Rafcor who personally guaranteed Rafcor’s note with UCB, intentionally induced Rafcor not to make further draws from UCB in order to limit their personal liability to UCB.
The superior court allowed motions to dismiss filed by UCB and by Tedesco and Occhino. A divided panel of the Court of Appeals reversed. The majority deemed plaintiff’s claim against UCB as an equitable lien on the construction loan balance, reasoning plaintiff was entitled to equitable relief because it had completed construction in reliance on the disbursal of the fund when the owner was not in default. The majority also reversed the superior court’s dismissal of plaintiff’s claim against defendants Tedesco and Oсchino. Noting that the right of officers and directors to interfere with the contracts of their corporation is limited, the Court of Appeals held that plaintiff’s complaint stated facts sufficient to support its allegation that the individual defendants’ acts had been in their own interest and adverse to that of their firm, thus exposing them to individual liability for an individual tort.
The dissent observed that no occasion for equitable intervention by the courts arises when a remedy at law is available and opined that under the circumstances of this case plaintiff’s remedies are limited to the lien procedures of N.C.G.S. §§ 44A-7 through 44A-23. Because “the creditor possesses an interest only to the extent of the amount disbursed,” UCB was not unjustly enriched.
II.
On motion to dismiss a complaint for failure to state a claim, the complaint’s factual allegations are taken as true. The court must determine whether the complaint alleges the substantive elements of a legally recognized claim and whether it gives sufficient notice of the events that produced the claim to enable the
*491
adverse party to prepare for trial.
Peoples Security Life Ins. Co. v. Hicks,
Plaintiffs allegations that UCB retained the balance of the construction loan despite plaintiff’s completion of the project underlie its claim that UCB has been unjustly enriched and that the balance of the loan fund constitutes a “trust fund” on which plaintiff has an equitable lien.
The court’s equitable intervention is obviated when an adequate remedy at law is available to the plaintiff, as the dissent correctly notes. “[EJquity will not lend its aid in any case where the party seeking it has a full and complete remedy at law.”
Insurance Co. v. Guilford County,
As alleged, 1 however, the circumstances of this case are not among those for which Chapter 44A supplies a remedy. Section 44A-8 provides, in pertinent part:
*492 Any person who performs or furnishes labor or ... materials pursuant to a contract, either express or implied, with the owner of real property for the making of an improvement thereon shall, upon complying with the provisions of this article, have a lien on such real property to secure payment of all debts owing for labor done or . . . material furnished pursuant to such contract.
N.C.G.S. § 44A-8 (1989). The purpose of this lien statute is to protect the interest of the contractor, laborer or materialman.
See, e.g., Carolina Builders Corp. v. Howard-Veasey Homes, Inc.,
Commentators, too, have observed that the statutory remedies of Chapter 44A include no relief “against the construction lender or the funds in his hands.” William H. Higgins,
Construction Lending
— General
Contractor v. Lender,
54 N.C. L. Rev. 952, 954
*493
(1976) [hereinafter Higgins]. The remedies available under Chapter 44A are “often of no-practical value” for the very reasons plaintiff here seeks equitable relief.
Id.
at 953. When a contractor’s lien is subordinate to a construction loan mortgage, as here, or to prior encumbrances such as a purchase money mortgage, any lien on the owner’s property or its improvements is worthless when the owner is insolvent.
Id.
at 954 n.10.
Cf. Carolina Bldrs. Corp. v. Howard-Veasey Homes, Inc.,
In other jurisdictions, attemрts made to reach construction funds remaining with the lender under equitable assignment, third party beneficiary, and trust fund theories have been generally unsuccessful. Higgins at 954 n.12.
See also
Edmund T. Urban,
Future Advances Lending,
13 Wake Forest L. Rev. 297, 343 n.281 (1977) [hereinafter Urban].
E.g., Gordon Building Corp. v. Gibraltar Sav. & Loan Ass’n,
Attempts to obtain relief in the form of an equitable lien based on a theory of detrimental reliance or unjust enrichment have been more fruitful, most notably in California
2
and Florida.
E.g.,
*494
Pacific Ready Cut Homes v. Title Ins. & Trust Co.,
When unjust enrichment underlies an equitable lien, some courts have considered completion of the plaintiff’s work — or of the project itself — critical. In
Urban Systems Development Corp. v. NCNB Mortgage Corp.,
Plaintiff avers that by UCB’s refusal to disburse the monies remaining in the construction loan fund, coupled with its receipt of all the security for which it bargained in the form of a completed building, UCB was unjustly enriched. We agree. As of completion of the building in March 1988, UCB had received all the security for which it had bargained with Rafcor. UCB’s subsequent refusal to release the balance of the construction loan caused it to be unjustly enriched at the expense of plaintiff. 3
*496
“A person who has been unjustly enriched at the expense of another is required to make restitution to the other.”
Booe v. Shadrick,
Several federal courts considering suits by contractors involved in building projects whose loans were insured by HUD have held retainages and construction loan balances generally constitute an identifiable
res
upon which an equitable lien may be attached. In
Spring Const. Co. v. Harris,
Accepting as true plaintiff’s allegations that as of March 1988 it completed the project but was refused its applications for payment from the balance of the construction loan fund held by UCB, we hold plaintiff’s complaint was sufficient to state a claim for relief in the form of an equitable lien based upon UCB’s unjust enrichment.
III.
Plaintiff also alleges defendants Tedesco and Occhino, who personally guaranteed Rafcor’s note with UCB, had actual knowledge of Rafcor’s obligations to pay plaintiff for amounts due under the contract, that they intentionally induced Rafcor not to pay amounts requested in plaintiff’s last two applications for payment nor to request UCB to draw funds from the construction loan fund to pay plaintiff, and in so doing “acted without justification and in their own interest to avoid further liability to UCB under their guarantees.” Plaintiff alleges these facts support a claim for tortious interference with contract.
The Court of Appeals held plaintiff alleged all the elements of that tort. It surmised the trial court granted defendants’ motion to dismiss under the mistaken impression that the element that defendants had acted without justification “[could not] be established since defendants, as officers and directors of the contracting cоrporation, had the right and duty to act for the company in regard to its contracts and other business.”
*498 The dissent considered plaintiff’s allegations incomplete for failure to add that the аcts of defendants Tedesco and Occhino had been “adverse” to the interests of their firm.
The elements of tortious interference with contract are:
(1) a valid contract between the plaintiff and a third person which confers upon the plaintiff a contractual right against a third person; (2) defendant knows of the contract; (3) the defendant intentionally induces the third person not to perform the contract; (4) and in doing so acts without justification; (5) resulting in actual damage to the plaintiff.
United Laboratories, Inc. v. Kuykendall,
Whether an actor’s conduct is justified depends upon “the circumstances surrounding the interference, thе actor’s motive or conduct, the interests sought to be advanced, the social interest in protecting the freedom of action of the actor[,] and the contractual interests of the other party.”
Peoples Security Life Ins. Co. v. Hooks,
In the context of interference with contract by an insider, however, the element that the defendant acted without justification is potentially vitiated by the defendant’s corporate position. Officers, directors, shareholders, and other corporate fiduciaries have “a qualified privilege to interfere with contractual relations between the corporation and a third party.”
Wilson v. McClenny,
The privilege, however, is qualified, not absolute; the presumption that an officer’s acts are in the corporation’s interest and thus justified is overcome when the means or the officer’s motives are improper.
See id.
at 133,
First, the qualified privilege of . officers and directors to interfere with the corporation’s contracts rests upon the assumption that their actions are “in good faith and for the best interests of their corporation.”
Wilson v. McClenny,
Second, it is unreasonable to require the plaintiff to negate in its pleadings facts that more properly support a defense. One California appellate court, reciting elements of tortious interference with contract similar to those recognized in North Carolina,
4
has held: “Unless it appears on the face of the complaint that a defendant’s conduct was justified, justification is an affirmative defense.”
Freed v. Manchester Serv., Inc.,
Third, notice pleading and its corollary, the liberal construction of complaints, supports our view that plaintiff adequately stated the claim’s fourth element. “Under the notice theory of pleading, a statement of a claim is adequate if it gives sufficient notice of the events or transactions which produced the claim to enable the adverse party to understand its nature and basis and to file a responsive pleading.”
Pyco Supply Co., Inc. v. American Centennial Ins. Co.,
A complaint alleging corporate insiders tortiously interfered with plaintiff’s contract with their corporation does not thereby disclose an insurmountable bar to recovery, for the insiders’ privilege is qualified, not absolute. Beсause privilege is qualified, presumption of privilege does not nullify the element that defendants allegedly acted without justification, as the trial court apparently assumed. In order to state that element, the plaintiff must allege facts demonstrating that defendants’ actions were not prompted by “legitimate business purposes.”
*501
We hold it was sufficient, under the liberal concept of notice pleading, for plaintiff to allege the existence of a valid contract between itself and Rafcor entitling plaintiff to payment from the construction loan fund, that defendants Tedesco and Occhino knew of this contract and intentionally induced Rafcor not to perform “in their own interest to avoid further liability to UCB under their [personal] guarantees,” and that in so doing they acted without justification to plaintiffs detriment. These allegations give sufficient notice of the events on which the claim is based to enable defendants to respond- and prepare for trial and are “sufficient to satisfy the substantive elements of the claim” of tortious interference with сontract.
Privette v. University of North Carolina,
We further hold the Court of Appeals properly reversed orders of the superior court dismissing plaintiffs complaint against defendants UCB and Tedesco and Occhino. The decision of the Court of Appeals is accordingly
Modified and affirmed.
Notes
. Reasons why the remedies of Chapter 44A would not satisfy a claim against Rafcor for the remainder of the construction fund are not articulated in plaintiff’s complaint. In its brief UCB argues plaintiff filed a claim of lien on 1 July 1988 but failed to perfect the lien within 180 days. Had plaintiff perfected its claim, it could have forced a sale of the improved property and thus “would have been protected to the extent intended by Chapter 44A.” Plaintiff responds that because UCB’s mortgage interest was superior to plaintiff’s lien, plaintiff’s interest was cut off, virtually obliterating any likelihood plaintiff would collect either the $110,383 *492 it was owed or the $70,000 remaining in the loan fund. UCB did in fact foreclose on the property on 30 December 1988, effectively cutting off any subordinate liens. In addition, the contract between plaintiff and Rafcor stated final paymеnt would not become due until all liens arising out of the contract were released.
. Controversy wrought by the liberal application of the equitable lien by California courts,
see, e.g.,
Lefcoe & Shaffer,
Construction Lending and the Equitable Lien,
40 S. Cal. L. Rev. 439 (1967), inspired an amendment to the California lien
*494
statute, Cal. Civ. Code § 3264 (West 1974), which bars any equitable relief outside the contract or the statute.
See Boyd v. Lovesee Lumber Co. v. Western Pacific Financial Corp.,
. This situation differs markedly from that in which the lender has disbursed all loan funds to the borrower, who diverts the funds to purposes other than paying contractors. See Lefcoe & Shaffer, Construction Lending and the Equitable Lien, 40 S. Cal. L. Rev. 444 (1967) (if funds disbursed once already, lender not unjustly enriched); Urban and Miles at 350 (“[T]here is justification for the [equitable lien] doctrine’s application when the contractor has completed performance, the entire project itself is completed, and the lender forecloses, becoming the owner of the completed project seeking to retain undisbursed funds. But there is little justification for the doctrine’s application when the lender has made a disbursement for all labor or materials furnished up through foreclosure without any knowledge of any unpaid claims, and funds are diverted from the project by the borrower. *496 In that instance, application of the doctrine results in the inequity of the lender having to in effеct pay twice for the same thing. Any application of the doctrine, therefore, should be restricted to obvious cases of unjust enrichment.”).
. “[T]he allegations necessary in order for the complaint to withstand a general demurrer [are:] the existence of a valid contract; that the defendant had knowledge of the existence of the contract and intended to induce a breach thereof; that the contract was in fact breached resulting in injury to plaintiff; and the breach and resulting injury must have been proximately caused by defendant’s unjustified or wrongful conduct.”
Freed v. Manchester Serv., Inc.,
