After respondent Pajaro Valley Water Management Agency (Agency) enacted three ordinances (ords. Nos. 2002-02, 2003-01, 2004-02) that increased groundwater augmentation charges for the operators of wells in the Agency’s jurisdiction, several lawsuits challenging the constitutionality of the ordinances were filed. In 2008, these lawsuits were resolved by a stipulated agreement for entry of judgment. In 2010, appellant John G. Eiskamp filed a complaint against the Agency seeking a declaration that ordinance No. 2002-02 (Ordinance) was invalid, a refund of augmentation charges, and an order directing the Agency to cease collection of the augmentation charges. The trial court sustained the Agency’s demurrer to the complaint without leave to amend and entered judgment in favor of the Agency. We hold that the doctrine of res judicata bars relitigation of the causes of action in Eiskamp’s complaint and affirm the judgment.
I. Factual and Procedural Background
On May 31, 2002, the Agency’s board of directors (Board of Directors) approved the Ordinance, which established an augmentation charge of $80 per acre-foot for the extraction of groundwater from facilities within the Agency’s boundaries. The Board of Directors did not comply with the notice, hearing, and voting requirements of article XIII D, section 6 of the California Constitution. Eiskamp is presently a member of the Board of Directors, and was a member when the Ordinance was approved.
In October 2002, several citizens filed a reverse validation action (Scurich Lawsuit) in which they challenged the validity of the Ordinance.
In May 2003, the Board of Directors approved ordinance No. 2003-01, which increased the augmentation charge to $120 per acre-foot. The Board of Directors did not comply with the notice, hearing, and voting requirements of article XIII D, section 6 of the California Constitution.
In July 2003, the Agency filed an action entitled Pajaro Valley Water Management Agency v. All Persons Interested in the Matter of the Validity of Pajaro Valley Water Management Ordinance 2003-01 (Amrhein Lawsuit). (Italics added.) In February 2004, the Amrhein Lawsuit came on for trial.
In August 2004, the trial court entered judgment in the Amrhein Lawsuit in favor of the Agency. Shortly thereafter, the Amrhein defendants filed an appeal in this court.
In November 2004, the Board of Directors adopted ordinance No. 2004-02, which increased the augmentation charge to $160 per acre-foot. The Board of Directors did not comply with the notice, hearing, and voting requirements of article XIII D, section 6 of the California Constitution.
In January 2005, Harold Griffith filed a lawsuit challenging ordinance No. 2004-02 and other actions of the Agency in Griffith v. Pajaro Valley Water Management Agency (Griffith Lawsuit). About three weeks later, the San Andreas Mutual Water Company and others, including the Amrhein defendants, filed a lawsuit challenging ordinance No. 2004-02 in San Andreas Mutual Water Co. v. Pajaro Valley Water Management Agency and All Persons Interested in the Matter of the Validity of the Pajaro Valley Water Management Agency Ordinance No. 2004-2 (San Andreas Lawsuit).
The Griffith and San Andreas Lawsuits were consolidated with the Scurich Lawsuit under case No. 144843 (Consolidated Lawsuits).
In July 2006, this court affirmed the judgment in the Amrhein Lawsuit. After the Amrhein defendants filed a petition for rehearing, this court granted the petition to consider the effect of Bighorn-Desert View Water Agency v. Verjil (2006)
In January 2008, the Scurich plaintiffs, the San Andreas plaintiffs, Harold Griffith, and the Amrhein defendants wanted to resolve all disputes in the Amrhein Lawsuit and the Consolidated Lawsuits. They and the Agency then entered into a stipulated agreement for entry of judgment (stipulated agreement). The stipulated agreement provided: “all matters raised in the Consolidated Lawsuits and the Amrhein Lawsuit (collectively the ‘Pending Litigation’) as to the Agency’s actions shall be resolved by entry of judgment in the Pending Litigation”; the Agency would pay $1.8 million to the Scurich plaintiffs, the San Andreas plaintiffs, Harold Griffith, and the Amrhein defendants for legal fees, costs, and expenses; and the augmentation charges collected pursuant to ordinances Nos. 2003-01 and 2004-02 would be refunded. It also stated that the “settlement extinguishes any and all claims arising out of the Pending Litigation all issues, transactions and/or related claims or actions including all claims that the parties have made or could have made with respect to the validity of any Augmentation Charge or Management Fee ordinances currently in effect . . . .” The stipulated agreement did not provide for either the repeal of the Ordinance or the refund of augmentation charges imposed under the Ordinance.
In February 2008, judgment was entered pursuant to the terms of the stipulated agreement.
In August 2010, Eiskamp filed a complaint against the Agency for declaratory relief and a petition for writ of mandate. The complaint alleged that Eiskamp was a member of the public and the owner of three parcels of real property within the Agency’s jurisdiction. The complaint further alleged that the Board of Directors established the augmentation charge of $80 per acre-foot without complying with the notice, hearing, and voting requirements of article XIII D, section 6 of the California Constitution, thus rendering the Ordinance void. In May 2009, Eiskamp paid $9,024.39 and $5,516.96 that had been levied pursuant to the Ordinance in connection with two parcels of his real property. He then submitted written claims to the Agency for refunds of these amounts. These claims were deemed denied. In July 2010, the Agency sent bills to Eiskamp for augmentation charges for three parcels of his real property. The complaint sought refund of the amounts that Eiskamp had paid and an order directing the Agency to cease collecting the augmentation charges under the Ordinance.
The Agency filed a demurrer to the complaint and a request for judicial notice in support of the demurrer. Following a hearing, the trial court
II. Discussion
In reviewing an order sustaining a demurrer, “ ‘we examine the complaint de novo to determine whether it alleges facts sufficient to state a cause of action under any legal theory, such facts being assumed true for this purpose. [Citations.]’ (McCall v. PacifiCare of Cal., Inc. (2001)
The Agency contends that the trial court properly sustained the demurrer on the ground that Eiskamp lacked standing to maintain an action for a writ of mandate. Relying on Carsten v. Psychology Examining Com. (1980)
In Carsten, the appellant was a member of the psychology examining committee of the Board of Medical Quality Assurance (board). (Carsten, supra,
Carsten also acknowledged that taxpayers have standing to challenge a governmental agency’s expenditure of public funds, but concluded that the appellant lacked standing under this theory. (Carsten, supra,
In Braude, the appellant was a member of the respondent city council, a taxpayer, and a commuter on the respondent’s freeways. (Braude, supra,
Here, unlike the appellants in Carsten and Braude, Eiskamp has a “direct and substantial” beneficial interest to be protected. (Save the Plastic Bag Coalition v. City of Manhattan Beach (2011)
The Agency contends, however, that the present action is barred by the doctrine of res judicata. We agree.
“ ‘Res judicata’ describes the preclusive effect of a final judgment on the merits. Res judicata, or claim preclusion, prevents relitigation of the same cause of action in a second suit between the same parties or parties in privity with them.” (Mycogen Corp. v. Monsanto Co. (2002)
In considering this issue, we note that “[a] validation action implements important policy considerations. ‘[A] central theme in the validating procedures is speedy determination of the validity of the public agency’s action.’ [Citation.] The text of section 870 and cases which have interpreted the validation statutes have placed great importance on the need for a single dispositive final judgment.’ [Citation.]” (Friedland v. City of Long Beach (1998)
A validation proceeding is “in the nature of a proceeding in rem.” (Code Civ. Proc., § 860.) Thus, “[t]he judgment in a proceeding brought under the general validation procedure is ‘binding and conclusive . . . against the agency and against all other persons . . . .’ (Code Civ. Proc., § 870, subd. (a), italics added.) Because the proceeding is in the nature of an action against the entire world, ‘[jurisdiction of all interested parties may be had by [newspaper] publication of summons . . .’ and such other notice as the court may order. (Id., § 861.) More importantly, the general validation procedure is broad enough to include actions to invalidate public agency matters (sometimes called reverse validation actions). Code of Civil Procedure section 863 permits ‘any interested person [to] bring an action ... to determine the validity of [the] matter’ (italics added), and the phrase ‘any interested person’ might of course include a party contesting the matter in question.” (Bonander v. Town of Tiburon (2009)
Here, the Scurich plaintiffs filed a reverse validation action in 2002 in which they challenged the validity of the Ordinance. This court “validated] the $80 Augmentation Charge ... to the extent that the charge [was] used to fund capital facilities construction,” but held that the statute of limitations did not bar the Scurich plaintiffs from challenging the Ordinance to the extent
However, in 2003, the Agency filed a validation proceeding (the Amrhein Lawsuit) to determine whether ordinance No. 2003-01 was valid.
In sum, the trial court properly sustained the demurrer to the complaint and entered judgment in favor of the Agency.
The judgment is affirmed.
Duffy, J.,
A petition for a rehearing was denied February 2, 2012, and appellant’s petition for review by the Supreme Court was denied May 9, 2012, S200039.
Notes
The plaintiffs in this lawsuit were James P. Scurich, John E. Eiskamp (appellant’s son), Vincent J. Gizdich III, Dick Peixoto, and William J. McGrath.
Eiskamp concedes that there are “no legal differences” between the Ordinance and ordinances Nos. 2003-01 and 2004-02.
Eiskamp does not contend that the Agency failed to comply with the notification requirements for a validation proceeding (Code Civ. Proc., § 861).
Eiskamp cites several federal cases on res judicata, collateral estoppel, privity, and stare decisis for the proposition that he is entitled to challenge the Agency’s collection of the augmentation charges that were held invalid in Amrhein, supra,
Retired Associate Justice of the Court of Appeal, Sixth Appellate District, assigned by the Chief Justice pursuant to article VI, section 6 of the California Constitution.
Judge of the Santa Clara Superior Court, assigned by the Chief Justice pursuant to article VI, section 6 of the California Constitution.