58 Wash. 163 | Wash. | 1910
This action was commenced by J. Y. Eichbaum against Caldwell Brothers Company, a corporation, to recover $3,890 and interest, for a turbine pump sold and delivered to defendant by H. R. Worthington, a corporation, plaintiff’s assignor. From a judgment in plaintiff’s favor, the defendant has appealed.
The claim was assigned to Eichbaum for collection, he being the agent of H. R. Worthington, the vendor corporation and real party in interest, hereinafter designated as the respondent. The appellant, after alleging that the pump was to weigh 35,000 pounds; that it was to be shipped within eight weeks after August 11, 1906; that respondent failed to make any shipment until December 1, 1906, and that an inferior pump of lighter weight and construction, worth $1,500 less than the one ordered, was then shipped, further alleged:
“That because of the delay of the said Worthington in furnishing any pump at all and his then furnishing only a pump of the sort and value hereinabove set out, the defendant is damaged in the sum of four thousand three hundred dollars ($4,300), which is in excess of the plaintiff’s total claim.”
The appellant contends, that the trial court erred in admitting evidence to show that it should be estopped from interposing any claim for damages, the respondent having failed to plead an estoppel. Although it appears that the trial court admitted the evidence and regarded it as material, we will not discuss its competency, for assuming, without deciding, that it was incompetent, and eliminating it from our consideration, we have nevertheless concluded that, upon the competent evidence, the judgment must be affirmed. The cause is now before us for trial de novo, upon the competent evidence, and we will so consider it, there being no contention that any competent evidence was improperly excluded.
We find that, on Monday, August 13, 1906, the appellant executed the following order:
*165 “The Caldwell Bros. Co., Machinery Merchants.
“Date of order Aug. 13, ’06.
“To be shipped. Seattle, Wash.
“Mr. J. V. Eichbaum, Mgr. H. R. Worthington Pump Co., Alaska Bldg., Seattle.
“Gentlemen: Please enter our order for shipment upon above terms. Ship to ourselves at Seattle, Route N‘. Y. C., Lake Shore, C., M., St. P. & U. P.
“One 4-stage Turbine pump with a capacity of 4,000 gals, per minute, designed for head 430 ft. under conditions as explained to Mr. Eichbaum with brass impellers and shaft;
“Instructions later as to whether this pump will be belt or rope driven.
“Shipment eight weeks from Aug. 11th, 1906.
“Guaranteed weight 35,000 lbs.
“Confirmation of verbal order given you by Mr. Mather.
“The Caldwell Brothers Co.
“GFK—J. By John Mather, General Manager,”
that on the preceding Saturday the probable weight of the pump was discussed with reference to its capacity and with reference to the freight charges; that the respondent had not theretofore manufactured a pumpi of the capacity contemplated; that not knowing its probable weight, the parties agreed upon 35,000 pounds as guaranteed in the order; that the respondent did not manufacture the pump within the time agreed; that on November 20, 1906, appellant’s president called upon the respondent in New York City, and learning that the manufacture of the pump had not yet been commenced, without expressly waiving any rights, then urged the respondent to manufacture and ship it as soon as possible ; that respondent did so, making the shipment on December 1, 1906; that it reached Seattle fifty-six days later than it would had it been shipped at the time stipulated; that the appellant received the pump, but was unable to install or use it for several days thereafter, as a necessary concrete foundation had not been prepared to receive it; that before receiving the pump, appellant learned from the bill of lading and other sources of information, that it weighed not more than
Although no estoppel was pleaded, the trial court held the appellant was estopped from' claiming damages, because it knew the actual weight before receiving the pump, and because it urged the respondent to manufacture and ship the pump after the time for shipment had expired. If the appellant did in fact sustain damages resulting from light weight, it was entitled to receive the pump actually shipped, and when shipped, recoup its losses by pleading its damages in this action. By accepting a pump of lighter weight, it only waived its right to insist upon the delivery of a pump weighing 35,000 pounds as guaranteed, but did not waive its right to any resulting damages which it sustained. In other words, if the pump weighing 27,400 pounds and actually received was less valuable than a similar pump weighing 35,000 pounds, appellant was entitled to recover such difference in value by recoupment in this action. If, however, it was equally valuable, notwithstanding its lighter weight, no damages resulted and no recovery therefor could be sustained.
At the time the order was given, the parties did not know the actual weight of a pump of the capacity desired and ordered. Evidence admitted disclosing such lack of knowledge was competent, not to vary the terms of the written' contract, but as bearing upon any information the parties had, at the date of the order, as to whether 35,000 pounds weight was necessary to insure the stipulated capacity and power, appellant having waived the warranty as to weight
Shipment of the pump was delayed for fifty-six days. Appellant offered evidence to show that the fair rental value of the pump was $50 per day, and now claims $£,800 damages for rentals lost. A vendee injured by the breach of a vendor’s contract to manufacture, sell, and deliver personal property within a specified time, is entitled to recover damages therefor, including gains prevented as well as losses sustained; but such damages to be recoverable must be actual and certain and must constitute such a loss as might be expected to naturally follow, or directly result from the breach. Mr. Mechem, at § 1757, of his work on Sales, citing Hadley v. Baxendale, 9 Exch. 341, and Griffin v. Colver, 16 N. Y. 489, 69 Am. Dec. 718, leading cases, says:
“The general rule governing the allowance of damages for breach of contract generally has in, view the two conditions referred to in the preceding section. As stated in substance in the famous English case of Hadley v. Baxendale, and in the American case of Griffin v. Colver, that rule is this: The party who has broken his contract is liable to make compensation to the other for all such losses resulting from that breach as are either-—■
“(1) The ordinary, the usual, the commonly-to-be-expected consequences of such a breach of such a contract; or
“(£) The peculiar or unusual consequences of the breach of the particular contract in question, if, under the circumstances, it can fairly be said that both parties had those consequences in their contemplation, at the time the contract was made, as a probable result of its breach; and if those unusual consequences are neither uncertain in their nature nor remote as to their cause.”
“The broad general rule in such cases is that the party injured is entitled to recover all his damages, including gains prevented as well as losses sustained; and this rule is subject to but two conditions: the damages must be such as may fairly be supposed to have entered into the contemplation of the parties when they made the contract, that is, must be such as might naturally be expected to follow its violation; and they must be certain, both in their nature and in respect to the cause from which they proceed.”
The theory upon which the appellant contends it is en-. titled to rents is that profits for the use of a pump could not be readily shown, but that the value of the rents could. Rents are therefore demanded as compensation in lieu of profits lost. There is nothing in the record to show that any such damage could have been within the contemplation of the parties when making the contract, or that they were actually sustained. The evidence does show that the pump was received before the appellant was ready to use it, or could use it. It is therefore manifest that appellant sustained no actual, loss as a result of delay in shipment. Before it could recover rents as damages, it should in any event have shown an opportunity to actually rent the pump had it been promptly shipped. Wagner v. Corkhill, 40 Barb. 175. We are unable to find that the appellant has sustained any damages in the actual value of the pump, or in the delay in shipment.
The judgment is affirmed.