66 Ct. Cl. 333 | Ct. Cl. | 1928
delivered the opinion of the court:
The plaintiff is a New Jersey corporation. In the years 1915, 1916, and 1917 plaintiff entered into 32 separate contracts with the defendant to construct and deliver 32 submarine torpedo boats. The total original consideration for the entire undertaking was $23,806,000.00. Under the contracts the vessels were to be delivered at stated times, and express provision was made reserving to the defendant the right to make changes in plans and specifications. Changes were made and the vessels were not delivered upon the contract dates. Time for completion of the vesesels was duly extended by the Government, and they were accepted without the imposition of deductions as meeting requirements under this stipulation. This case is due exclusively to the interposition of war conditions, and the amounts claimed as losses are predicated upon alleged contracts of reimbursement for such losses, recognized by and due wholly to acts of the Government whereby the cost of completing the contracts was greatly enhanced. The facts, not particularly involved but somewhat extensive, are as follows: The President on March 22, 1917, issued a proclamation suspending the provisions of the eight-hour law in Government contracts and thereby established a new standard for labor, resulting in the authorization of overtime work and wages. This was immediately prior to our entrance into the war. Subsequent to this latter event the Navy Department adopted the policy of constructing destroyers and giving this form of construction precedence over all other construction work. The plaintiff had sublet to the Fore River Shipbuild
On March 29,1918, the plaintiff in writing brought to the attention of the Secretary of the Navy the seriousness of the situation respecting the increase in cost and financial
The department, to meet the unusual situation on an equitable basis, should authorize reimbursement to both the prime contractor and its subcontractor on a basis substantially equivalent to the increase in wages authorized for other shipyards in the vicinity; that the adjustment should be determined under the stipulation in the contracts authorizing changes therein, after the plaintiff had submitted its original estimate of actual cost under its fixed-price contracts in such detail as to enable the department to accurately determine the increased costs. Overhead expense was to be so adjusted under changed conditions as to preclude allowance of profits, and in no event to include profits in excess of 10%, including bonuses on the basis of the plaintiff’s fixed-price contracts.
On April 29, 1918, the same day the Oapps report was received, the Secretary of the Navy indorsed thereon a ref
On October 31, 1918, the Labor Adjustment Board notified the plaintiff as to new wage schedules to become effective October 1, 1918, and plaintiff again, at its request, received written assurances that it would receive reimbursement for1 the additional costs to be incurred in performing its con
In April, 1920, the plaintiff appealed to the Secretary of the Navy for the appointment of a naval board to consider its claims for reimbursement. In May, 1920, the Secretary of the Navy created the Baxter Board, a board composed of five naval officers, and to it committed the consideration of plaintiff’s claims. This board made a finding recommending a total allowance to the plaintiff of $3,392,023.50, from which was to be deducted the $700,000.00 previously advanced, leaving as due the plaintiff $2,692,023.50. On April 13,1921, a board on changes, created by the Secretary of the Navy, reported an allowance due the plaintiff for changes of $141,302.34 instead of $134,782.51 allowed by the Baxter Board. The findings of the Baxter Board were disapproved by the Navy Department, and on June 21, 1922, the Taylor Board came into existence. The Taylor Board report is found in Finding XIII. The controversy culminated on November 16, 1923, by the Navy Department denying legal liability to make any reimbursements, predicating its opinion upon the absence of authority so to do without supporting legislation, and hence the plaintiff received no payments except the $700,000.00 heretofore mentioned, and for the recovery of which the defendant interposes a counterclaim.
The final petition of the plaintiff prays for a judgment of $5,020,712.70 and “ such rate of profit as the court maj? deem just and equitable.” The right of recovery under this phase of the litigation is rested upon the proof of an alleged cost-plus contract as recited in detail in Findings IX and X. Doubt as to a preliminary oral agreement between the parties respecting the making of a cost-plus contract to take the place of plaintiff’s existing fixed-price contracts is removed by the record. An agreement embodying the matter
The defendant insists that the record does not sustain a supplemental contract to reimburse the plaintiff for. increases-in cost of construction due to increased wage scales; that the advanced scale of wages promulgated from time to time by the Labor Adjustment Board and overtime wages fixed were voluntarily paid by the plaintiff without express order or the slightest compulsion upon the part of the Government. Aside from the positive facts negativing the above contention, we think the record unmistakably warrants the inference that the element of voluntary assent to the changed conditions is distinctly lacking. The contractor could, if so disposed in time of war, have stood upon his contract rights, and the Government might have done likewise. The statement needs no demonstration. We are not concerned with what the parties might have done; the case is the outgrowth of what was done. To assert that a contractor confronted with an acute paucity of labor in a position to demand increased wages and overtime working hours voluntarily meets the demands when he is without recourse to do otherwise, and thereby absorb all his contemplated profits and perhaps encounter financial embarrassment in addition, is to take away from the word “ voluntary ” that freedom of choice the word imports. This record discloses the fact that the plaintiff had available under the existing conditions and the terms of its contracts a
Counsel for the defendant from a very able and careful analysis of the record deduces a conclusion that the proven facts at best establish an agreement upon the part of the Government officers to do no more than consider1 the plaintiff’s claim, and that an agreement to consider claims creates the single obligation to fix the mind thereon, examine into, and at some future time render a definite conclusion, and in this case no final conclusion was reached; in other words, consideration was all that obtained. The subject matter before the Secretary of the Navy and other responsible officers of the department was a contention for an agreement to pay the plaintiff for excess cost of production, due to the increased wage scale. It involved serious consideration, first as to the legal right to grant the request, and, secondly, the extent of the liability to be assumed. The expressed intent of the Secretary indicated at the initiation of the controversy was to do justice and equity, and the subsequent proceedings as the court finds from the record resulted in an agreement, as the result of consideration, to reimburse the plaintiff when a legal way should be found to do so. The single disturbing factor to a consummated written understanding was what route to take; not that all routes should be closed. If, then, the Secretary was in accord with the claim presented by the contractor, and consented to his claim, the fact that he misconceived his legal authority in the premises does not remove from the negotiations the important element of mutuality. We think the record is replete with facts which clearly demonstrate a condition wherein had the Secretary had before him the decision of the Supreme Court in the Bliss case this litigation would not have followed. To consider, as usually employed in legal proceedings, conveys the meaning of consideration and adjudication. The Secretary was not, we think, using the
We have no difficulty, in view of the findings, in holding that a supplemental agreement to reimburse the plaintiff for its increased costs of production, due to the waiver of the eight-hour law by the Government and the wage increases established by the Labor Adjustment Board, with the approval and assent of the Government obtained. From the beginning of the long controversy to its finality there exists but one positive statement that in anywise negatives the Government’s complete assent to reimburse the plaintiff, and that one statement made in 1923, five years after the close of hostilities, in the face of an express opinion from the Comptroller of the Treasury previously given that an agreement might be legally consummated to care for the situation, is rested not upon a denial of the existence of such a contract, but wholly upon a question of legal liability to make the reimbursements.
In the course of the Navy Department’s efforts to check the books of accounts of the plaintiff the Baxter Board adopted a method of ascertaining increased cost. The report of the Baxter Board (Finding XI) reflects its efforts and discloses that it is the result of an exhaustive examination of plaintiff’s books and records up to August 30, 1920, asserting in addition that the report reflects “ actual cost and damage ” as per directions contained in the precepts. The Taylor Board (Finding XIII), in its report, materially reduced the findings of the Baxter Board. The Taylor Board succeeded the Baxter Board following the disapproval bjr the department of the Baxter Board’s report. The plaintiff assented to the correctness of three findings of the Taylor Board, but declined to accept the remaining ones. The Judge Advocate General sustained plaintiff’s objection to one finding. The final conclusion of the effort to satisfactorily reach an amount terminated in the plaintiff’s refusal as above mentioned, and the defendant’s determination of an entire absence of legal liability for any of the increases. The single available source of evidence to establish the amount of the increases, aside from Government records of the rates of increases, was the plaintiff’s books of account. Of course, difficulties were to be encountered in ascertaining with indisputable exactness, to the very penny, the amounts expended by the plaintiff in meeting the increases. Thirty-two contracts, representing a consideration of almost twenty-four million dollars, were involved, and it is not to be expected, nor is it required under the law, that the bill of damages shall measure up to a greater degree of certainty than is required in cases of this nature. Transactions like this ex
We think the settled rule as to damages is that they are not to be denied because they may not be susceptible to indisputable accuracy. The test to be applied is, Have the sums claimed been calculated upon a reasonable basis, and under all the circumstances of the case does the claimed amount reflect the proximate injury? If the element of speculation is absent, if the basis of computation is the usual and customary one followed in cases of a similar character, and the court is satisfied that the method of computation employed reflects with reasonable certainty the extent of the loss, judgment may be predicated upon this
“Where the originals consist of numerous documents which can not be conveniently examined in court, and the fact to be proved is the general result of an examination of the whole collection, evidence may be given as to such result by any person who has examined the documents and who is skilled in such matters, provided the result is capable of being ascertained by calculation. This has been permitted when another course would cause great loss of time and tend to confuse the jury; and competent witnesses have been allowed to summarize the accounts and to state conclusions as to balance, solvency or insolvency, and the like. Of course, the court may require the production of the originals if this is deemed necessary.1'’ (Jones on Evidence, civil cases, p. 254.) ' . J
The proof offered is in our opinion the best evidence of the loss available, and establishes with certainty the extent of the same. The judgment awarded is not the judgment sought in the petition, plaintiff contending for the amount of increases plus a reasonable profit. The court, however, is authorized under our forms of pleading to award a judgment in accord with the facts stated and proven, notwithstanding the absence of a count in the pleadings for the particular recovery. Wood et al. v. United States, 49 C. Cls. 119; Clark v. United States, 95 U. S. 539.
The defendant’s counterclaim will be dismissed. Judgment for the plaintiff for $3,083,732.64. It is so ordered.