Ellinwood v. City of Worcester

154 Mass. 590 | Mass. | 1891

Knowltoít, J.

Prior to the passage of the St. of 1872, c. 318, under an entire contract to furnish both labor and materials in the erection of a building on real estate, to be paid for at an entire price, no lien attached for the labor unless a lien was also secured for the materials before furnishing them by giving notice in writing to the owner, if the owner was not the purchaser, that the contractor intended to claim a lien for materials. Pub. Sts. c. 191, § 3. Felton v. Minot, 7 Allen, 412.

The St. of 1872, c. 318, § 1, (Pub. Sts. c. 191, § 2,) provides that under such a contract a lien for the labor may be “ enforced, if .it can be distinctly shown what such labor was worth, but in no case shall such lien be enforced for a sum greater than the price agreed upon for the entire contract.” For the protection of all persons interested in the estate, the statement to be filed in such a case must set forth, in addition to the other particulars mentioned in the preceding statutes, “ the entire price for the entire contract, the number of days of labor performed or furnished, and the value of the same.” St. 1872, c. 318, § 2. Pub.

Sts. c. 191, § 6. The filing of a statement containing these particulars within the time prescribed is a condition precedent to the enforcement of the lien. The obvious purpose of the statute is to enable the owner and others interested in the property to ascertain from the record the particulars of the claim, and whether it is of such a kind that it can probably be enforced against the land, and if so, for what amount.

*592The contract price, the number of the days of labor, and the value of the labor, are important elements entering into this question. These must be stated as required by the statute, or there is no lien. Pub. Sts. c. 191, § 8. A mere “inaccuracy in stating the amount due for labor or materials,” if the result of mistake, will not defeat the lien. This was a provision of the General Statutes, and the subsequent St. of 1872, c. 318, makes new requirements in regard to the statement. This section can have no greater effect in its application to these requirements than to relieve the petitioner from the effect of mistakes in giving the number of days of labor or the value of it. It does not nullify the provision of the later statute, which requires the number of days of labor and the value of it to be given, as well as the contract price, and does not apply to a case where there is an entire omission to give them.

In Hurley v. Lally, 151 Mass. 129, it was decided that a statement under the statute which did not contain the contract price was fatally defective, and the principle which governs that case is decisive of this also. The exceptions show that all the labor and materials were furnished under an express contract, for an entire price; and, while the statement sets forth a large amount of labor by the number of hours occupied W performing it and the price per hour, it contains one item as follows: “ Labor of myself between September 1, 1889, and May 1, 1890, $900,” without anything to indicate the number of days for which claim is made. The next item, “ Labor laying 1100 yards concreting at 25 cents per yard in the last part of August, 1890, and ending August 30, 1890, $275.00,” is equally defective. There was obviously no attempt to give the whole number of days of labor done under the contract, and this non-compliance with the requirements of the statute makes it unnecessary to inquire whether the remaining part of the statement which states the time in hours alone is sufficient.

Exceptions overruled.

midpage