193 Iowa 330 | Iowa | 1921
Briefly outlining the situation of the parties at the date of the contracts between them, it should be said that the defendant railway company, having undertaken the project of building an electric railway from the city of Waterloo to the city of Cedar Rapids, let the contract for the construction of such improvement to its codefendant, the Cedar Valley Railway Construction Company, which company in turn sublet the work for grading the roadbed to R. A. Elzy, since deceased. For some reason, this work of grading was let to Elzy in four distinct parts, each part being made the subject of a distinct written agreement. The contract for the first of these parts, extending from Waterloo to La Porte, dated April 19, 1912, was to be completed September 1, 1912; the second contract, dated August 20, 1912, was for the grading from La Porte to Urbana, to be completed to Brandon June 1, 1913, and to Urbana Jtxly 1, 1913; the third contract, dated September 8, 1913, was for the grading from Urbana to Center Point, to be completed April 15, 1914; and the fourth and last contract, dated January 6, 1914, provided for the completion of the grade from Center Point to Cedar Rapids June 1, 1914. The said several sections of grading were not all completed within the contract periods, but the work as a whole seems to have been finally and formally accepted on September 5, 1914; and the contractor, Mr. Elzy, died on the following day.
The plaintiffs, as executors of the Elzy estate, engaged in a somewhat prolonged effort to effect' a settlement with the defendants, who, while expressing a willingness and desire to pay whatever was justly due the estate, found themselves hampered, for the time being, by unfavorable conditions in the money market. In November, 1914, counsel for plaintiffs prepared a statement of their claim, ready for filing a mechanics’ lien, but, before placing it upon record, interviewed the defendants again upon the subject of a settlement. Defendants again pleaded the difficulty they were experiencing in obtaining the needed funds,
On August 31, 3917, this action was begun at law, to recover the alleged unpaid remainder of the claim due the estate. The issues, as at first defined by the pleadings, were very numerous; but in the course of the trial below, many minor matters of dispute were eliminated or abandoned, and defendants’ appeal to this court is limited to the single proposition that the trial court erred in refusing to assess liquidated damages against the Elzy estate. In their brief, counsel for appellant state the question thus:
“Did the contract provide for liquidated damages in case of default in the time of performance, or did it provide for a penalty only? If it provided for a penalty only, it is to be conceded, without more ado, that the action of the court was correct, because it was admitted that the amount of actual damages was not attempted to be proven.”
By the ruling of the trial court upon the motions for a directed verdict, the plaintiffs’ recovery was for moneys alleged to be due them upon the claims stated in Count 4 of Division 4 of their amended and substituted petition, which is based upon the contract covering the grading of the roadbed from La Porte to Urbana. Stated in the aggregate, it is there charged that Elzy’s earnings under this contract were $102,259.28, against
Answering this claim, the defendants’ admit Elzy’s earnings under this contract and the credits due to the defendants thereon to be as alleged, but aver that the remainder due from defendants upon such account should be reduced by the further sum of $12,600, as liquidated damages because of the .contractor’s failure to complete the work within the agreed time. Upon this contention the court below ruled against the defendants, and upon this holding the principal error argued is assigned.
I. Whether a given contract is to be construed as providing for liquidated damages is not always easy of determination. Counsel for appellant frankly concede upon this question that:
“The court will not necessarily be concluded by the language used in the contract, but will scrutinize the whole contract, the subject-matter thereof, and the extraneous facts tending to make clear the real nature of the stipulation. Neither the use of the word ‘liquidated’ or the words ‘liquidated damages’ nor the fact that the actual damages would be difficult of proof, nor even the intention of the parties to actually provide for liquidated damages, will necessarily control such construction. Doubts will be resolved against the allowance.”
This is, of course, not a concession that such circumstances are to be ignored; for they are both relevant and material, and to be given due consideration for what they are fairly worth, in arriving at a conclusion whether, upon the record as a whole, and under the settled rules of law upon the subject, the contract under investigation does or does not provide for stipulated damages.
At the outset upon this question, let us_ look to the particular clause of the contract which appellants quote as the foundation of their claim for such damages. The language so selected by counsel is that:
“The contractor specifically agrees to pay to the railway company as liquidated damages the sum of $50 for each and every day from and beyond June 1, 1913; that the grading from La Porte to Brandon remains unfinished and $50 for each and every day from and beyond July 1, 1913, that the grading from Brandon to Urbana remains unfinished, and it is specifically*334 understood and agreed that the railway company may reimburse itself for the full aggregate amount of sums named for either or both of these defaults from any money or moneys remaining in its hands, and owing the contractor under the terms of this agreement, but should the railway company so elect it may bring action in any of the courts of this state to collect said amounts due under said defaults.”
Now, the language so quoted and relied upon by appellants does appear in the contract, but counsel omit therefrom very much matter without which its legal effect cannot be fully comprehended. The entire contract, as executed, contains 24 distinct paragraphs, and it is .in the twelfth of these that we find the quoted clause. This paragraph is very long, and not a little complicated; but the bull? of its many provisions has, as we think, a decisive bearing upon the vital question presented by the appeal, and at the risk of making our ppinion tedious, we here quote it in full.
“Payment of Labor.
‘112. Under the terms and conditions of this agreement, the contractor shall have until June 1, 1913, to complete the grading from La Porte to Brandon, and until July 1, 1913, to complete the grading from Brandon to Urbapa, but in case the contractor by use of more equipment, of men, teams, and machinery, or in any other manner, succeeds in completing the entire job of grading from La Porte to Urbana as contemplated by this contract on or before December 20, 1912, then and in that event, the railway company specifically agrees to pay the contractor, in addition to'the sums provided for by this contract, the further sum of,$7,500 cash, which amount shall be the only additional payment required from the railway company in consideration of the contractor completing all the work on or before December 20, 1912, nor shall any of the above mentioned additional $7,500 be due or payable should the grading be completed subsequent to December 20, 1912, but prior to the above dates of June 1, 1913, and July 1, 1913.
“On the other hand, however, and in consideration of the railway company’s agreement to pay the further sum of $7,500 should the grading be finished on or before December 20, 1912,
To be valid and enforcible, an agreement for stipulated damages, like all other contracts, must expressly or impliedly
To a brief resume of these reservations or alternatives we prefix the final clause of the paragraph, as casting light upon the company’s own conception of the nature and effect of the reserved alternatives. It reads as follows:
“In all eases, the railway company shall be entitled to reimbursement by the contractor to the full extent of the damages or loss arising to the company by default of the contractor under this contract. Should the railway company avail itself of any of the remedies herein above described as an alternative to the penalties of $50 per day for failing to complete the grading * * # then and in that event the right of the company to collect said penalties shall cease and determine but otherwise it shall remain in full force and effect; but'it is understood and agreed that the service of the- notice hereinabove mentioned or any other act of the company except the actual carrying out of one or more of said alternatives shall not relieve the contractor from the payment of the penalties.”
It will thus be seen that, while appellants now insist that
All these alternatives were open to the defendants to the last moment; and if the situation had proved to be such, or if at any time they believed that, by taking advantage of any one of the alternatives, they could exact greater damages than could be assessed under the alleged stipulation, there was nothing in. their contract to prevent their doing so. It is not necessary, upon this appeal, that we pass upon the validity of such an agreement. It is enough here to say that it cannot be construed as providing for stipulated damages.
II. While our conclusion, already stated, necessitates an affirmance of the judgment below, we think that the result is easily sustainable on other grounds. So far as concerns the subject-matter of the contract and the importance of the work
III. Counsel on both sides have given very considerable attention to the question whether, assuming that there was a stipulation for fixed damages, such provision was not waived by the parties. Had we found that there was a provision for
Supplemental Opinion.
The same kind of plea was made as to the Ellis Lumber Company item, but we find in the record no testimony or concession to support it; and, as it is admitted that this item was, in fact, paid by the defendants, we are disposed to hold that they should have had credit therefor. That this item did not have attention in writing the original opinion is due to the fact that the contest in the court below and upon submission in this court was centered almost exclusively upon the question whether the contract in suit provided for liquidated damages, and these items of counterclaim received only slight and incidental notice at the hands of counsel on either side.
Subject to the modification here suggested, we find nothing in the petition for rehearing to justify us in reopening the case to further consideration. It is therefore ordered that the amount of the verdict directed in favor of the plaintiff and judgment entered thereon be reduced by the sum of $300, with interest at 6 per cent from January 20, 1915, to the date of the entry of said judgment. As thus modified, the opinion heretofore filed will stand. The costs in this court are taxed to the appellants, except the sum of $25, to be paid by the appellee. Petition for rehearing overruled. '