delivered the opinion of the court:
Plaintiff, Myron Eichengreen, brought an action alleging breach of contract and negligence against defendant, Rollins, Inc., f/k/a Apollo Central Protection, Inc., resulting from a fire at his residence. The trial court granted defendant’s motion for summary judgment on both counts of the complaint. Plaintiff now appeals. We affirm.
In 1983, plaintiff purchased a residence at 100 Maple Hill Road in Glencoe, Illinois. At that time, the house included a security system that had been installed in 1980 by defendant Apollo. In 1985, plaintiff constructed a bathhouse at his property that could not be accessed through the residence, but did share one common wall with the house. The bathhouse contained a natural gas fueled water heater and a natural gas fueled barbeque grill affixed to an exterior wall. From the time of plaintiffs purchase of the residence until August 1988, defendant maintained the security system that was in place.
In August 1988, the parties entered into a contract, which is now the subject of this lawsuit. Specifically, on August 16, 1988, defendant Apollo submitted a letter, for plaintiff’s approval, containing an estimate of work to be done. The original letter listed the following items: one digital dialer transmitter; one smoke detector; five heat detectors — replace; one temperature switch — 45°; one heat detector— electrical room; one fire horn; one fire signal; and one building temperature signal. The letter also listed a price of $675 as the amount for the items as installed and additionally provided that the terms were one-half down, balance upon completion. It is undisputed that this letter became the final written contract between the parties. Plaintiff did not sign the letter, but it is further undisputed that plaintiff made the several handwritten modifications and additions contained in the letter changing the original terms proposed by defendant. Plaintiff crossed out the “temperature switch” and “fire horn” items. Plaintiff changed the “installed” price from $675 to $575 and added the notation “battery incl.” Plaintiff also аdded the term “$287.50 plus 100 for #2414 battery 8/22/88.” In addition, plaintiff inserted the following provision: “system to be in good working order and guaranteed for at least 12 months.” The system was installed sometime shortly after the letter was exchanged.
On September 13, 1995, a fire occurred at plaintiffs home. The fire originated in the bathhouse in the area of the grill. The fire activated the burglar alarm at plaintiffs residence. When poliсe officers responded to the alarm, they noticed the southeast wall of the home engulfed in flames. The police then summoned the fire department. By the time the fire department arrived, plaintiff and his wife had already exited the residence.
On December 5, 1997, plaintiff filed a two-count verified complaint against defendant. Count I alleged breach of contract. Count II alleged negligence. On March 25, 1999, defendant filed a motion for summary judgment. After full briefing and two hearings, the trial court granted defendant’s motion for summary judgment in its entirety. Plaintiff appeals the trial court’s grant of summary judgment.
In appeals from summary judgment, this court conducts a de novo review. Boub v. Township of Wayne,
Count I: Breach of Contract
On appeal, plaintiff argues that the trial court erred in granting summary judgment on plaintiffs breach of contract claim because an issue of material fact existed regarding the “intent” of the pаrties. Plaintiff contends that the “intent” of the parties was for the installation of a new security system that would provide protection for plaintiffs entire premises. Plaintiff does not rely on the terms of the written agreement in support of his assertion of the parties’ intent. Instead, plaintiff contends that “[h]e informed [defendant] that he wanted the security of having the entire home protected.” Thus, plaintiff asks this court to consider extrinsic evidence of the parties’ prior negotiations in determining the intent of the parties. He further relies on extrinsic evidence as support for the reasonableness of his subjective belief that the parties intended to enter into a contract for protection of the entire premises.
Defendant counters that the August 16, 1988, letter stands unchallenged as thе only and entire agreement between the parties. As such, defendant asserts, the terms of that letter, alone, represent the intentions of the parties.
A proper analysis of this case begins with a review of the established guidelines of contract interpretation under Illinois law. It is well settled that a court, when construing a contract, should ascertain the intent of the parties and give effеct to that intent. In re Marriage of Olsen,
“Traditional contract interpretation principles in Illinois require that:
‘[a]n agreement, when reduced to writing, must be presumed to speak the intention of the parties who signed it. It speaks for itself, and the intention with which it was executed must be determined from the language used. It is not to be changed by extrinsic evidencе.’ [Citation.]” Air Safety, Inc. v. Teachers Realty Corp.,185 Ill. 2d 457 , 462,706 N.E.2d 882 , 884 (1999).
The Air Safety court noted that this approach has been referred to as the “four corners” rule. Air Safety,
In Air Safety, the court considered the applicability of what has been referred to as the provisional admission approach. Under the provisional admission approach, in contrast to the four corners rule or the parol evidence rule, “although the language of a contract is facially unambiguous, a party may still proffer parol evidence to the trial judge for the purpose of showing that an ambiguity exists which can be found only by looking beyond the clear language of the contract.” Air Safety,
The contract at issue here does not contain an integration clause. Nevertheless, citing Air Safety, defendant contends that this court should apply the four corners rule and decide that the terms of the August 16, 1988, letter alone represent the intentions of the party. Defendant further asserts that the letter constitutes the entirе contract between the parties. Plaintiff has not directly challenged defendant’s contention that the contract is a final and complete expression of the parties’ intent. Instead, in arguing that a genuine issue of material fact exists regarding the parties’ intent, plaintiff does not address the contract principles we have outlined but, rather, presupposes that extrinsic evidеnce may be considered. Plaintiff takes no position on the applicability of the four corners rule or parol evidence rule in the present case with respect to the issue of ascertaining the parties’ intent.
In J&B Steel Contractors, the Illinois Supreme Court specifically considered the issue of “whether evidence beyond a writing itself may be considered in determining its comрleteness for purposes of the parol evidence rule.” J&B Steel Contractors,
N.E.2d at 1217. No integration clause was identified in the contract at issue in J&B Steel Contractors, which consisted of a purchase order. Based upon the nature of the document and the court’s discussion on the issue of integration, we can assume no integration clause existed. The court acknowledged that “[t]he more modеrn approach favors liberalizing the admission of evidence to determine the integration question.” J&B Steel Contractors,
Sound policy reasons exist for this rule. The Armstrong court explained the rationale for the rule as follows:
“When parties sign a mеmorandum expressing all the terms essential to a complete agreement!,] they are to be protected against the doubtful veracity of the interested witnesses and the uncertain memory of disinterested witnesses concerning the terms of their agreement, and the only way in which they can be so protected is by holding each of them conclusively bound by the terms of the agreement as expressed in the writing. All conversations and parol agreements between the parties prior to the written agreement are so merged therein that they can not be given in evidence for the purpose of changing the contract or showing an intention or understanding different from that expressed in the written agreement. [Citation.]” Armstrong Paint & Varnish Works v. Continental Can Co.,301 Ill. at 106 ,133 N.E. at 713 .
As the Armstrong court further noted:
“[T]he contentions of the parties to the contract are not the criterifa] which should guide the court in determining whether the written contract is a full expression of the agreement of the parties. The court must determine this from the writing itself. If it imports on its face to be a complete expression of the whole agreement, — that is, contains such language as imports a complete legal obligation, — it is to be presumed that the parties intrоduced into it every material item and term, and parol evidence cannot be admitted to add another term to the agreement although the writing contains nothing on the particular term to which the parol evidence is directed.” Armstrong Paint & Varnish Works v. Continental Can Co.,301 Ill. at 106 ,133 N.E. at 713 .
The J&B Steel Contractors court, after stating that, generally, a writing’s completeness as measured against it remains a legal question to be determined by the trial judge (J&B Steel Contractors,
Thus, our assessment of whether the parol evidence rule applies so as to exclude any extrinsic evidence depends upon a preliminary determination that the August 16, 1988, lettеr was a complete integration of the parties’ agreement. See J&B Steel Contractors,
Plaintiff has failed to present any evidence that defendant breached the contract. Defendant complied with the written contract terms by providing to plaintiff the system that was outlined in the letter. The system in place at the time of the fire worked рroperly and as it was designed to work on the day of the fire. The trial court properly granted summary judgment as to count I of plaintiffs complaint.
Count II — Negligence
Plaintiff further alleged that defendant owed a duty to plaintiff to place heat sensors in the areas of the house containing a possible ignition source or to inform plaintiff of the risks involved with leaving such an area unprotected so that plаintiff could make an informed decision as to whether to waive such protection. Plaintiff asserts that the trial court erred in granting summary judgment in favor of defendant by ruling that defendant did not owe a duty of care to plaintiff.
An allegation of negligence based upon a contractual obligation, although sounding in tort rather than contract, is nonetheless defined by the contract. Ferentchak v. Village of Frankfort,
Whether a duty exists in a particular case is a question of law for the court to determine. Calhoun v. Belt Ry. Co. of Chicago,
Plaintiffs allegations of negligence in his complaint mirror his allegations for breach of contract and provide that “it was the duty of the defendant to provide a security system to plaintiff sufficient to provide protection for his entire home, including the pool house attached to the main portion of the residence.” Plaintiff alleged that defendant breached its duty because defendant:
“(a) failed to provide a security system sufficient to provide protection for the entire Eiehengreen residence;
(b) failed to provide a security system with heat sensors or smoke detectors near the pool house, which was attached to the main portion of the Eiehengreen home;
(c) provided a system that was below the ‘industry standard’ at the time that the system was installed, failing to provide adequate protection for the home; and
(d) failed to provide a heat detector or smoke detector in the pool house, given the absence of protected material in the common wall which would stop a fire from spreading to the main portion of the home.”
These allegations exceed the scope of defendant’s contractual undertaking. The August 16, 1988, letter provides that defendant would “replace” five heat detectors and install one heat detector in the electrical room. Plaintiff did not allege that defendant failed to install or improperly installed the system as it was delineated in the August 16, 1988, letter.
Plaintiff further alleged in his complaint that it was defendant’s duty to “provide a security maintenance system which would properly forward a fire alarm to the fire department” and that defendant “was negligent in the security maintеnance" agreement’ ’ by:
“(a) failing to repair the security system, even though a service call was conducted on August 8, 1995;
(b) failing to repair the security system, even though a service call was conducted on August 11, 1995; and
(c) allowing the security system to remain in a defective and broken condition, such that the fire alarm was improperly routed to the police department.”
Summary judgment in favor of defendant was appropriate because defendant had not contractually undertaken any of the duties alleged by plaintiff. Moreover, no evidence was presented by plaintiff that defendant breached any of the duties it did undertake. Nor did plaintiff present any evidence that the system did not function properly or that there were any “defects.” Although a plaintiff is not required to рrove his case at the summary judgment stage, he must present some evidentiary facts in support of his cause of action. Calhoun v. Belt Ry. Co. of Chicago,
In accordance with the foregoing, the order of the circuit court of Cook County granting defendant’s motion for summary judgment as to counts I and II of plaintiffs complaint is affirmed.
Affirmed.
O’BRIEN and O’MARA FROSSARD, JJ., concur.
Notes
The court noted, however, that this rule applied in those cases which were not governed by the Uniform Commercial Code (UCC) (810 ILCS 5/1— 101 et seq. (West 1994)). J&B Steel Contractors,
