Lead Opinion
El Pаso Electric Co. (“EP Electric”) appeals from three decisions
I. Background
A. Factual Background
This case concerns a scheme of planning, cost allocation, and regulation imposed by FERC on EP Electric and the Intervenor electricity providers.
In 2011, FERC enacted Order No. 1000 to address changes in the electric power industry and to keep rates just and reasonable. Id. at 52. As relevant to the challenges we address in this appeal, Order No. 1000 requires:
Each transmission provider must participate in a regional transmission planning process that complies with the planning principles in [a previous order,] Order No. 890, produces a regional transmission plan for development of new regional transmission facilities, and includes procedures to identify transmission needs driven by public policy requirements established by federal, state, or local laws or regulations and evaluate potential solutions to those needs.
South Carolina,
Order No. 1000 mandated cost allocation reforms designed to ineentivize the development of cost-efficient transmission facilities in the regional planning process. It did so, in part, by encouraging transparency and certainty about the costs and benefits of such projects, and about which parties would be eligible to fund and develop each project. See Order No. 1000 ¶ 11,
OAT Tariffs must comply with certain cost allocation principles, the most pertinent of which is cost causation.
Another important principle for this appeal is that Sections 205 and 206 of the FPA only give FERC the authority to directly regulate “jurisdictional” utilities, a specified category of public utilities that transmit power in interstate commerce. See generally South Carolina,
B. Procedural History
Together, EP Electric and Intervenors are members of a regional planning organization called WestConnect. EP Electric and Intervenors emphasize the unique na
EP Electric and the WestConnect jurisdictional utilities coordinated with each other to file tariff revisions in attempts to comply with Order No. 1000. FERC addressed each of these revisions in its Compliance Orders.
1. FERC’s First Compliance Order
The first WestConnect compliance filing noted that jurisdictional and non-jurisdictional utilities alike tentatively intended to enroll in the WestConnect region. EP Electric proposed that costs be allocated depending on the agreement of beneficiaries identified through the regional planning process, and its compliance filing specified that no entity was obligated to implement cost allocation. Of note here, FERC’s First Compliance Order required revision of the proposed cost allocation process to provide for “binding” cost allocations “upon identified beneficiaries.” Pub. Serv. Co. of Colo., “Order on Compliance Filings,”
2. FERC’s First Order on Rehearing
WestConnect jurisdictional utilities responded in the second compliance filing by seeking a rehearing. They also proposed to include non-jurisdictional utilities in the regional planning as “Coordinating Transmission Owners” who would have all the rights of an enrolled jurisdictional utility, except that they would not be subject to binding cost allocatiоn. The WestConnect utilities proposed to exclude any project from regional cost allocation that “electrically interconnects with, or that is demonstrated to provide quantifiable benefits” to a non-enrolled transmission owner in the WestConnect region. The utilities proposed to study and identify projects that met regional needs, including those of the non-jurisdictional utilities, but to obtain funding from participants in a voluntary manner rather than through a binding cost allocation that could not include the non-jurisdictional utilities. The non-jurisdictional utilities supported this approach.
In FERC’s First Order on Rehearing, FERC accepted the inclusion of non-jurisdictional utilities as Coordinating Transmission Owners for regional planning and the ability of the regional planning process to account for the Coordinating Transmission Owners’ needs. Pub. Serv. Co. of Colo., “Order on Rehearing and Compliance,”
3. FERC’s Second Order on Rehearing
The WestConnect utilities again sought a rehearing and filed proposed revisions, objecting that the First Order on Rehearing would create free ridership and violate cost causation. Specifically, the WestCon-nect utilities objected that FERC’s First Order on Rehearing mandated that jurisdictional utilities pay the costs to develop new transmission facilities and exempted non-jurisdictional utilities from those costs. The WestConnect utilities argued that this structure violated cost causation, which requires allocating costs in at least a roughly commensurate fashion to thоse who receive the benefits of transmission development. Additionally, if non-jurisdictional utilities could benefit from transmission development without paying for it, they would become the subsidized free riders that Order No. 1000 sought to reduce or eliminate. In the alternative, the WestCon-nect utilities also proposed to make a project ineligible for cost allocation if a non-jurisdictional utility opted out of benefits allocated to it and the re-allocation of costs to jurisdictional utilities increased their original costs more than 10%. The non-jurisdictional utilities supported this proposal.
FERC rejected this proposal and the request for rehearing, noting that
[w]hile [the situation] may create the potential for free ridership if a nonpublic utility transmission provider elects to not enroll in a region and benefits from a transmission project selected in the regional transmission plan for purposes of cost allocation, that potential exists because the transmission project has benefits for entities that are not required to enroll, and have not enrolled, in the region.
Pub. Serv. Co. of Colo., “Order on Rehearing and Compliance,”
Finally, FERC declined to accept West-Connect’s 10% cap proposal for cost allocation “because the proposal might lead to the transmission planning process rejecting rеgional cost allocation for a proposed transmission solution that continues to be a more efficient or cost-effective solution for the remaining beneficiaries compared to other alternatives even after a cost shift.” Id. ¶ 57,
II. Standard of Review
We review FERC’s orders under the “arbitrary and capricious” standard of the Administrative Procedure Act (“APA”). See La. Pub. Serv. Comm’n v. FERC (La. II),
FERC’s choices in regulating rates, tariffs, and related practices involve technical issues within its purview that are entitled to great deference. La. II,
III. Discussion
EP Electric and the Intervenors challenge multiple facets of FERC’s decisions in the Compliance Orders. We address each challenge in turn.
In this appeal, the Utilities argue that FERC’s mandate of binding cost allocation was arbitrary and capricious because it applies only to the jurisdictional utilities and thus forces the jurisdictional utilities to subsidize projects benefitting the non-jurisdictional utilities. This creates a “free rider” problem that Order No. 1000 sought to reduce or eliminate. The Utilities therefore assert that this marks a departure from Order No. 1000 and unlawfully violates the principle of cost causation that FERC follows to ensure just and reasonable rates.
As a threshold issue, we conclude that this challenge is not a collateral attack on Order No. 1000. Although Order No. 1000’s failure to require the participation of non-jurisdictional utilities in binding cost allocation has been generally challenged, see South Carolina,
We conclude that FERC’s Compliance Orders fail to adequately explain how the mandates in those orders do not ensure rnjust and treasonable rates as between jurisdictional and non-jurisdictional utilities (and their customers) in the West-Connect region. We therefore grant the petition for review and remand this issue to FERC for further proceedings consistent with this opinion.
FERC argues that it need not account for the non-jurisdictional utilities or more forcefully incentivize their participation in binding cost allocation for three primary reasons. First, FERC argues that the FPA only requires -it to regulate jurisdictional utilities. Accordingly, it need not account for the benefits to the non-jurisdictional utilities in аny analysis of whether the regional planning process requires paying costs roughly commensurate with the. benefits received. FERC chose not to regulate non-jurisdictional utilities through Order No. 1000. Thus, FERC contends that any free ridership resulting from its Compliance Orders for the WestConnect region does not contravene Order No. 1000’s purpose of reducing free ridership. Second, FERC argues that it may regulate incrementally, relying at first on the voluntary participation of non-jurisdictional utilities before attempting to more forcefully incentivize participation. Third, FERC argues that cost causation need not be perfect, and that this imprecise form of cost
It is true that Order No. 1000 declined to regulate non-jurisdictional utilities and therefore does not address free ridership by those utilities. It is also certainly within FERC’s discretion to balance cоmpeting objectives, and FERC’s regulations need only roughly correlate costs to benefits. Yet, FERC has a statutory duty to ensure just and reasonable rates, and Order No. 1000 emphasized the cost causation principle in service of that goal. See Order No. 1000-A ¶ 592,
As they stand, the Compliance Orders do not apply that foundational principle of cost causation for about half of the utilities in the WеstConnect region.
Before this court, FERC argues that the Compliance Orders may not result in unjust and unreasonable rates because it may be able to use the “reciprocity condition” to incentivize participation of non-jurisdictional utilities in binding cost causation. See generally South Carolina,
A non-public utility transmission provider may continue to satisfy the reciprocity condition in one of three ways. First, it may provide service under a tariff that has been approved by the Commission under the voluntary “safe harbor” provision of the pro forma [Open Access Transmission Tariff (“OATT”) ]. A non-public utility transmission provider using this alternative submits a reciprocity tariff to the Commission seeking a declaratory order that the proposed reciprocity tariff substantially conforms to, or is superior to, the pro forma OATT. The non-public utility transmission provider then must offer service under its reciprocity tariff to any public utility transmission provider whose transmission service the non-public utility transmission provider seeks to use. Second, the non-public utility transmission provider may provide service to a public utility transmission provider under a bilateral agreement that satisfies its reciprocity obligation. Finally, the non-public utility transmission provider may seek a waiver of the reciprocity condition from the public utility transmission provider.
Order No. 1000-A ¶ 771,
How the reciprocity condition might operate in the WestConnect region is a question the parties have raised, which hаs been left unanswered by the Compliance Orders and FERC’s arguments on appeal. For example, although FERC has stated that the reciprocity condition may be satisfied in three ways, see id., in the Compliance Orders, FERC only addressed one method of satisfying the reciprocity condition. See First Order on Reh’g ¶ 55 n.101,
It is well settled that we “must disregard any post hoc rationalizations of [an agency’s] action and evaluate it solely on the basis of the agency’s stated rationale at the time of its decision.” Luminant Generation Co. v. U.S. EPA,
Absent a more reasoned explanation for why the non-jurisdictional utilities will participate in the binding cost allocation process, or why their lack of participation will not result in unjust and unreasonable rates, we conclude that the Compliance Orders are arbitrary and capricious and cannot be approved in their current form.
B. EP Electric’s Other Challenges
EP Electric also separately challenges whether FERC violated the APA by requiring binding cost allocation at the regional planning stage and by requiring the regional planning process to select a particular developer, entitling that developer to rely’on cost allocation for a given' project. EP Electric argues that FERC unlawfully sub-delegated its ratemaking duties under the FPA by giving the West-Connect Planning Management Committee (‘WestConneet Committee”) the power to select projects with binding cost allocation. Binding cost allocation also violates the Mobile-Sierra doctrine,
We conclude that all of these challenges are barred as impermissible collateral attacks, save the argument regarding improper sub-delegation, and we find that
To distinguish between collateral attacks and permissible challenges, we ask whether the FERC order the petition challenges was a clarification or a modification of a prior FERC order.
First, the Compliance Orders merely clarified that Order No. 1000 meant to impose binding cost allocation, which Order No. 1000 clearly signaled and the D.C. Circuit has already recognized. See, e.g., Order No. 1000-A ¶¶ 567-68,
Second, the selection of one developer that will be eligible for cost allocation in the regional planning process is a predictable clarification of Order No. 1000’s reforms, and we DISMISS the petition for review as to this issue. Order No. 1000 explicitly declined to grant developers rights to build projects, but noted that its “framework” allowed “the developer” of a facility selected in a regional transmission plan for the purposes of cost allocation “to rely on the relevаnt cost allocation method or methods within the region should it desire to move forward with its transmission project.” Order No. 1000 ¶ 339,
Finally, we DENY review as to EP Electric’s argument that the Compliance Orders violate the Mobile-Sierra doctrine. The Mobile-Sierra doctrine prevents FERC from abrogating a valid contract setting rates unless that contract seriously harms the public interest. See Morgan Stanley,
The sole remaining challenge that is not barred as a collateral attack is EP Electric’s argument that FERC improperly delegated its authority to review rates under FPA Section 205 by giving the WestConnect Committee the power to impose binding cost allocation. According to EP Electric, Order No. 1000 indicated that FERC would review proposed tariffs of developers selected in the regional planning processes through its Section 205 authority. We agree that there is some inconsistency between the Compliance Orders and Order No. 1000 on this issue. Compare Order No. 1000 ¶ 543,
Nevertheless, we cannot agree with EP Electric that FERC has “abdicate[d] its role as a rational decision-maker” through the Compliance Orders. See La. Pub. Serv. Comm’n,
IV. Conclusion
For the reasons stated, we GRANT the petitions for review in part, as to the challenge to the role of non-jurisdictional utilities in the regional planning and cost allocation processes of the WestConnect region. We VACATE FERC’s Compliance Orders on this issue and REMAND for further explanation and fact finding con
Notes
. Collectively, we refer to the decisions being challenged as FERC's "Compliance Orders,” unless we specify a particular order. The Compliance Orders include: Pub. Serv. Co. of Colo., "Order on Compliance Filings,"
. We refer collectively to these rules as "Order No. 1000” unless otherwise specified.
. We granted leave for the following entities to intervene in this appeal: Arizona Public Service Company, Black Hills Power, Inc., Black Hills Colorado Electric Utility Company, LP, Cheyenne Light, Fuel, and Power Company, NV Energy, Inc., Public Service Company of New Mexico, Tucson Electric Power Company, UNS Electric, Inc., Xcel Energy Services Inc., and Public Service Company of Colorado.
. OAT. Tariffs originated before Order No. 1000. Transmission providers must file an OAT Tariff “containing minimum terms of non-discriminatory transmission service." South Carolina,
.As Order No. 1000 stated: "[F]ree riders by definition are entities who are being subsidized by those who pay the costs of the benefits that free riders receive for nothing.” Order No. 1000-A 11 578,
. This binding cost allocation process only applies to projects selected in the regional transmission plan for the purposes of cost allocation, meaning these projects are approved as more efficient or cost-effective solutions to regional needs. See Order No. 1000 ¶ 5,
. We express no opinion about whether (if at all) or in what manner FERC may exercise authority over non-jurisdictional utilities under Section 211A of the FPA, since FERC has not attempted to exercise any authority it may or may not have under this provision.
. The Supreme Court has emphasized the deference courts must give to FERC, but that deference only applies when FERC has "articulate[d] a satisfactory explanation for its action.” FERC v. Elec. Power Supply Ass’n, - U.S. -,
. EP Electric and Intervenors briefed these issues separately. Intervenors "adopt and incorporate the list of issues identified by El Paso in its brief,” but "focus their briefing” only on certain arguments. Therefore, we refer to arguments made only in EP Electric's brief as EP Electric's arguments. When discussing arguments made fully by both EP Electric and the Intervenors, we refer to the parties collectively as the "Utilities.”
. Order No. 1000 clearly linked cost causation, the elimination or reduction of free ridership, just and reasonable rates, and more efficient transmission planning and development. Order No. 1000-A states:
The requirements of Order No. 1000 are based on the principle of cost causation, which requires that costs be allocated in a way that is roughly commensurate with benefits. The principle of cost causation is intended to prevent subsidization by ensuring that costs and benefits correspond to each other. Indeed, in seeking to eliminate free riders on the transmission grid, Order No. 1000 seeks to eliminate a form of subsidization, as free riders by definition are entities who are being subsidized by those who pay the costs of the benefits that free riders receive for nothing.
Order No. 1000-A ¶ 578,
. See, e.g., First Order on Reh'g ¶¶ 54-57,
. The dissеnting opinion argues we should consider the reciprocity condition and trust FERC's judgment that the condition will in-centivize the non-jurisdictional utilities' participation. Deference to FERC on this issue is not possible because FERC has not made clear how the reciprocity condition will operate in this unique region to incentivize participation. Due to that lack of explanation in the face of the Utilities' objections below, the Utilities were not given the opportunity to challenge FERC’s terse reasoning, except in equally terse form on appeal and without a properly developed agency record. To avoid this scenario, our precedent prevents us from considering post hoc rationalizations, and we decline to do so here. See Luminant,
. The dissenting opinion relies on FERC's reasoning for rejecting a 10% cost cap in the Second Order on Rehearing. In that Order, FERC specified that if a Coordinating Transmission Owner rejects binding cost allocation for a project that would provide benefits to that Owner, the transmission planning process removes the benefits that Owner would reap and recalculates future cost allocation determinations such that they only account for the benefits accorded to the entities that have agreed to binding cost allocation. See Second Order on Reh'g ¶ 57,
. The Mobile-Sierra doctrine “address[es] the Commission's authority 'to modify rates set bilaterally by contract rather than unilaterally by tariff.' ” South Carolina,
. The inquiry into whether FERC violated the APA by changing its interpretation of Order No. 1000 through the Compliance Orders is similar to the collateral attack inquiry. Compare Pac. Gas & Elec. Co. v. FERC,
Dissenting Opinion
dissenting:
There is no justification to remand for “a more reasoned explanation for why the non-jurisdictional utilities will participate in the binding cost allocation process, or why their lack of participation will not result in unjust and unreasonable rates.” The Majority errs by labelling Order No. 1000’s reciprocity condition a post hoc rationalization and errs more deeply still by failing to accord FERC’s policy decision appropriate deference.
FERC, Order No. 1000 includes the “reciprocity condition” that requires non-jurisdictional utilities to “participate in transmission planning and cost allocation in exchange for open access.” S. Carolina Pub. Serv. Auth. v. F.E.R.C.,
The court here disregards the reciprocity condition because only one mention is made in the Compliance Orders. However, in the Second Order on Rehearing, FERC reminds that “if a coordinating transmission owner does not accept the cost allocation, the transmission planning process removes the benefits of those coordinating transmission owners that do not accept the cost allocation” and cost allocation determinations therefore remain “commensurate with the estimated benefits considered.” Second Order on Rehearing at ¶ 57. In any event, the reciprocity condition is a rule found within Order No. 1000 and cannot be written off as a mere post hoc rationalization.
FERC has the responsibility of deciding how to achieve its statutory mandate of ensuring just and reasonable rates, and we must trust its judgment that the reciprocity condition adequately incentivizes participation of the non-jurisdictional utilities. We are not “to ask whether [the] decision is the best one possible or even whether it is better than the alternatives,” including the Utilities’ alternative suggestions. F.E.R.C. v. Elec. Power Supply Ass’n, — U.S. -,
Thus, FERC does not have to cоnvince us that its approach is sounder than the Utilities’ approach. “The disputed question here involves both technical understanding and policy judgment,” and the record establishes that FERC “engaged in reasoned decisionmaking” by weighing competing views, selecting an approach based on the methods and goals of Order No. 1000, and “intelligibly” articulating “the reason for making that choice.” Id. at 784. This is sufficient. Id. For but one example of FERC’s reasoned decisionmaking, consider Paragraph 31 of the Second Order on Rehearing. There, FERC explained why it would permit the non-jurisdictional utilities to participate in the WestConnect region as Coordinating Transmission Owners
The Commission has accepted Filing Parties’ proposal to plan for non-public utility transmission providers, as coordinating transmission owners, without requiring that those non-public utility transmission providers enroll in the WestConnect transmission planning region and, thus, be subject to binding cost allocation. The Commission explained that doing so “will increаse transparency, support the building of a record with respect to transmission planning, and allow regional transmission planning to be conducted inclusive of nonpublic utility transmission providers, so as to expand opportunities for identifying and proposing more efficient or cost-effective regional transmission projects.” Allowing a non-public utility transmission provider to determine, consistent with its statutes, whether to accept the cost allocation may further expand open, transparent planning. By not enrolling, the non-public utility transmission providers are not full members of the WestCon-nect transmission planning region and, therefore, cannot be involuntarily allocated the costs of new transmission facilities that are selected in the regional transmission plan for purposes of cost allocation. While this situation may create the potential for free ridership, as it does when any entity not enrolled in the transmission planning region benefits from a new trаnsmission facility, it is not inconsistent with Order No. 1000.
(Second Opinion on Rehearing at ¶ 31.)
This is precisely the reasoned decision-making to which we must defer. FERC has decided that, even accounting for the Utilities’ free rider objection, other considerations support its determination. The Majority perceives a major concession in this paragraph: that under the Compliance Orders, there may be free riders. Majority Op. at 507-08 n.13. It is no such thing for three reasons. First, as has been already explained, the statement regarding free riders merely shows that, even when considering “the potential for free ridership,” FERC’s policy decision best serves its goals. This conclusion merits our deference.
Second, the statement demonstrates that the sort of free rider problem the Utilities complain of is not unique but rather is the same free rider problem that arises “when any entity not enrolled in the transmission planning region benefits from a new transmission facility.” In other words, this particular free rider problem is indistinguishable from the free rider problem acknowledged in Order No. 1000. (Order No. 1000 ¶ 660, 76 Fed.Reg. at 49,942 (“We acknowledge that this Final Rule’s approach may lead to some beneficiaries of transmission facilities escaping cost responsibility because they are not located in the same transmission planning region as the transmission facility. Nonetheless, the Commission finds this approach to be appropriate.”).
Third, there is simply no support for the conclusion that a “potential for free ridership” is fatal to FERC’s regulatory scheme. See South Carolina,
At bottom, the Majority errs by treating the required “satisfactory explanation” as one that actually persuades the court as to the wisdom of FERC’s decision or that actually rebuts the Utilities’ speculative contentions regarding unintended consequenсes.
. See Majority Op. at 505,("FERC’s Compliance Orders nowhere provide a reasoned explanation for why the non-jurisdictional utilities have incentive or obligation to participate in binding cost allocation when they can get many of the same benefits at the jurisdictional utilities’ expense.... FERC does not explain how it can meet its obligation to ensure just and reasonable rates by effectively assuring that many of the costs of new development will be imposed on only half of the utilities in the WestConnect region.... Absent a more reasoned explanation for why the non-jurisdictional utilities will participate in the binding cost allocation process, or why their lack of participation will not result in unjust and unreasonable rates, we conclude that the Compliance Orders are arbitrary and capricious and cannot be approved in their current form.”).
