61 F. 527 | S.D.N.Y. | 1894
The bills of lading required delivery of the cargo “as soon as possible.” This is equivalent to a provision for quick dispatch in unloading, and required the consignee to make use of all the means of discharge that were readily available; it did not admit of a detention of the vessels for such a disposition of the cargo as merely suited the convenience, or the business purposes, of the consignor and consignee.
Each libelant had two canal boats loaded with wood. Egan’s two boa ts arrived at Saugerties on the 29th of June. The defendant had a slip there in Esopus creek, and on each side of the slip were suitable places for the discharge of wood. Under such a stipulation in the hill of lading, I think it was the duty of the consignee to admit of the discharge of the two vessels at both places at the same time, on the two opposite sides of the slip; and to supply men enough to remove the wood as fast as it was put upon the wharf by the vessel’s men. The defendant, for its convenience, allowed the discharge on one side of the slip only, where a car track could he made use of for removing the wood to a shed some five or six hundred feet distant,; and the second boat had, therefore, to wait: until the first was discharged.
The libelant chose to employ hut four men to unload his wood. His witnesses testified that these were sufficient to remove the wood in two days. But what the men hired were capable of do
There was no delay in the preparations for unloading after the arrival of Egan’s boats on Thursday, the 29th of June. Work was begun on Friday the 30th; on Saturday the men worked three-quarters of a day only. As July 2d was Sunday, and the 4th a holiday, three days for unloading 110 cords would carry the unloading of the first boat, to the forenoon of the 5th. The deck load of the second boat being previously removed, her discharge was completed upon the 7th. The first boat should, therefore, have been fully discharged by the forenoon of Wednesday the 5th; and the other boat by the same time, on the opposite side of the creek. This libelant is, therefore, entitled to two days’ demurrage on both boats, which I find to be of the value of $6 each per day, including the men, making $24, or with interest, $25.20.
Mr. Smith’s two boats arrived with about 83 cords each on the 30th of June. The defendant is not responsiblé for the delay caused by the use of the wharf by Egan’s boats up to the time when his two boats should have been discharged, viz., by noon of the 5th of July. Mr. Smith employed the four men previously employed by Egan, and began discharging on the 7th, as soon as Egan’s boats were unloaded. Upon the rule above stated, each of these boats should have been discharged in two and a half days, on the opposite sides of the slip, and the discharge completed by the night of Friday the 7th. The discharge was not completed until the 13th. Smith is, therefore, entitled to six days’ demurrage on his two boats, amounting, at the same rate, to $72, adding interest, $75.60.
Decrees may be entered accgrdingly, with costs.