This case involves the construction of a termination clause of a purchase-and-sale agreement. The defendants in the trial court were Carinthia Trailside Associates, a limited partnership, and Donald Swain, a general partner of Carinthia.
The following facts were stipulated. The parties in the case at bar entered into purchase-and-sale agreements for two condominiums built by defendants. Defendants offered a $3500-to-$5000 discount per unit if the plaintiffs would sign the agreement and deposit ten percent of the purchase priсe of their respective units before March 1, 1984. On February 28th, plaintiffs signed the purchase-and-sale agreements and made the deposits. Under the agreements, closing on the units was to take place within ten days of completion but no later than March 19, 1984. Each agrеement contained an addendum dealing with mortgage financing. The addendum made the agreement contingent on the purchasers obtaining approval of a mortgage for a sum certain at a specified rate. This contingency was deemed waived, however, unless the purchasers notified the sellers by certified or registered mail, return receipt requested, no later than March 19,1984, of the purchasers’ inability to obtain mortgage approval. If notice of unavailability of financing was given under the addendum, the purchaser wаs entitled to return of the deposit.
With defendants’ assistance, plaintiffs sought financing from the Factory Point National Bank.
On April 10,1984, plaintiffs’ mortgage applications were denied.
The stipulation does not show when defendants were ready to convey title. Defendants alleged that they were ready and able to convey title on or before March 19,1984 and filed an affidavit to that effect. Plaintiffs denied this allegation. The stipulation indicates that plaintiffs were never given written notice of the date of the completion of the units but, at some point, were given oral notice that the units were ready on March 1, 1984. The purehase-and-sаle agreement calls for the sellers’ architect to certify when a unit is ready for occupancy, with closing to take place within ten days thereafter but no later than March 19,1984. As indicated above, the March 22nd letter stated that the units had been ready since Mаrch 1st.
Defendants’ motion for summary judgment argued that the purchase-and-sale agreements were clear and unambiguous, that the agreements stated clearly that time was of the essence, and that plaintiffs failed to comply with the terms of the agreements. Plaintiffs resрonded that there were material issues of fact, because it was disputed whether defendants were ready to close on March 19, 1984 and that the March 22nd letter promised financing and obviated the need for notice under the adden
The trial court’s opinion and order concluded that the failure to give notice of the unavailability of financing by the March 19th deadline was not effective to remove the financing contingency “because the financing application was still being processed.” It went on to conclude that defendants were entitled to notice only when the financing fell through and they received such notice, albeit in a form different from that specified in the addendum. Relying primarily upon Town of Newport v. State,
This case is unnecessarily difficult because of the wholly inadequate state of the record on which the trial court made its decision. As discussed more fully below, we find the stipulation of facts to be incomplete, a deficiency which is particularly critical when we are considering a motion for summary judgment. Here, the parties opposing summary judgment were entitled to the “benefit of all reasonable doubts and infеrences in determining whether a genuine issue exists.” Cavanaugh v. Abbott Laboratories,
Defendants’ theory here and in the trial court focused exclusively on the March 19th date by which plaintiffs were to give notice of inability to obtain financing. Defendants ignore, however, that March 19th was also the last date for closing and that closing was to occur ten days after each unit was ready for occupancy as certified by defendants’ architect. Although it seems clear that the architect never certified when the units were ready for оccupancy, we cannot tell from the stipulation what, if
The facts are consistent with at least three theories under which plaintiffs could recover the deposit here.
Seсond, the contract may have terminated on March 19th when closing did not occur and the communications thereafter may be viewed as incomplete negotiations to establish a new contract. In this respect, the facts bear some resemblance tо those in Evarts v. Forte,
In this case, the contract specified a March 19th closing, and in the absence of an attempt to close on that date, defendants’ actions may hаve amounted only to an offer for a new contract with a different closing date. Again, additional facts are necessary to determine the status of the original contract after March 19th and the relationship between the parties.
Third, there may have beеn some kind of waiver of the notification deadline. In Meyer v. Furgat,
As in Meyer, defendants may have foregone their right to insist on notice of the unavailability of financing by extending the closing date beyond March 19th. Certainly, defendants are in the tenuous position of extending the closing date because financing had not beеn determined and insisting on the deadline for notification of the unavailability of financing. We cannot find, however, that the undisputed facts showed a waiver of the notice date as a matter of law, the requisite finding for a grant of summary judgment. See Price v. Leland,
Although we conclude that the trial court should not have granted summary judgment for plaintiffs, the rеcord does not support a grant of summary judgment for defendants. Accordingly, the case must be remanded for a fuller development of the facts for summary judgment or for trial.
Reversed and remanded.
Notes
It appears that defendants presented to plaintiffs a document entitled “Financing Terms Glen Run Condominiums” which dеscribed two alternative financing plans. Apparently, these were plans that were to be available through the Factory Point National Bank.
Apparently, plaintiffs learned of the denial by telephone call from defendant Swain on April 10th. The official notice from the bank is dated April 16th.
We agree with defendants that the trial court’s construction of the contract cannot be sustained on this record. The court held that the requirement to notify the sellers by March 19th of the unavailability of financing was triggered only if financing had been rеfused by that date and not if the financing application was still pending. We must construe a contract to give effect to the intent of the parties as expressed in their writing. See Agway, Inc. v. Marotti,
We do not preclude the possibility that trial will disclose further issues. For example, plaintiffs have assеrted that the financing source here was, in effect, an agent of defendants.
Defendants emphasize that time was of the essence in this contract in arguing that only a notice given on or before March 19th could be effective to cancel the contraсt. The fact that time is of the essence in a contract for sale of land relates only to its enforceability in equity by specific performance. Mouat v. Wolfe,
It is also possible that a new contract was formed as a result of the actions of plaintiffs in response to defendants’ suggestion of a new closing date. We do not know, however, how plaintiffs responded to defendants’ proposal. If there were a new contract, the trial court would have to determine what, if any, finance contingency clause was intended to be contained therein.
