ON MOTION FOR RECONSIDERATION EN BANC
OPINION
Cindy Olson Bourland, Justice
RLJ filed a motion for rehearing, motion for reconsideration en banc, and motion to redesignate our “Memorandum Opinion” as an “Opinion.” We deny RLJ’s motion for rehearing, grant in part and overrule in part RLJ’s motion for reconsideration en banc, and grant RLJ’s motion to redes-ignate our memorandum opinion as an opinion. We withdraw our earlier memorandum opinion and judgment dated January 20, 2017, and substitute the following opinion and judgment in their place.
Appellant Elness Swenson Graham Architects, Inc. (Elness) appeals from a final judgment in favor of appellees RLJ II-C Austin Air, LP; RLJ II-C Austin Air Lessee, LP; and RLJ Lodging Fund II Acquisitions, LLC (collectively, RLJ). RLJ also filed a cross-appeal against Elness. Elness raises five issues on appeal, challenging RLJ’s right to bring suit for breach of contract, the trial court’s admission of certain evidence and award of attorney’s fees to RLJ, the propriety of the jury charge, and the sufficiency of the evidence to support RLJ’s damages. RLJ raises two issues in its cross-appeal, contending that the trial court erred in applying settlement credits to the damages awarded to RLJ at trial and in failing to award attorney’s fees to RLJ for its claims against two other defendants with which it ultimately settled before the end of trial. We will reverse the trial court’s finаl judgment and render judgment that RLJ take nothing.
BACKGROUND
The record shows that this case arises from alleged defects in the design and construction of a hotel near the airport in Austin. RLJ, the owner of the hotel at the time that the alleged defects were discovered, filed suit against multiple defendants involved in the design and construction of the hotel, alleging that the defendants’ work caused the hotel to have a defective foundation that caused building movement and further damage. RLJ had previously purchased the hotel from White Lodging Services Corporation (White Lodging),
Based on other pre-trial rulings by the trial court and non-suits filed by RLJ, RLJ’s only remaining claims as trial neared were breach-of-contract claims against three defendants: Elness, an architectural firm; EBCO General Contractor, Ltd., and EB CO/Warrior Management, LLC (collectively, EBCO), a general contractor; and Terracon Consultants, Inc. (Terracon), a geotechnical engineеring firm. RLJ then entered into a settlement agreement with Terracon before trial and a settlement agreement with EBCO dur
At the close of trial, the jury found that Elness had “fail[ed] to comply with the [contract between Elness and White Lodging] regarding the structural engineering services required by the contract” and awarded RLJ $785,000 in damages. Elness then filed a motion asking the trial court to apply settlement credits to the damage amount based- on the payments RLJ received from its settlements with Terracon and EBCO. The trial court granted Elness’s motion. The parties agreed to submit the issue of attorney’s fees to the trial court, and RLJ submitted evidence of its attorney’s fees in the amount of $1,388,019 for its claims against Elness, EBCO, and Terracon. In the alternative, RLJ requested its fees against Elness only, which it alleged were $920,847. The trial court ultimately awarded RLJ fees in the amount of $901,650.96 for RLJ’s suit against Elness only. In its final judgment, the trial court applied the settlement credits (a total of $1,170,000)' to the amounts awarded in damages and attorney’s fees and ordered that RLJ recover the remaining amount, which was $516,650.96. Both parties appeal from the trial court’s judgment.
DISCUSSION
Elness raises several issues on appeal, and RLJ raises two issues as well as several sub-issues on cross-appeal. We will address these issues in their logical order, which will sometimes require us to turn to an issue on cross-appeal before returning to an issue on appeal.
RLJ’s Capacity to Bring Suit
A. Background
Elness and White Lodging entered into a contract (the hotel contract) in March 2005 in which Elness agreed to provide architectural services for the development of the hotel. The hotel contract contained an anti-assignment provision stating that neither party could assign the contract to another entity without the written consent of the other party. In September 2005, with Elness’s consent, White Lodging assigned the hotel contract to a company called South Ausaircourt (Au-saircourt). In March 2016, RLJ entered into a purchase and sales agreement with several sellers, including Ausaircourt, Whi-teco Industries, and White Lodging, who served as the manager and agent for Whi-teco Industries.
In December 2007, the parties closed on the sale of the hotel. On the same date as the closing, RLJ and Ausaircourt executed an “Assignment and Assumption of Licenses, Permits and Intangibles” (the Assignment). The Assignment assigned Ausairc-ourt’s “interest” in the hotel to RLJ and further stated that “[Ausaircourt] hereby sells, transfers, conveys and assigns to [RLJ] all of [Ausaircourt’s] right, title, and interest in and to all licenses, permits and all other intangible assets relating to the [hotel] (collectively, ‘Licenses’), subject, however, to the terms and covenants of the Licenses and this Assignment.” At some point after RLJ took possession of the hotel, it noticed alleged problems in the hotel’s foundation and eventually filed suit against Elness and other defendants.
After RLJ filed suit, Elness filed traditional and no-evidence summary-judgment motions arguing, among other things, that RLJ had not been validly assigned the hotel contract or a cause of action for breach of the hotel contract and thus could not bring a breach-of-contract suit against Elness. RLJ filed its own partial summary-judgment motion in which it contended that the hotel contract and all causes of action arising from it had been assigned to it in the Assignment. The trial
B. Standard of Review
To prevail on a traditional motion for summary judgment, the movant must show that “there is no genuine issue as to any material fact and the [movant] is entitled to judgment as a matter of law[.]” Tex. R. Civ. P. 166a(c); Browning v. Prostok,
C. Analysis
Elness contends that the trial court erred in determining that RLJ had capacity to bring suit for breach of the hotel contract because, Elness argues, the Assignment did not assign causes of actions under the hotel contract to RLJ. Both the trial court and the parties at times referred to this issue as a challenge to RLJ’s standing rather than its capacity, but all of the arguments made by Elness in the summary-judgment proceedings and on appeal with respect to this issue challenge only RLJ’s privity of contract with Elness, which is a challenge to capacity, not standing.
To recover on an assigned cause of action, the party claiming the assignment occurred must show the existence of a cause of action capable of being assigned
Absent specific circumstances not present in this case, causes of action in Texas are freely assignable. See PPG Indus., Inc. v. JMB/Houston Ctrs. Partners Ltd. P’ship,
In construing a written assignment, an appellate court applies the rules of interpretation and construction applicable to contracts. Commercial Structures & Interiors, Inc. v. Liberty Educ. Ministries, Inc.,
The portion of the Assignment that RLJ relies on in asserting that Ausaircourt assigned causes of actions arising from the contract to RLJ states:
Assignment of Licenses, Permits and Intangibles
[Ausaircourt] hereby sells, transfers, conveys and assigns to [RLJ] all of [Au-saircourt’s] right, title and interest in and to all licenses, permits and all other intangible assets relating to the Property (collectively, “Licenses”), subject, however, to the terms and covenants of the Licenses and this Assignment.
RLJ contends that the phrase “all other intangible assets relating to the Property” includes causes of actions arising from the contract. In interpreting the meaning оf the term “intangible assets,” we first note that neither the term nor each individual word within the term is defined in the Assignment. Thus, we look to the plain, ordinary, and generally accepted meaning of the words. See id. “Intangible property” is defined as “property having no physical substance apparent to the senses: incorporeal property (as dioses in action) often evidenced by documents (as stocks, bonds, notes, judgments, franchises) having no intrinsic value or by rights of action, easements, goodwill, trade secrets.” See Webster’s Third New Int’l Dictiona'ry 1173 (2002) (emphasis added). A “chose in action” is defined as “the right to bring an
In addition to Webster’s, case law also indicates that choses in action are intangible property. See In re Marriage of Malacara,
Elness argues that the assignment of “intangible assets” here was still not sufficient to assign causes of action because “[a] subsequent owner who did not own the property at the time of the injury may only bring suit where the subsequent owner receives an express assignment of the cause of action,” and the provision assigning “intangible assets” was not an express assignment. In support of its argument, Elness cites to a line of cases that require an express assignment for a claim for damages under certain circumstances. See Exxon Corp. v. Emerald Oil & Gas Co., L.C.,
In a letter from the trial court to the parties explaining the trial court’s deci
Admission of Hotel Contract
Elness also contends that the trial court erred in admitting the hotel contract into evidence over Elness’s objections. Elness contends that the trial court
In arguing that the hotel contract is inadmissible hearsay, Elness points out that the witness who testified about the contract was an employee of RLJ and was therefore not a party to the contract and did not have personal knowledge of the terms of the contract. Elness further argues that RLJ failed to establish an exception to the hearsay rule. However, a signed instrument, such as a contract, that creates legal rights is not hearsay because it has legal effect independent of the truth of any statement contained in it. See Kepner-Tregoe, Inc. v. Leadership Software Inc.,
With respect to Elness’s objection based on a lack of proper authentication of the hotel contract, we also conclude that the trial court did not err in оverruling the objection. The witness testified that he was the senior vice-president for design and construction at RLJ. He further testified that his job required him “to review [contracts], to understand them and to execute and administrate them.” He testified that the types of contracts he worked with included “design contracts, construction contracts, project management contracts, [and] construction management contracts.” He further testified that he had been employed by RLJ for the past ten years and was employed there when RLJ purchased the hotel in this case. He testified that it was part of his job to receive all paperwork with regard to the design and construction of the hotel in this case and that he received “plans, specifications, [and] contracts” from White Lodging at the time of purchase. In addition, he testified that the specific contracts he received when RLJ bought the hotel were “the contract for design services and the contract for construction management services.” Later in his testimony, counsel for RLJ handed the witness both purported contracts and asked him to identify them. The witness testified that the exhibit at issue, Exhibit 15, was the agreement between Elness and RLJ regarding the hotel, and that the other exhibit, Exhibit 48, was a construe
Authenticity is a condition precedent to an exhibit’s admissibility. See Tex. R. Evid. 901. Evidence sufficient to support a finding that the matter in question is what its proponent claims satisfies this requirement. See id. R. 901(a). Here, RLJ has consistently claimed that Exhibit 15 is the contract that is the basis of this suit, which is the contract between the owner of the hotel (White Lodging at the time of the agreement) and Elness. Thus, the witness’s testimony that Exhibit 15 portrays what RLJ claims it portrays was sufficient to satisfy the authentication requirement of Rule 901(a). See In re J.P.B.,
We further note that Elness does not dispute that the hotel contract is the contract at issue in this case and that the contract was entered into between White Lodging, the hotel owner at the time of the agreement, and Elness, the architect for the hotel. In fact, a Bates stamp on Exhibit 15 indicates that the document itself was produced by Elness during discovery. See Tex. R. Civ. P. 193.7. Moreover, RLJ elicited further testimony without objection from two experts—a structural geotechnical engineer and an architect—in which the experts also testified that Exhibit 15 portrayed what RLJ claims it portrayed. Specifically, the engineer testified without objection that Exhibit 15 was “the [American Institute of Architects] contract between owner and architect.” The architect also testified without objection that Exhibit 15 was “the agreement between the owner and the architect. It is based on the American Institute of Architects form ... This appears to be the agreement between the owner and the architect for the architect’s services to design this project.”
Because we conclude that the trial court did not abuse its discretion in overruling Elness’s objections to the hotel contract, we overrule Elness’s third issue.
Jury Charge
Elness also asserts that the trial court erred in overruling its objection to one of the liability questions in the jury charge. We review complaints of error in the jury charge under an abuse-of-discretion standard. See Shupe v. Lingafelter,
The portion of the jury charge of which Elness complains is a question asking the jury the following: “Did [Elness] fail to comply with the [hotel contract] regarding the structural engineering services required by the contract?” At the charge conference, Elness objected to the question on the basis that “there is no evidence to support ... the failure to comply with the [hotel contract] regarding structural engineering services.” The trial court overruled the objection, and upon consideration of the issue, the jury answered the question in the affirmative.
On appeal, Elness contends that the trial court erred in submitting the jury question because the hotel contract stated only that Elness’s services would “include” structural-engineering services and did not provide a warranty or guarantee regarding the quality of the services. Elness further contends that the question was erroneously submitted because “RLJ did not plead or prove any theory of respondeat superior or vicarious liability against [Elness] for [the structural-engineering company’s] structural engineering services.”
To preserve error for appeal, the argument made in the trial court must comport with the argument made on appeal. See Aero Energy, Inc. v. Circle C Drilling Co.,
Here, Elness’s argument on appeal does not comport with the objection it raised at trial. An objection that RLJ presented no evidence to show that Elness failed to comply with the ■ structural-engineering services referenced in the hotel contract is an entirely different argument than one asserting that Elness was not required to provide structural-engineering services
Damages Award
Elness also contends that the evidence presented at trial is legally insufficient to support the jury’s award of damages compensating RLJ for the impaired value of the hotel in the amount of $700,000. In conducting a legal-sufficiency review, we review the evidence presented in the trial court in a light most favorable to the jury’s verdict,' crediting favorable evidence if reasonable jurors could and disregarding contrary evidence unless reasonable jurors could not. Del Lago Partners, Inc. v. Smith,
Under a legal-sufficiency analysis, an expert’s opinion may constitute no more than a mere scintilla of evidence if the opinion is not reliable under the same standards that govern admissibility, is speculative or conclusory on its face, or assumes facts contrary to the undisputed facts. See Coastal Transp. Co., Inc. v. Crown Cent. Petroleum Corp.,
In this case, the question submitted tó the jury regarding damages stated the following:
What sum of money, if any, if paid now in cash, would fairly and reasonably compensate [RLJ] for its damages, if any, that resulted from [Elness’s] failure to comply with the [hotel contract] that you found in answer to [the questions about Elness’s liability]?
[[Image here]]
Consider only the following elements of damages, if any, and none other. Answer separately in dollars and cents for damages, if any:
(a) The difference, if any between the value of the hotel as constructed and the value of the hotel had [Elness] complied withthe [hotel contract]. The difference in value, if any, shall be determined as of August 31, 2010.
(b) The reasonable and necessary cost, if any, for barrier remediation that you find is due to [Elness’s] failure to comply.
(c) The reasonable and necessary cost of repairs to the hotel, if any, made through August 31, 2010 that you find is due to [Elness’s] failure to comply.
Elness’s legal-sufficiency challenge pertains only to the jury’s аnswer to subsection (a). All of Elness’s arguments regarding this issue focus on the propriety of the expert’s testimony and report and his opinion about the reduction in the market value of the hotel based on the alleged errors committed by Elness. However, subsection (a) does not ask about differences in market value. In fact, market value is not defined or mentioned at any point in the jury charge. Rather, subsection (a) asks for the difference between the value of the allegedly defectively built hotel and the value of the hotel if it had been constructed properly as set out in the hotel contract. This is a question asking for an amount of benefit-of-the-bargain damages. See Henry S. Miller Co. v. Bynum,
Here, Elness did not object in the trial court to the language of subsection (a), propose different language, or request an instruction related to market value. It objected only on the basis that the evidence was legally and factually insufficient to support the request for damages. Where a party does not complain that the jury charge’s measure of damages was improper or provide a proper measure of damages, we measure the sufficiency of the evidence for damages based on the language in the jury charge that was given. See Romero v. KPH Consolidation, Inc.,
Based on the language that was provided in the jury charge, the record contains evidence other than the expert’s testimony that is legally sufficient to support the jury’s damages award. Specifically, the trial court admitted an exhibit presented by RLJ that included more than one-thousand pages of invoices as well as a summary of the invoices and amounts that showed that RLJ paid more than $1 million after August 31, 2010, to fix the problems associated with the allegedly defective construction and design of the hotel. Two of RLJ’s witnesses testified abоut the exhibit. The first witness, RLJ’s senior vice-president for design and construction, testified that the exhibit included invoices for problems
As stated above, the jury identified the amount of $700,000 as the difference between the value of the hotel as constructed and the value of the hotel had Elness complied with the hotel contract. Also as stated above, the total amount of work done to the hotel after August 31, 2010 (the date the jury was instructed to use to determine its answer) because of problems caused by the allegedly defective foundation wаs identified in the exhibit as more than $1 million dollars. Thus, the jury had sufficient evidence from which to determine benefit-of-the-bargain damages.
Issue on Cross-Appeal: One-Satisfaction Rule
In its first issue on cross-appeal, RLJ contends that the trial court erred in applying the one-satisfaction rule to the jury award and therefore reducing the damages awards by the amounts RLJ received in its settlements with Terracon, the geotechnical engineer, and EBCO, the general contractor. The one-satisfaction rule is “the longstanding proposition that a plaintiff should not be compensated twice fоr the same injury.” Stewart Title Guar. Co. v. Sterling,
The party seeking a settlement credit has the burden to prove its right to such a credit. Utts v. Short,
Here, RLJ asserted in its petition several claims against Elness and -the settling defendants, including breach-of-contract claims against all three defendants, a claim for declaratory relief against Terracon, a breach-of-warranty claim against EBCO, claims for equitable subrogation against all three defendants, and a tort claim for breach of fiduciary duty against EBCO. RLJ pled generally as to all defendants in its request for damages as follows:
As a result of the breaches of contract, breach of fiduciary duties, breach of warranty, tort/negligence breaches, and negligent acts alleged above, Plaintiffs have sustained damages in еxcess of the minimal jurisdictional requirements of this court. The appropriate measure of damages for the breach of contract and breach of warranty claims is the difference in value between the building as constructed and the value of the building had it been designed and constructed pursuant to the respective contracts. In the alternative, the measure of damages is the cost to fully and completely repair the Project.
The measure of damages for the tort/negligence causes of action are all out-of-pocket costs, plus all current and future lost revenue, profits, diminution in value, future repair costs, along with all other direct, special, or consequential damages. Plaintiffs also request that EBCO be required to disgorge and forfeit all fees from the Project, as a result of the breach of its fiduciary duty.
As its final prayer in its petition, RLJ requested “that upon final hearing, [it] have judgment against the Defendants, jointly and severally, for [its] damages, interest, attorneys’ fees, costs, and any other relief to which [it] may be entitled.”
Based on pre-trial rulings and other proceedings, the only remaining defendants and claims as trial neared were breach-of-contract claims against Elness, EBCO, and Terracon. The еvidence presented at trial regarding damages included the invoices discussed above showing work done to the hotel to fix the problems caused by the defective foundation, RLJ’s expert’s testimony about the diminished market value of the property due to the defective foundation, and various other testimony and exhibits evidencing damage to the hotel due to the defective foundation. None of the evidence presented to the jury was apportioned to each defendant that allegedly caused it; all of the evidence focused on the totality of the damage caused to the' hotel. In fact, RLJ’s expert on the diminished market value of the hotel testified on cross-examination that he did not allocate damages among the defendants. Specifically, the following exchange occurred between the expert and Elness’s counsel:
Elness’s Counsel: [Y]our opinions also tell the jury nothing about who, if anybody, was responsible for the diminution in value that the hotel may have experienced, can it?
RLJ’s Expert: That’s correct. I did not try to parse that or allocate that, no, sir.
Elness’s Counsel: So to the extent the geotechnical engineer, Terra-con, is responsible for any reduction in the hotel’s value, you’re not able to parse that out, as you said, from anyone else?
RLJ’s Expert: I am not.
After the jury returned its verdict, Elness filed a motion requesting that the trial court apply the one-satisfaction rule by applying settlement credits to the jury’s damage award based on the settlement agreements RLJ made with EBCO and Terracon. Elness provided copies of the settlement agreements, which indicate that EBCO agreed to pay RLJ $1.1 million and Terracon agreed to pay RLJ $70,000. After Elness satisfied its burden to provide evidence of the settlement agreements and amounts, RLJ had the burden to show that the settlement amounts were apportioned to separate rather than joint damages. Casteel,
However, the settlement agreement’s language does not establish an allocation of damages associated with each defendant’s liability. As explained above, all of RLJ’s
Because RLJ failed to apportion damages to each defendant, the trial court properly applied the total of the two settlement amounts, which was $1,170,000, to the jury’s awards of damages. See Ellender,
In its second sub-issue, RLJ contends that the jury in this case could not have awarded damages for an “indivisible injury” because RLJ’s counsel argued in closing arguments that the jury should reduce its awards by twenty percent due to the other defendants’ roles in causing the defective hotel and because the question posed to the jury specifically asked for the amount that would compensate RLJ
In its third sub-issue, RLJ asserts that the one-satisfaction rule applies only to tort cases, not breach-of-contract cases. RLJ acknowledges that several cases, including cases from this Court, explicitly state that the application of the one-satisfaction rule is not limited to tort cases but argues that “the cases suggesting tort liability is not necessarily required are distinguishable in light of a complete analysis of the authority relied upon to make that suggestion.” We are unpersuaded' by RLJ’s argument. We have already determined that the one-satisfaction rule can apply to breach-of-contract cases. Specifically, in Galle, we stated, “In cases where [the statutory scheme for application of the one-satisfaction rule in tort cases] or another settlement credit scheme does not apply, the ‘one-satisfaction’ rule may require a trial court to reduce a damage recovery based on a settlement.”
In its fourth sub-issue, RLJ argues that the application of the one-satis
RLJ cites to only one case for the proposition that Section 16’s reference to “laws” includes judicial decisions. See Fairfield Ins. Co. v. Stephens Martin Paving, LP,
In its fifth sub-issue, RLJ asserts that Elness waived the right to seek the application of the one-satisfaction rule. Specifically, RLJ argues that Elness waived the application of the rule because Elness failed to (1) specially except to RLJ’s failure to allocate damages, (2) request a jury question or instruction requiring damages allocation, and (3) plead the one-satisfaction rule as an affirmative defense. Within this sub-issue, RLJ also contends that “the post-verdict assertion of the one [satisfaction] rule is also precluded by laches.”
We note at the outset that it was RLJ’s burden, as the plaintiff in a breach-of-contract suit, to establish damages as a result of Elness’s breach of the hotel contract in order to be entitled to damages from Elness. See Emerson Constr. Co. v. Ranger Fire, Inc., No. 03-09-00567-CV,
Regarding RLJ’s first argument—that Elness was required to specially except tо RLJ’s failure to allocate damages in its
We also reject RLJ’s second argument—that Elness waived its right to seek the application of the one-satisfaction rule because it did not request a jury question or instruction about damages allocation. Elness was not required do so in order to assert the one-satisfaction rule. See National City Bank of Ind. v. Ortiz,
We further reject RLJ’s third argument—that Elness waived its right to seek the application of the one-satisfaction rule by failing to plead the rule as an affirmative defense—as Elness was not required to plead the rule as an affirmative defense in order to seek application of it. See Ortiz,
Regarding RLJ’s final argument—that Elness’s assertion of the one-satisfaction rule was precluded by laches— we are likewise unpersuaded. Laches is an equitable remedy that prevents- a plaintiff from asserting a claim due to a lapse of time. Green v. Parrack,
However, as we stated above, it was RLJ’s burden to prove damages attributable to Elness due to Elness’s alleged breach of the hotel contract. We further note that Elness stated in its Answer that:
[ P]ursuant to Chapter 33 of the Texas Civil Practice and Remedies Code, Defendants are entitled to a credit for any settlement Plaintiffs receive from any other person or entity. If Plaintiffs settle with any other person or entity, thenDefendants reserve the right to make a written election of credit for settlement under [Chapter 33] of the Texas Civil Practice and Remedies Code.
Although Elness referenced only the statutory authority for the application of settlement credits for torts, the reference was nevertheless some notice that Elness intended to assert the one-satisfaction rule if RLJ settled with other defendants and that RLJ should be prepared for such an event. Because RLJ has not shown that laches applies under the circumstances of this case, we reject this argument,
Given the foregoing, we conclude that the trial court did not err in applying the one-satisfaction rule in this case, and we overrule this issue. See Ellender,
Attorney’s Fees Awarded to RLJ
Elness challеnges the trial court’s award of attorney’s fees to RLJ, arguing that the trial court erred in awarding RLJ its fees because RLJ did not recover any damages after the application of the settlement credits and was therefore not a prevailing party under Chapter 38 of the Texas Civil Practices & Remedies Code. See Tex. Civ. Prac. & Rem. Code § 38.001, Generally, we review a trial court’s award of attorney’s fees under an abuse-of-discretion standard. See Ridge Oil Co. v. Guinn Invs., Inc.,
Attorney’s fees are recoverable in a suit only if they are authorized by contract or statute. Tucker v. Thomas,
Elness argues that RLJ was not entitled to attorney’s fees from Elness because, although RLJ was awarded damages by the jury, it did not actually recover damаges due to the application of the settlement credits and was thus not a “prevailing party.” Because of Texas Supreme Court precedent on the recovery of attorney’s fees, we must agree. See Intercontinental Grp. P’ship v. KB Home Lone Star L.P.,
The supreme court explicitly stated in Intercontinental that it was following precedent from the United States Supreme Court and quoted the following provisions from a U.S. Supreme Court case, which held that the plaintiff “prevailed” in the suit and was therefore entitled to attorney’s fees because he was awarded one dollar in damages:
[ T]o qualify as a prevailing party, a ... plaintiff must obtain at least some relief on the merits of his claim. The plaintiff must obtain an enforceable judgment against thе defendant from whom fees are sought, or comparable relief through a consent decree or settlement. Whatever relief the plaintiff secures must directly benefit him at the time of the judgment or settlement. Otherwise the judgment or settlement cannot be said to “affect the behavior of the defendant toward the plaintiff.” Only under these circumstances can civil rights litigation effect “the material alteration of the legal relationship of the parties” and thereby transform the plaintiff into a prevailing party. In short, a plaintiff “prevails” when actual relief on the merits of his claim materially alters the legal relationship between the parties by modifying the defendant’s behavior in a way that directly benefits the plaintiff. A judgment for damages in any amount, whether compensatory or nominal, modifies the defendant’s behavior for the plaintiffs benefit by forcing the defendant to pay an amount of money he otherwise would not pay.
Id. at 654 (quoting Farrar v. Hobby,
The language from Intercontinental that we hаve emphasized above makes it clear that we must look to the judgment, not preliminary verdicts or rulings, as the critical component of our analysis regarding whether a party “prevailed” in a suit and is thus entitled to attorney’s fees. Other cases from this Court decided after Intercontinental confirm this conclusion. See Continental Healthcare, Inc. v. Remedy Therapy Staffing, PLLC, No. 03-14-00464-CV,
Taking Texas Supreme Court precedent into account, as we must, the circumstances of this case compel us to reach the conclusion that the trial court erred in awarding attorney’s fees to RLJ. See id. at 652; Green Int’l,
Issue on Cross-Appeal: Segregation of Attorney’s Fees
In its second issue on cross-appeal, RLJ contends that the trial court erred in segregating the attorney’s fees “expended on RLJ’s claim against [Elness] from those on its claims against [EBCO and Terracon].” Because we have determined that RLJ was not entitled to any attorney’s fees from Elness, we need not reach this issue. See Tex. R. App. P. 47.1.
CONCLUSION
We reverse the trial court’s final judgment and render judgment that RLJ take nothing.
Reversed and Rendered
Chief Justice Rose, Not Participating
Notes
. The purchase agreement listed Whiteco Industries as the seller and White Lodging as the manager and agent of Whiteco Industries. However, based on the parties' briefs and the issues on appeal, we need not address Whi-teco Industries’ involvement in the case and instead refer, as do the parties, to White Lodging as the initial owner and developer of the hotel.
. We also note that in its answer to RLJ’s petition, Elness filed a verified denial of RLJ’s capacity to file suit based on an alleged lack of a valid assignment, which is a requirement in order to challenge a plaintiff’s capacity to bring suit. See Tex. R. Civ. P. 93(1), (2).
, Elness also raises an argument that an anti-assignment clause in the hotel contract prohibited an assignment of the contract itself (as opposed to a cause of action under the contract) but acknowledges that "assignment of the contract itself is irrelevant to assignment of the ... cause of action,” and raises the' issue "in an abundance of caution” due to certain statements made by the trial court. Because we hold that RU showed as a matter of law that Ausaircourt assigned it a cause of action for breach of the hotel contract, we need not address the issue of whether an anti-assignment clause in the hotel contract prohibited an assignment of the contract under the facts of this case. Whether Ausaircourt validly assigned the contract itself does not affect our conclusion regarding the assignment of a cause of action under the contract because Texas law distinguishes between a contracting party's ability to assign rights under a contract containing an anti-assignment clause and that same party’s ability to assign causes of action arising from the breach of that contract. See Tex. Bus. & Com. Code § 2.210(d); Dearborn Stove Co. v. Caples,
. The witness testified as though RU were a party to both contracts, but the record shows that the exhibit at issue is an agreement between Elness and White Lodging, not Elness and RLJ, and that the other exhibit is an agreement between Elness and EBCO, not Elness and RLJ. As we stated above, White Lodging originally owned the hotel, and RLJ owned it at the time of trial. Read in context, the witness seems to have misspoken when he stated RLJ was a party to the contracts rather than White Lodging and EBCO. However, we need not address how the witness’s misstatements affected the authentication of the contract because Elness does not raise the issue on appeal and because all of the other circumstances surrounding the contract establish that the contract was properly admitted into evidence in this case.
. As set forth above, the jury assigned the amount of $70,000 under subsection (b) of the damages question as the reasonable and necessary cost for barrier remediation due to Elness's failure to comply with the hotel contract and $15,000 under subsection (c) as the reasonable and necessary cost of repairs to the hotel made through August 31, 2010 due to Elness’s failure to comply with the hotel contract. The question at issue referred only to benefit-of-the-bargain dаmages as of August 31, 2010. Although Elness does not challenge the jury’s answers to subsections (b) and (c), we note that the same exhibit that showed the cost of work done to the hotel due to Elness's failure to comply with the hotel contract supported the jury’s answers to all of the subsections because the invoices totaled more than one-million dollars. Further, we need not address whether the use of August 31, 2010, as a valuation date was proper, as Elness did not object to the use of this date in the jury charge and did not request a different date.
. RLJ notes in its brief that it "was not given the opportunity to segregate or apportion damages to satisfy the trial court’s reasoning before the case was submitted to the jury,” but does not cite to any portion of the record supporting this assertion.
. To the extent that our holding in this case conflicts with CTTI Priesmeyer, Inc. v. K & O Ltd. P’ship,
. We need not address the propriety of the application of the settlement credits to the attorney’s fees award as neither party raises the issue.
. We further note that there is a line of cases from intermediate courts of appeals dated before Intercontinental that hold that plaintiffs in DTPA suits who receive a jury award for damages are not entitled to attorney’s fees if they have already settled for an amount greater than the jury award against the non-settling defendant. See Imperial Lofts, Ltd. v. Imperial Woodworks, Inc.,
