Electro-Lab of Aiken asserts that Sharp Construction Company breached the parties’ contract by replacing Electro-Lab with a different subcontractor. The parties became contractually bound, Electro-Lab argues, by virtue of Sharp’s use of Electro-Lab’s subcontracting bid in its general contracting bid and by certain acts following the use of the bid. The trial court disagreed, concluding that no contract existed between the parties. We affirm.
FACTS
On April 24, 1997, bidding closed for all general contractors on two projects to build schools in York County, South Car
Sharp, as the low bidder for the project, was awarded the general contract and was required to provide payment and performance bonds. When Electro-Lab contacted Sharp to inquire about the project, Sharp notified Electro-Lab that its bid was the lowest and that it was listed as the electrical subcontractor in Sharp’s successful bid. Sharp’s project manager testified that during this telephone conversation, he told Electro-Lab that he would like to know what its bond rate was and asked Electro-Lab to fax its bid in writing. Shortly thereafter, Sharp discovered that Electro-Lab’s subcontract bid was not the lowest bid received, and asked Electro-Lab if it could perform the work for $1,140,000. Electro-Lab agreed, and Sharp submitted the following confirmatory fax:
Dear Michael:
This letter is to confirm that we will be issuing a subcontract for the electrical work on the above referenced project for $1,140,000.00.
Please proceed immediately with having shop drawing completed and performance and payment bonds issued. A subcontract is forthcoming. We look forward to working with you.
Sincerely,
SHARP CONSTRUCTION CO. OF SUMTER, INC. HAL TURNER
Following receipt of this letter, Electro-Lab attended a pre-construction conference at Sharp’s request and began gather
After Electro-Lab informed Sharp that it could not obtain the bonds, Sharp entered into a subcontract for the same dollar amount with Ind Com, which provided payment and performance bonds as required. By letter, Sharp confirmed that it would be switching to a different electrical subcontractor because of Electro-Lab’s inability to obtain bonding.
Electro-Lab did not protest the change until nine months later when it initiated the instant lawsuit, alleging that Sharp breached their contract by switching the subcontract for the project’s electrical work to Ind-Com. After a full trial on the merits, the trial judge ruled in favor of Sharp, determining that no contract existed between the parties and that Electro-Lab’s proof of damages was legally insufficient.
STANDARD OF REVIEW
An action for breach of contract is an action at law.
Auto Owners Ins. Co. v. Langford,
ISSUES
1. Did the trial court err when it found no contract existed between the parties?
2. Did the trial court err when it found that Electro-Lab’s proof of damages was legally insufficient?
Electro-Lab argues a contract existed between the parties by virtue of the use of Electro-Lab’s bid in Sharp’s successful general contracting bid, the parties’ subsequent communications, and Electro-Lab’s attendance at a pre-construction meeting and its gathering of submittals from suppliers. We disagree.
“A contract is an obligation which arises from actual agreement of the parties manifested by words, oral or written, or by conduct.”
Regions Bank v. Schmauch,
Jurisdictions outside of South Carolina have consistently held that a general contractor’s use of a subcontractor’s bid is not an acceptance that creates a contractual relationship between the general contractor and the subcontractor should the general contractor become the successful bidder.
See, e.g., Elec. Constr. & Maint. Co. v. Maeda Pac. Corp.,
In accordance with these jurisdictions and based on general contract law principles, we agree that a general contractor’s mere use of a subcontractor’s bid in a general contractor’s successful overall bid does not constitute acceptance of an offer. “Acceptance of an offer is a manifestation of assent to the terms thereof made by the offeree in a manner invited or required by the offer.” Restatement (Second) of Contracts § 50 (1981). A typical contract contains mutual promises and is created by an acceptance constituting a return promise by the offeree.
See
Restatement (Second) of Contracts § 50 cmt. c (1981);
Sauner v. Pub. Serv. Auth.,
Electro-Lab argues that even if the use of a bid by a general contractor from a subcontractor does not necessarily form a contract, such use is indicative of the formation of a contract between the two companies. Electro-Lab asserts, based on the totality of circumstances, that the culmination of Sharp’s and Electro-Lab’s actions formed an enforceable contract. We disagree. Following Sharp’s use of Electro-Lab’s bid, Sharp’s project manager testified that he told Electro-Lab that its bid was low, inquired about Electro-Lab’s bond rate and asked Electro-Lab to fax its bid in
Electro-Lab also asserts that principles of mutuality of contract require we find the parties bound in contract. We do not find the principles of mutuality of contract to be invoked under these circumstances. In support of this argument, Electro-Lab relies on
Powers Constr. Co. v. Salem Carpets, Inc.,
Because we agree with the conclusion of the trial court that no enforceable contract existed between the parties, we need not reach Electro-Lab’s argument concerning the sufficiency of damages.
See Futch v. McAllister Towing of Georgetown, Inc.,
AFFIRMED.
