Ellsworth Paulsen Construction Co. v. 51-SPR, L.L.C.Ellsworth Paulsen Construction Co. v. 51-SPR, L.L.C.
OPINION
¶ 1 This ease arises from a real estate project gone bad. We have before us the appeal and cross-appeal from several aspects of the trial court’s rulings. We reverse in part and affirm in part, and remand for additional proceedings.
BACKGROUND
¶2 Plaintiff Ellsworth Paulsen Construction Company (Ellsworth) entered into two construction contracts with Guy Hatch and his company, Broadstone Investments, L.C. (Broadstone), under which Ellsworth agreed to act as general contractor for the construction of two commercial buildings (Building I and Building II) as part of a project in American Fork, Utah (the Northshore Prop
¶ 3 Apparently, however, Ellsworth knew nothing about SPR’s involvement in the project, having no direct dealings with SPR until Hatch disappeared toward the end of construction and Ellsworth sought payment on outstanding invoices that Hatch had left unpaid. 1 Until that time, Ellsworth had dealt exclusively with Hatch as the owner of Broadstone, Broadstone being designated under the Agreement as the project manager in charge of supervising construction on the Northshore Property.
¶4 To fund the construction, Broadstone had entered into two separate construction loan arrangements with Central Bank, which Hatch and a co-member of Broadstone, Dan Parkinson, personally guarantied. Under the Agreement, Broadstone was “in charge of obtaining remaining needed construction financing and institutional permanent financing.” The Agreement also required that Broadstone was to “provide financing for needed construction monies for the office building[s] and remaining cash needs of the project” beyond SPR’s $2.9 million investment. The Agreement also expressly provided that “Guy Hatch will guaranty such financing.”
¶ 5 Prior to disappearing, and toward the end of construction on the Northshore Property, Hatch had become suspiciously slow in paying Ellsworth’s invoices, apparently due to the fact that the construction loan funds were almost exhausted. At least according to SPR, Hatch had been drawing on the construction loan funds and using them in other projects unrelated to the Northshore Property. Despite not being paid, Ellsworth continued its work. Toward the end of the project, with the construction loan funds apparently exhausted and Hatch having disappeared, Ellsworth had nowhere to send its final three draw requests.
¶ 6 Throughout the earlier course of construction, Ellsworth would submit draw requests to Central Bank either directly or through Hatch. Once the draws were approved, Central Bank would then issue cheeks to Ellsworth for its work and for the work of its subcontractors. Each check bore a lien waiver provision on the reverse side of the instrument. 2 The trial court ruled on summary judgment that the lien waivers were valid and enforceable, and therefore cut off any lien rights through the date of each draw request, which is the date the draw was requested and not the date the check was received or cashed. In considering a subsequent motion for summary judgment, however, the trial court ruled that the indemnity provision within the lien waivers was inapplicable, invalid, and unenforceable, and that Ellsworth was not responsible to indemnify SPR against any subcontractor claims.
¶ 8 Ellsworth brought additional claims against Hatch and Broadstone for, among other things, failure to pay amounts due under two construction contracts entered into pursuant to the Agreement. Ellsworth brought those same claims against SPR on the theory that SPR was in a joint venture relationship with Hatch and Broadstone in the development of the Northshore Property. SPR defended against these claims by initiating, in a separate proceeding which was later consolidated into this lawsuit, an action to quiet title in Building I and Building II. SPR also brought claims against Ellsworth under Utah’s abusive hen statute, see Utah Code Ann. § 38-1-25 (2005), for including in its lien claim $78,000 that SPR asserted was attributable to an unrelated project on which Hatch and Ellsworth were collaborating without SPR’s involvement.
¶ 9 A three-day bench trial was held on the issues not previously decided on summary judgment. At the conclusion of the trial, the court ruled in Ellsworth’s favor on its lien and breach of contract claims in the amount of just over $721,000. Although it disallowed the claim for $78,000, the trial court denied SPR’s related abusive lien argument, holding that Ellsworth had acted in good faith in including the $78,000 in its lien claim and had not intended to exact more from SPR than was due. The trial court also granted Ells-worth attorney fees as the prevailing party under the lien statute, but refused to award Ellsworth pre-judgment contractual interest on its final three draws because Ellsworth never submitted those final draws and, thus, the court could not fix a date at which the contract was breached and from which interest began to accrue. Both sides now appeal various aspects of the trial court’s resolution of this complicated dispute.
ANALYSIS
I. Joint Venture Ruling
¶ 10 SPR argues that the trial court erred in concluding, on partial summary judgment, that it was in a joint venture relationship with Broadstone and Hatch. Specifically, SPR attacks the trial court’s conclusion that SPR had a duty to share in the losses of the Northshore Property. Because there is a genuine issue of material fact regarding the key issue of whether SPR agreed to share losses with Broadstone and Hatch, we reverse the trial court’s partial summary judgment ruling.
¶ 11 The “duty to share in any losses” is one of the elements of a joint venture relationship that the Utah Supreme Court has deemed to be “essential” to the existence of such a relationship.
Bassett v. Baker,
¶ 12 Ellsworth argues that in such instances a duty to share losses may be inferred from an agreement or from the nature of the parties’ relationship, especially when all the other elements of a joint venture relationship are present. While the Utah Supreme Court has indicated that “the agreement to share losses need not necessarily be stated in specific terms ... to permit [a] court to infer that the parties intended] to share losses as well as profits,”
Bassett,
¶ 13 The trial court concluded that “[t]he terms of the Agreement, SPR’s ownership interest
in
the Project, and SPR’s undisputed actions all gave rise to SPR’s duty to share in any losses which may be sustained by the Project.” Ellsworth argues that the trial court properly inferred from the Agreement, SPR’s undisputed actions, and the other undisputed facts that SPR had the duty to share in losses. We disagree because when “we view the facts and all reasonable inferences drawn therefrom in the light most favorable to [SPR],” there is a genuine dispute of fact on a material issue, which precludes summary judgment.
Surety Underwriters v. E & C Trucking, Inc.,
¶ 14 “ ‘A genuine issue of fact exists where, on the basis of the facts in the record, reasonable minds could differ’ on any material issue.”
Ron Shepherd Ins., Inc. v. Shields,
¶ 15 Although the trial court regarded Chi-mento’s affidavit testimony as nothing more than “bald assertions” and “conclusory allegations” that did not “create any genuine issue of material fact” because they were “sharply contradicted by both the terms of the Agreement and the undisputed facts,” we conclude that Chimento’s affidavit
did
create an issue of fact concerning the duty to share losses. Indeed, when Chimento’s affidavit testimony is viewed together with the Agree
¶ 16 Chimento’s affidavit asserts that under the Agreement the parties intended to make Hatch and Broadstone solely responsible for “all expenses, costs, losses, and risks associated with the Northshore project” and did not intend to make SPR liable for any losses, liabilities, or responsibilities, meaning that SPR stood only to lose its capital investment in the Northshore Property. The provisions in the Agreement that expressly release SPR from all obligations arising by way of any note or guaranty for construction financing and instead place the sole obligation of obtaining and repaying construction financing and other cash needs of the project on Broadstone and Hatch, at the very least give rise to the inference that SPR did not agree to share in other financial obligations, i.e., the net operating losses of the North-shore Property. Additionally, the Agreement’s terms guarantying SPR “a 10% return on its capital commencing December 1, 2000,” with Broadstone and Hatch guarantying to even “contribute any and all sums to the project needed for payment of such return,” support Chimento’s affidavit and the inference that even if the project lost money, Broadstone alone bore the responsibility to contribute funds to cover the losses and to ensure that SPR, as an investor, received its guarantied return.
¶ 17 Other terms of the Agreement that the trial court interpreted as having “essentially put SPR’s $2.9 million immediately at risk should the venture completely fail” and making “SPR one-half owner of a tenancy in common with all the accompanying liabilities of a real property owner,” when viewed in their proper light on summary judgment, together with Chimento’s affidavit, also give rise to equally plausible inferences that contradict the trial court’s conclusion that SPR agreed to share in the losses of the project. 7 In addition, SPR’s “undisputed actions” on which the trial court relied to conclude SPR was not acting as a mere investor — i.e., “when it agreed with Central Bank in April, 2002 to guarantee ‘Broadstone’s’ [$]4.3 million construction loans” and when it “voluntarily conveyed the Project property to Broadstone for one day in January 2001 so that Broadstone could secure additional financing for the Project” 8 — when viewed in the light most favorable to SPR, also support the assertion that SPR may not have agreed to share in losses.
¶ 18 While we do not suggest that the inferences the trial court drew from the Agreement and other evidence before it are necessarily incorrect, the fact that there are other equally plausible inferences to be drawn from the evidence manifests that summary judgment should not have been granted.
See Goodnow v. Sullivan,
[a] party opposing the motion is required only to show that there is a material issueof fact. Affidavits and depositions submitted in support of and in opposition to a motion for summary judgment may be used only to determine whether a material issue of fact exists, not to determine whether one party’s case is less persuasive than another’s or is not likely to succeed in a trial on the merits.
Lamb v. B & B Amusements Corp.,
II. Timeliness of Ellsworth’s Mechanic’s Lien
¶ 19 SPR argues that the trial court erred when it determined on summary judgment that Ellsworth’s mechanic’s lien was timely filed on November 16, 2001. Specifically, SPR claims the trial court erred in concluding that there was nontrivial, substantial work performed on Building I and Building II in September 2001 and October 2001 at “the request of Broadstone and/or SPR” and that the ninety-day filing period did not begin to run until that work was completed. SPR asserts that there were, on the record before the court, genuine issues of material fact concerning whether the Building I contract was completed by May 2001, whether the Building II contract was completed by July 2001, and whether any work performed after these dates fell within the scope of the original building contracts and was substantial enough to preclude the start of the ninety-day filing period. Likewise, SPR contends there is a question of material fact concerning when the owner’s acceptance of Ellsworth’s work occurred. We agree with SPR that summary judgment on these issues was also improperly granted.
¶20 “Utah courts have articulated a two-prong test” for determining whether a mechanic’s lien has been timely filed.
Interiors Contracting, Inc. v. Smith, Halander & Smith Assocs.,
¶ 21 While it appears to be undisputed that some work continued on Building I and Building II after May 2001 and July 2001, respectively, both parties presented evidence on summary judgment that supported conflicting completion dates and cast doubt on the scope of the work performed on or after August 15, 2001 — ninety days before Ells-worth filed its mechanic’s lien. When we view all of the facts and reasonable inferences to be drawn therefrom in the light most favorable to SPR’s position,
see Surety Underwriters v. E & C Trucking,
¶ 22 The fact that SPR can point to documents wherein Ellsworth certified that the
¶ 23 In addition, evidence that Ellsworth certified that the Building II contract was 100% complete in July 2001 and that its subcontractors’ invoices reflecting that they had completed all their work by July 2001— even though the same subcontractors performed more work on Building II after July 2001 — raises a genuine issue of material fact concerning when substantial completion occurred. This determination is especially unclear in light of evidence SPR advanced to show the minimal value of the work performed after July 2001.
¶ 24 Ellsworth asserts that SPR’s contentions should fail “in the face of compelling — if not overwhelming — evidence that contravenes [SPR’s] conclusory contentions” and “in the face of extensive testimony by subcontractors and [Ellsworth] that they were all performing thousands — perhaps tens of thousands — of dollars of work on the project during the months of August, September and October.” Ellsworth’s assertions are unavailing, however, since summary judgment cannot be granted based on the credibility and weight of the parties’ respective evidence.
See Lamb v. B & B Amusements Corp.,
III. Ellsworth’s Inclusion of $78,000 in its Lien Claim
¶25 Both parties appeal the trial court’s ruling concerning $78,000 Ellsworth included in its lien claim. Ellsworth contends that since it was entitled to claim the $78,000 as part of its lien claim, the trial court erred in not awarding the $78,000 as part of its lien and contract claims. SPR contends that the
A. Ellsworth’s claim to the $78,000
¶ 26 Ellsworth argues that the trial court erred by not holding SPR liable to pay Ells-worth the $78,000, advancing several theories on appeal in support of its contention. We conclude, however, that the trial court was correct. Given the trial court’s findings and conclusions, Ellsworth is not entitled to recover the $78,000 under any of the theories advanced. The trial court explicitly found that Ellsworth paid the $78,000 to Hatch for work on the proposed development of a different piece of property, that it did not relate to Hatch’s agreements with Mr. Chimento and SPR for the construction of Building I and Building II, and that Broadstone was responsible for repaying the amount to Ells-worth. Ellsworth has made no earnest attempt on appeal to challenge the trial court’s findings concerning the $78,000.
See Chen v. Stewart,
¶27 The plain language of the Mechanics’ Liens statute makes clear that Ells-worth was only entitled to record or file a “lien upon the property upon or concerning which [it has] rendered service, performed labor, or furnished or rented materials or equipment for the value of the service rendered, labor performed, or materials or equipment furnished or rented.” Utah Code Ann. § 38-1-3 (2005). Although Ellsworth would be entitled to file a lien for services rendered even if the planned development never occurred, the lien must nevertheless be filed against “the property concerning which [it] has rendered professional service.”
Zions First Nat’l Bank v. Carlson,
¶28 Ellsworth insists, however, that the trial court’s findings do not prevent the conclusion that when Hatch signed a change order indicating that the $78,000 was to be part of the Building II contract, Hatch made the $78,000 a “partnership” debt, for which SPR should be equally responsible. But even assuming that a joint venture existed between Hatch and SPR, the trial court’s findings prevent imposing liability on SPR for the change order.
¶ 29 It is true that “[e]very partner is an agent of the partnership for the purpose of its business, and the act of every partner ... binds the partnership,” Utah Code Ann. § 48-1-6(1) (2002), but that binding authority does not extend to “[a]n act of a partner which is not apparently for the carrying on of the business of the partnership in the usual way.”
Id.
§ 48-1-6(2). The business of this alleged partnership or joint venture was the development of the Northshore Property. And the findings are clear that the $78,000 was unrelated to the Northshore Property and not part of the Agreement between Hatch and SPR. By the trial court’s findings, then, the $78,000 was for use on another of Hatch’s own business undertakings, completely unrelated to the Northshore Property. Absent some showing that the trial court’s findings in this regard were incorrect and absent an affirmative finding that the $78,000 was indeed related to the business of this alleged partnership, Hatch’s act of signing a change order in an apparent attempt to make his unrelated obligation part of the partnership business has no binding effect on SPR under partnership law.
12
See id.
We
B. Violation of Utah’s Abusive Lien Statute
¶ 30 The question remains whether the trial court properly concluded that Ells-worth did not violate Utah’s abusive lien statute by including $78,000 as part of its lien claim when the trial court ultimately held that Ellsworth was not entitled to do so. The trial court concluded that although Ells-worth was not entitled to include the $78,000 amount in its lien claim, it “acted in good faith in claiming the $78,000.” The court found that Ellsworth had filed the lien pursuant to Hatch’s change order and Hatch’s instructions, and that Ellsworth did not cause the lien to be filed with an intent to cloud the title of the property, to exact more than it believed was due, or to procure an unjustified advantage. SPR contends the abusive lien statute does not condition liability on a lien claimant’s subjective belief that it is seeking more than is due and does not require a showing that the lien claimant specifically intended to exact more than is due. Thus, SPR contends that Ellsworth should have been penalized under the abusive lien statute for including $78,000 more in its lien claim than it was legitimately owed for work on the Northshore Property. We disagree.
¶ 31 The abusive lien statute provides that “[a]ny person entitled to record or file a lien under Section 38-1-3 is guilty of a class B misdemeanor who intentionally causes a claim of lien against any property, which contains a greater demand than the sum due to be recorded or filed” and the person does so “(a) with the intent to cloud the title; (b) to exact from the owner or person liable by means of the excessive claim of lien more than is due; or (c) to procure any unjustified advantage or benefit.” Utah Code Ann. § 38-1-25(1) (2005). 13 The statute is peculiarly phrased, in that while the language of subsection (1) provides that the lien claimant must intentionally cause a lien to be filed that demands more that the lien claimant is due, one of the subsections provides a further requirement concerning mental state while the other two do not. Thus, subsection (l)(a) speaks of “the intent to cloud the title,” while subsections (l)(b) and (l)(c) do not further prescribe what culpable mental state the lien claimant must have with respect to filing the lien “to exact ... more than is due” or “to procure any unjustified advantage or benefit.” Id. But the abusive lien statute is a criminal statute and it does not “clearly indicate[ ] a legislative purpose” to impose strict liability for the crime. Utah Code Ann. § 76-2-102 (2003). As a result, the default culpable mental state of “intent, knowledge, or recklessness shall suffice to establish criminal responsibility” under the last two variants of the abusive lien statute. 14 Id.
¶ 33 Ellsworth relied on Hatch’s signed change order referencing the Northshore Property as providing a contractual basis under which it could include the $78,000 in its lien claim on the Northshore Property. While Ellsworth’s reliance ultimately has proven to be incorrect, it at least provides evidence that tends to support the finding that Ellsworth included the amount based on what it thought was a legitimate and binding change order and did not intentionally, knowingly, or recklessly include the amount to exact more than was due.
¶ 34 Although SPR points to other evidence giving rise to inferences about what Ellsworth knew or did not know about the $78,000, we are not convinced that the trial court’s finding was clearly erroneous. Thus, although Ellsworth “intentionally cause[d] a claim of lien ... which contained] a greater demand than the sum due to be recorded or filed,” it did not do so with the requisite culpable mental state to cloud the title, to exact from the owner more than was due, or to procure some other unjustified advantage.
IV. Lien Waivers
¶ 35 We next consider two aspects of the applicability of the hen waivers at issue in this case. With respect to both, we remand for further consideration.
A. Application of Lien Waivers
¶ 36 SPR argues that the trial court erred by ultimately not applying the lien waivers after correctly concluding before trial that the lien waivers were valid and enforceable. 15 We admit we are slightly puzzled by the trial court’s handling of the lien waiver issue, especially since neither party points us to a clear finding or explanation concerning why none of the lien waivers, held to be valid and enforceable in the abstract, were made applicable by the trial court. Indeed, both sides assert different draw dates that are supposed to have cut off Ellsworth’s lien rights for work performed prior to those dates. SPR asserts dates (April 11 and June 25, 2001) that if found to be the draw dates would indeed waive Ellsworth’s right to file a lien for some portions of the work it claimed in its mechanic’s lien. The draw dates on which Ellsworth relies (each sometime in February 2001) would support the conclusion that no portion of its lien claim was waived by the April and June checks to which SPR cites in support of its position.
B. Indemnity, Warranty, and Guaranty Language of the Lien Waiver
¶ 38 We reverse the trial court’s summary judgment ruling that, although the lien waivers were otherwise valid and enforceable, the indemnity language in the lien waiver provisions was “inapplicable, invalid and unenforceable.” We give no particular deference to a trial court’s interpretation of unambiguous contract language on summary judgment.
See Meadow Valley Contrs., Inc. v. Transcontinental Ins. Co.,
¶ 39 Here, as part of the valid lien waiver provisions, the applicability of the indemnity and guaranty language hinges on the relevant draw dates for each check, as is so with the specific lien waiver language itself. Under the plain language of the lien waiver provisions, when construed together as a whole, the “[playee warrants and guarantees” that through the draw dates “payment in full has been made ... to the suppliers of all labor and materials to the Property incurred at the insistence of payee.” To the extent “any liens or claims” are “made against the Property by any supplier of labor [or] material” provided up through the relevant draw date, the payee, by signing the lien waiver provision, “agrees to indemnify and hold harmless the owner of the Property ... from any loss, claims, or expenses incurred by [the Property owner] by reason of or rising out of any liens or claims made against the Property.” Thus, as with the question of whether Ellsworth has waived any amounts contained in its mechanic’s lien claim, whether Ellsworth must indemnify SPR for any of the lien claims brought against it by Ells-worth’s subcontractors and suppliers depends on whether any of those liens arose out of work performed before the draw date of a specific check that Ellsworth signed and also guarantied that it had paid. As to any such lien or claim, Ellsworth would be responsible for the payment by way of its guaranty and its agreement to indemnify the Property owner therefore. Accordingly, we remand for the trial court to make any additional findings necessary to determine the effect, if any, the indemnity, warranty, and guaranty language has on the liens filed against the Northshore Property and to determine any relief to which SPR may be entitled under those provisions.
V. Prejudgment Interest
¶ 40 Ellsworth appeals the trial court’s prejudgment interest determination. While we need not address this issue as our decision today reverses the final judgment in several respects and remands several issues for the trial court’s further consideration, we nonetheless choose to treat the prejudgment interest issue here because it could well arise again during the proceedings on remand.
See Bair v. Axiom Design, L.L.C.,
¶ 41 Ellsworth argues that the trial court erred in refusing to award Ellsworth interest
¶ 42 Ellsworth’s contention that the trial court’s ruling appears to blur the distinction between the requirements for receiving an award of contractual interest and those for receiving an award of prejudgment interest as a matter of damages is well taken.
See Consolidation Coal Co. v. Utah Div. of State Lands & Forestry,
¶ 43 The difficulty we have here with the trial court’s treatment of the prejudgment interest issue is that, while explicitly holding that Ellsworth was “entitled to pre-judgment contractual interest on its breach of contract claim as requested,” the trial court nevertheless refused to award interest attributable to the three payment applications. It is not clear whether the trial court did so because under the general rules governing prejudgment interest the amounts due on the three payment applications were not liquidated, or whether the trial court determined that under the terms of the contract Ellsworth was not entitled to contractual interest on the three payment applications because it never submitted them for payment.
¶ 44 It may very well be that under the terms of the contract Ellsworth is not entitled to interest on the payment applications because they were never submitted. The contract states, with our emphasis, that interest is to accrue at “[t]en percent (10%) per annum thirty (30) days
after the date of the Invoice for payment.”
Since it was undisputed that Ellsworth never submitted the three applications, there appears to be no “date of the Invoice for payment” that marks the beginning of the thirty-day period before interest would begin to accrue, which under the plain language of the contract suggests that contractual interest on those applications would be inappropriate.
See Consolidation Coal,
VI. Attorney Fees
¶45 SPR appeals from the trial court’s award of attorney fees below, and Ellsworth
¶ 46 It is clear that Utah law requires the prevailing party, and ultimately the court, to allocate the prevailing party’s attorney fees among those claims for which it is entitled to an award of attorney fees and those for which it is not.
See A.K. & R. Whipple Plumbing & Heating v. Aspen Constr.,
¶ 47 While it is true that under the mechanic’s lien statute Ellsworth is not entitled “to attorney fees incurred in pursuing its nonlien claims which were ‘completely separate,’ ”
American Rural Cellular, Inc. v. Systems Commun. Corp.,
CONCLUSION
¶48 We remand this matter to the trial court for further consideration in accordance with this opinion.
¶ 49 WE CONCUR: JUDITH M. BILLINGS and CAROLYN B. McHUGH, Judges.
Notes
. According to SPR, Hatch left Utah for Hawaii, where he apparently remains to this day.
. The lien waiver provisions read, in pertinent part:
In consideration of payment of this check, payee by negotiating tins check waives, releases, and relinquishes all right of lien or claims payee may have up to the date of the draw request described on the reverse side hereof (the "Draw Date"), upon the property described on the reverse side hereof (the "Property”). The payee certifies that this check is payment for labor and materials that were actually performed upon and furnished to the Property. Payee warrants and guarantees under penalty of fraud that payment in full has been made by payee to the suppliers of all labor and materials to the Property incurred up to the Draw Date at the insistence of payee. Payee agrees to indemnify and hold harmless the owner of the Property and Central Bank or its assigns, from any loss, claims, or expenses incurred by them by reason of or rising out of any liens or claims made against the Property by any supplier of labor [or] material at the insistence of payee.
. Shortly before Hatch disappeared, SPR learned of Hatch's purported misuse of the Northshore Property construction funds, SPR confronted Hatch, and Hatch agreed to relinquish to SPR Broadstone’s one-half interest in the property. By the time SPR assumed control of the North-shore Property, Broadstone had defaulted on the two construction loans.
. Several of Ellsworth's subcontractors also filed mechanics’ liens and the trial court granted summary judgment in favor of the subcontractors who had filed liens. To avoid foreclosure of those liens, SPR apparently paid those claims, leaving only Ellsworth's lien and contract claims remaining to be resolved. Thus, this appeal involves only Ellsworth's claims against SPR.
.The Utah Supreme Court has stated the "essential” elements of the joint venture relationship as follows:
The parties must combine their properly, money, effects, skill, labor and knowledge. As a general rule, there must be a community of interest in the performance of the commonpurpose, a joint proprietary interest in the subject matter, a mutual right to control, a right to share in the profits, and unless there is an agreement to the contrary, a duty to share in any losses which may be sustained.
Bassett v. Baker,
. It appears, then, that in most instances where there is no express agreement between parties concerning the sharing of losses, the question of whether one has a duty to share in losses will ordinarily be a question of fact — just as the overarching question of "[w]hether a joint venture exists is ordinarily a question of fact,”
Strand v. Cranney,
. For example, the fact that SPR's capital investment was put at risk by the Agreement quite reasonably supports the inference that SPR, like any investor, stood only to lose its investment and nothing more if the project failed. Moreover, much like in the realm of partnerships, holding property as tenants in common does not by itself establish a joint venture relationship. Cf. Utah Code Ann. § 48-1-4(2) (2002) ("Joint tenancy, tenancy in common, tenancy by entire-ties, joint property, common property, or part ownership does not of itself establish a partnership, whether such co-owners do or do not share any profits made by the use of the property.”).
. The trial court inferred from these actions that "[SPR] voluntarily put its own property at greater risk of loss” than would an "investor” or "simple creditor,” and that SPR had thereby waived the protection of language in the Agreement limiting SPR’s obligation arising by reason of any note or guaranty for construction financing. The court concluded that these actions manifested SPR's duty to share in losses. But it is equally plausible to infer from such actions that SPR was merely acting to protect its investment — and the potential return on its investment — by seeking to avoid foreclosure of the construction loans. Moreover, by mortgaging its interest in the Northshore Property, SPR did put the property at risk, but arguably only stood to lose its capital investment — which was used to purchase the property in the first place — and nothing more.
. SPR would have us rule as a matter of law that it had no duty to share in the losses and was therefore not a joint venturer with Broadstone. Even if we were to agree that the affidavits and undisputed facts entitled SPR to that conclusion as a matter of law — which we do not — SPR did not file a cross-motion for summary judgment, and we would therefore be procedurally constrained from entering judgment in its favor on this issue in any event.
. This familiar pronouncement is contrary to a startling statement by Professor David A. Thomas that a Utah Supreme Court case,
McBride v. Jones,
. The trial court's summary judgment ruling includes "Findings” that, indeed, appear to be true findings of fact reached by weighing evidence and assessing credibility rather than the misnomer we often see employed in a written ruling on summary judgment, where what is really a recitation of undisputed facts will appear under the heading "Findings.”
. A more simplistic example may help to explain our analysis: Aimee and Brian
form
a partnership in order to purchase and develop property into a strip mall. Aimee and Brian contract with general contractor Catherine to develop the land. Construction progresses as expected with Aimee and Brian signing various change orders throughout the project. During the construction, Brian offers to buy a pair of skis that he notices on Catherine's truck. Cath
. Besides the bite the criminal penalty puts into the abusive lien statute, a person who violates the statute is also liable "to the owner of the property or an original contractor or subcontractor who is affected by the lien for the greater of” double the amount by which the lien exceeds what is actually due, or the actual damages incurred. Utah Code Ann. § 38-1-25(2) (2005).
. Construing the abusive lien statute in this manner comports with the "fair import” of the statute's terms and "the objects of the law.” Utah Code Ann. § 76-1-106 (2003). Moreover, it assures that the abusive lien statute continues "to discourage outrageous lien claims,”
J. Pochynok Co. v. Smedsrud,
. On summary judgment, the trial court deemed the lien waivers applicable and held with respect to the lien waiver language that
[b]y endorsing the Central Bank checks, Ells-worth ... waived [its] claims and lien rights for work performed prior to the date that [its] draws were requested, but not for work performed subsequently. The date of the draw request is the date on which [Ellsworth] requested the draw, not the date the check was received or cashed.
This ruling was not challenged on appeal.