3 Wash. 534 | Wash. | 1892
The opinion of the court was delivered by
Appellants Wakeman and Devoe were contractors and builders, and during the summer of 1889 were engaged in erecting several brick buildings in the city of Port Townsend for different owners, and for which buildings said contractors furnished the materials. Appellant Hill was one of the persons with whom they so contracted to furnish the material and erect a building upon certain real estate owned by him in said city. The respondent was engaged in the manufacture and sale of brick, and he agreed to furnish said contractors with brick during said summer. He did furnish them during said time in quantities as called for by them brick to the number of 1,061,000, and received several payments thereon. Thereafter, in the month of December, in said year, the respondent claiming $2,878.20 as the unpaid balance due him from said contractors upon their said agreement, filed a notice that he claimed a lien therefor upon the building and premises of appellant Hill, and he subsequently brought this action to foreclose such lien, and to obtain a judgment against said contractors for
Appellants claim that no lien could be had under the circumstances, and that no judgment could be rendered in such action against the contractors, especially- if the lien could not be maintained.
It appears by the respondent’s own testimony that he furnished these brick to the contractors without any regard as to where they-were going to-use them, or in what way. When the several quantitieswere obtained he had no knowledge, even, that any particular supply was going to any particular building, or-even to any building. During the same time the Hill building was being erected, said contractors were furnishing material for and working upon other buildings for various different owners, and were using the brick therefor obtained from the respondent. One of these buildings was the custom house being erected for the United States, upon which he could have had no lien, and a part of the last brick furnished went into this building. The whole quantity of brick was furnished to said contractors under a general contract, and the different lots were charged to them generally as obtained, with nothing to show for whom any of them were to be used, and the payments made from time to time were credited to them generally. While the brick was being furnished it is clear that the respondent never contemplated availing himself of any security by way of a lien upon any of said buildings, but that he furnished the same upon the personal responsi
The fact that where no particular application of payments was made by the parties the law would generally apply them to the material first obtained in the order of priority would make no difference in this case, for while the greater part of the last brick furnished went into the Hill building, a portion of it went elsewhere, and as stated it was all furnished indiscriminately without reference to
As to the further question going to the power of the court to render a judgment in favor of the respondent against the contractors, where the lien fails, it must, if it exists, be inherent in the court, as we have no statute authorizing it. Our attention was called to § 1967 of the Code of 1881 which authorizes a judgment over in case of a deficiency, where thé lien is established but even in that case it would be very difficult to say a judgment against the contractor in favor of the sub-contractor is authorized. The closing clause of this section is, to say the least, a very gem of ambiguity. What it means or what purpose it was intended to fulfill can hardly be determined by any rule of construction. The section is devoted to cases where there are different liens, fixing their relative rank and providing in conclusion, that “ whenever on the sale of property subject to the lien there is a deficiency of proceeds, judgment may be rendered for the deficiency in like manner and with like effect as in actions for the foreclosure of mortgages.” The legislature probably meant to say that judgment should be rendered leviable on other property of the judgment debtor, in case there should prove a deficiency in the proceeds to satisfy it, on the sale of the property charged with the lien. If this is the right construction, what then is the scope of the provision ? It contemplates that the judgment debtor shall be also the owner of the premises charged with the lien, and is not intended to apply to an action by the sub-contractor against the owner an d his contractor j ointly; otherwise, it provides that the property subject to the lien, which belongs to a party not chargeable with th¿ indebtedness, shall first be exhausted before the property of the judgment debtor can be reached. Certainly there can be no such intendment.
It was also claimed that the judgment was authorized by chapter 22 of the code, but it is very doubtful under all the circumstances whether the general provisions of this chapter can be held to apply to actions of this nature, and if they do apply, I do not think they can operate to authorize a judgment where no lien is found to exist, or for anything more than the lien claim when it is established. These provisions can have no force to deprive a defendant of his right to a jury trial.
As the lower court had no power in this action to render a judgment in favor of the respondent, the judgment is vacated, and the cause remanded with instructions to dismiss it but without prejudice to an action at law to recover the amount due.
Anders, C. J., and Dunbar, Hoyt and Stiles, JJ., concur.