204 Wis. 60 | Wis. | 1931
Lead Opinion
The following opinion was filed January 13, 1931:
The plaintiff alleges as error (1) the dismissal of the complaint as to the defendant landowners and (2) the granting of the new trial as to the defendant contractor, and contends that upon the verdict he is entitled to judgment against the contractor upon the cause of action based upon the alleged agreement of the contractor to protect his building.
(1) Neither party requested submission to the jury of any question respecting ownership or adverse possession of the ten-inch s,trip. Under sec. 270.28, Stats., these questions were submitted to the court for determination. The possession by Pantzer of the strip was all that the situation permitted. No one else was making any claim adverse to him. We consider that the finding of adverse possession made by the court as above stated is supported by the evidence and that his conclusion that the defendant landowners owned the strip was correct. The defendant landowners were thus adjacent landowners. They owed no duty to plaintiff of lateral support of his building. Their only duty was to give timely notice to plaintiff of their .intention to excavate and that he protect his building. Schaefer v. Hoffman, 198 Wis. 233, 238, 223 N. W. 847. This duty they performed. It then devolved upon the plaintiff to protect his building, and he became liable to the defendant landowners for any injuries sustained by them as a result of his failure to do so. The undisputed evidence shows their damages to have been as above stated. The defendants being adjacent owners, there is no occasion to consider whether the removal of the soil of the strip would have given plaintiff any right of action had the strip been owned by a third party.
(3) The defendant contractor moved for review of the order for a new trial pursuant to sec. 274.12, Stats. It claims that its motion for a directed verdict should have been granted, and that, its motion having been denied, the answers of the jury to the questions submitted should have been changed upon its motion after verdict and judgment rendered dismissing the complaint and awarding damages upon its counterclaim. The trial judge carefully considered this contention. While the plaintiff doing absolutely nothing towards securing protection of his building from before three o’clock of the afternoon of August 1st to nine-thirty the next morning, when he knew that his building was in danger, that it looked shaky and that it was time to do something to save it, seems hard to reconcile with due diligence or common sense, the jury found the interval was not a reasonable time to enable plaintiff to save his building; the trial judge was of opinion that whether due diligence would have saved the building was a jury question, and we cannot say that it was not. It has so often been held,.in effect, that when reasonable minds may honestly differ upon full and fair consideration of the evidence as to the conclusion of fact to be drawn from it, it is for the jury to draw the conclusion, that it is not necessary to cite authority for the
(4) The contractor further contends that by negotiating with it for protection of his wall after he knew it would not underpin it for $25, the plaintiff abandoned his right to stand upon the $25 contract if it existed. This is untenable. Abandonment rests upon intent, and the plaintiff’s intent was a jury question. Gessler v. Erwin Co. 182 Wis. 315, 340, 193 N. W. 363.
The contractor is entitled upon its motion for review to relief in one respect. The jury found it was not negligent in its manner of excavating. This determined the plaintiff’s alleged fourth cause of action in the contractor’s favor and it should not be required to relitigate the issue of negligence. The order for a new trial should be modified to limit the retrial to the issues arising under plaintiff’s alleged fifth cause of action and defendants’ counterclaim.
By the Court. — The order is modified as indicated in the opinion and as modified affirmed.
Dissenting Opinion
(dissenting). I concur in the opinion of the court except upon one point. I am of the view that the evidence in this case is insufficient to sustain a finding that there was a contract between the plaintiff and the defendant Verhulst Company, and for that reason the complaint should be dismissed as to the Verhulst Company.
A motion for a rehearing was denied, with $25 costs, on March 10, 1931.