20 Md. 332 | Md. | 1863
delivered the opinion of this Court:
The decision of this appeal depends entirely upon the true construction of the contract between the parties, which is in these words: “I, the undersigned, do hereby agree to do all the carpenter’s work of the new dwelling house about to be erected on the north-west corner of Cathedral and Monument street, for D. H. Miller, in accordance with the plans and directions furnished by Niernsee and Neil-son, architects, and will do the said work in a complete and workmanlike manner at the rate of fifty peer cent, deduction from usual book of measurement prices.
“All work to be paid for as it progresses, by Niernsee and Neilson’s order to me on the said D. H. Miller. And I further agree to give due attention to the selection of all the lumber materials for the said buildings, and in case of any mismanagement on my part, it shall be at my expense.” — (Signed,)—“Emanuel W. Eichelberger.”
In the course of the trial below, the appellant asked the Court to instruct the jury, that upon these facts, he was entitled to recover under the contract- “for the work so destroyed, such an amount as the jury should find from the evidence in the case, the said work to have been worth.”
In the opinion of this.Court there was no error in refusing to give this instruction to the jury. According to our interpretation of the contract, the appellant was not entitled to demand payment for any carpenter’s work until the same was put into the dwelling house. The agreement was, “to do the carpenter’s work of the new dwelling house, in accordance with plans and directions furnished by the architects.” None of it could be considered as done or completed under the contract, till it bad been fitted into its appropriate place in the building. The stipulation that the work should “be paid for as it progresses, by Niernsee and Neilson’s order to me on the said D. H. Miller,” clearly shows this to liave been tbe intention of the parties.
There is some ground for saying that the order of the architects was a necessary preliminary to entitle the appellant to demand his pay; hut it is not necessary to express any opinion on that question. That provision in the contract seems to us clearly to import that the appellee’s obligation was to pay for the work after it had been done upon
We do not agree with the appellant's counsel, that the appellee was liable on the count for money had and received. The lumber furnished to the appellant, to be worked upon by him, continued to he the property of the appellee, was properly insured as his, and when destroyed, he was entitled to collect and retain indemnity for its loss. The appellant had also an insurable interest therein as bailee, to the value of his work done upon it, and might have protected himself from loss by obtaining a policy of insurance thereon. Not having clone so, ho must bear the loss.
Judgment affirmed.