delivered the opinion of the court.
On March 6, 1967, the plaintiffs brought suit against the defendant in the Circuit Court of McHenry County for an alleged breach of a written contract executed by them on May 10, 1965. Paragraph one of the complaint alleged that by the terms of the contract the defendant agreed to “furnish” a subdivided lot and “all the materials and
The written contract does not contain the express provision that the construction would be done in “a substantial and workmanlike manner” as alleged in the complaint but does state that it included “. . . all labor, material and services of every kind necessary for the proper performance of the work in accordance with the plans and specifications. . . .” The contract also provided that the construction would be completed by August 15, 1965, and that the plaintiffs would not be entitled to possession of the home until they indicated “acceptance of the work by the execution of an appropriate receipt” and complete payment.
The matter proceeded to trial, with a jury waived. Henry J. Ehard testified that construction commenced in June, 1965, and that he visited the site weekly thereafter. The original plans specified that the heating would be forced warm air “. . . of sufficient capacity to heat (the) home” but the parties subsequently agreed to use a hot water system in place of hot air. In late August, Ehard went to the home with a salesman employed by the defendant and advised him that it was necessary that he obtain possession immediately although construction was not completed. Although, Ehard wanted
“This is to certify that we have inspected the above-captioned building and find it fully completed in a first class workmanship-like manner, everything is in perfect working order and all work and materials are acceptable.
“We herewith accept the above building and authorize you to make complete disbursement to the builder from our loan proceeds.
“We understand labor and materials are guaranteed only for a period of one year (1 year) from this date; . . . .”
Ehard testified that he signed the direction with the verbal agreement with the defendant that all defects would be repaired. David Ladd, the secretary of Pistakee Builders testified that although he was not personally present at the conversation on August 28, such an arrangement was not unusual.
In November, 1965, Ehard first discovered that he could not adequately heat the house, that some rooms were too cold and others too hot and he complained to the defendant. Since the heating subcontractor who had installed the system was out of business, the defendant directed James Althoff, a heating subcontractor, to inspect the system and make all necessary corrections. Althoff found that the boiler was of insufficient size and on December 5, 1965, installed a new, larger boiler, additional radiators and three zone valves. Ehard was still dissatisfied and in a conversation with Althoff lost
In October, 1966, Ehard employed C. E. Ellison to inspect the heating system and make the necessary corrections to adequately heat the home. Ellison made a chart of the home, computed the necessary BTUs to heat each room and installed an additional 55 feet of baseboard radiation pipe, an increase of almost 50% of the pipe previously installed. Ehard paid Ellison’s bill in the amount of $674.48 and testified that the home was properly heated thereafter.
The presiding magistrate at the trial prepared and filed a memorandum opinion on May 21, 1968, that found that the plaintiffs had not waived their rights to have any defects repaired by their direction of August 28, 1965; that the heating system as installed by the defendant was in fact defective; that the defendant had the obligation to repair the defects and failed to do so; and that as a result the plaintiffs were damaged in the amount of $693.11, being the bill paid to Ellison and an additional $18.63 for some other expenditures by them. The memorandum also added that the action was one brought for “breach of implied warranty of fitness.” Judgment was entered in favor of the plaintiffs in the amount of $693.11 on June 21, 1968, and after post-trial motions were denied this appeal was filed.
The defendant contends that (1) the contract contained no express warranties in regard to the construction of the home and that Illinois does not recognize the existence
An exception to the general rule of caveat emptor in the sale of real estate has gained recognition in a number of jurisdictions in cases of new construction. In those jurisdictions, the courts have found an implied warranty by the builder-vendor that the house will be constructed in a substantial or workmanlike manner or will be habitable when completed. A useful discussion of the doctrine and review of the decisions is contained in 25 ALR3d 383. We agree with the defendant that some clarification on the point is needed in Illinois. In Week v. A:M Sunrise Const. Co., 36 Ill App2d 383,
It is undisputed that the parties agreed on August 28, 1965, that the plaintiffs would take possession of the house prior to completion and that the defendant would
It is true that a party to a contract may not complain of the nonperformance of the other party where that performance is prevented by his own actions. Eggan v. Simonds, 34 Ill App2d 316, 320,
We further find that the determination of the trial court that the heating system was defective is amply
Finally, the defendant complains that the trial court excluded evidence of an accord and satisfaction. During the testimony of Ehard and Ladd, the attorney for the defendant questioned them relative to a meeting in the spring of 1966 between the parties and their respective attorneys. Objections were sustained that the conversation at the meetings was privileged as an attempt to compromise the dispute. No offer of proof was made by the defendant so we are unable to consider the validity of the contention. People v. Dorsey, 66 Ill App2d 441, 444,
We conclude that the decision of the trial court was in all respects correct and should be affirmed.
Judgment affirmed.
MORAN, P. J. and SEIDENFELD, J., concur.
