Educators Associates, Inc. v. United StatesEducators Associates, Inc. v. United States
This is a government contracts ease in which plaintiff seeks an equitable adjustment to the contract price (or, in the alternative, reinstatement of the contract) on two separate claims: (1) defendant wrongfully terminated the contract for default; and (2) defendant negligently prepared the bid documents and grossly underestimated its requirements under the contract. Defendant moves to dismiss the first claim for lack of subject matter jurisdiction; it moves to dismiss the second on summary judgment. Both of defendant’s motions, now before the court, are allowed.
BACKGROUND
In October 1992, plaintiff was awarded a fixed-price requirements contract to provide test examination services to the Department of the Army and operate testing centers, learning centers, and computer assisted instruction centers at Fort Campbell, Kentucky. The contract was for one year, beginning in November 1992, with the next four years renewable at one-year options. Plaintiff performed the base year, one option year, and two months of the second option year before the contracting officer terminated the contract for default effective January 1, 1995.
' The contracting officer’s termination notice stated, “this is the final decision of the Contracting Officer.” (Compl.Ex. 6) The notice also informed plaintiff of its right to appeal to the Board of Contract Appeals or the United States Court of Federal Claims and set forth the appropriate time periods for appeal. On March 9,1995, plaintiff filed with the contracting officer a certified claim challenging the termination for default. Plaintiff amended the claim on March 16, 1995, to include claims for additional compensation for providing testing, copying, and transportation services in excess of the contract estimates.
The contracting officer did not reconsider plaintiffs contract termination claim. Instead, by letter dated July 10, 1995, the contracting officer referred plaintiff to the earlier termination notice dated January 1, 1995, and restated the time periods during which plaintiff could file suit in this court. Additionally, in this letter dated July 10, 1995, the contracting officer denied plaintiffs claims for additional compensation. As to these claims, the contracting officer stated, “this is the final decision of the Contracting Officer in regards to the claims concerning excess copier use, excess transportation and excess examinees.” (Compl.Ex. 9) He also noted the times to appeal this decision.
Plaintiff filed suit in the United States Court of Federal Claims on July 8, 1996. Defendant subsequently filed a motion to dismiss plaintiffs claim for wrongful contract termination due to lack of subject matter jurisdiction, arguing that plaintiff filed its claim too late under the Contracts Disputes Act. Judge Robinson heard oral arguments on February 24, 1997, but did not issue an order at that time, instead, allowing the parties an opportunity to settle the case.
DISCUSSION
I. Motion to Dismiss
In considering defendant’s motion to dismiss for lack of subject matter jurisdiction, the court must accept as true any undisputed allegations of fact made by the non-
Jurisdiction in this case is based on the Contracts Disputes Act of 1978, 41 U.S.C. § 609(a), which allows plaintiff to directly appeal a final decision of the contracting officer to the United States Court of Federal Claims. See 41 U.S.C. § 609(a)(1) (1994). Plaintiff, however, must file suit within twelve months of receiving the contracting officer’s final decision' or the court no longer has jurisdiction over the claim. See 41 U.S.C. § 609(a)(3) (1994); Seaboard Lumber Co. v. United States,
Defendant’s argument, in challenging jurisdiction, is simply one of timing. Plaintiff received the contracting officer’s final decision to terminate the contract via certified mail on January 4, 1995. Plaintiff did not file its complaint in this court until July 8, 1996, a year and a half later. Since plaintiffs complaint is six months too late, it must be dismissed for lack of jurisdiction.
Plaintiff, however, contends that the twelve-month time period does not begin to run until July 10, 1995, the date on which the contracting officer issued the final decision after plaintiff submitted its claim contesting termination. Plaintiff argues, in effect, that the horse must come before the cart. That is, the contracting officer cannot issue a final decision until plaintiff first files a certified claim with the contracting officer asking for relief. How, plaintiff asks, could the contracting officer issue a final decision on a claim when no such claim had been presented?
This court, however, rejects plaintiffs argument and holds that a default termination notice labeled as a final decision fulfills the statutory requirements of the Contracts Dispute Act and triggers the twelve month running of time in which plaintiff may file claim with this court. See Malone v. United States,
In 1994, Congress amended our jurisdictional statute and expressly granted this court power to hear contract termination disputes irrespective of claims for money damages. See 28 U.S.C. § 1491(a)(2) (1994) (granting jurisdiction over claims “including a dispute concerning termination of a contract ... and other nonmonptary disputes on which a decision of the contracting officer has been issued”). Prior to this amendment, however, the federal circuit had already held that a contracting officers’ decision to terminate the contract for default “falls precisely within the contours” of the Contracts Disputes Act and is immediately appealable even without first submitting a claim to the contracting officer. Malone,
In considering plaintiffs claim challenging contract termination, plaintiff received the contracting officer’s final decision on January 4, 1995. It is this date, and not the later July 10th date, that triggers the running of the statutory clock. Plaintiff had
The court, however, retains jurisdiction over plaintiffs claims for excess testing, copying, and transportation expenses. As to these claims, plaintiff timely filed suit. The claims for excess costs were not subject to the contracting officer’s final decision until July 10, 1995, and plaintiff filed suit in this court on July 8, 1996; this is clearly within the twelve-month period. These claims, however, are further subject to summary judgment analysis below.
II. Motion for Summary Judgment
Plaintiff contends that it was required to administer twice as many tests, produce twice as many copies, and travel many more miles than defendant estimated its requirements would be under the contract.
Assuming, as plaintiff contends, that defendant’s requirements increased, the question for the court is whether defendant negligently prepared the bid documents, or whether, in the absence of negligence, it grossly underestimated its testing, copying, and transportation requirements so as to render the resulting contract unconscionable. On this issue, defendant is entitled to summary judgment.
Summary judgment is appropriate when there are no genuine issues of material fact and the moving party is entitled to judgment as a matter of law. See RCFC 56(e); Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247,
In a solicitation for a requirements contract, the contracting officer must provide a realistic estimate of the quantity of goods or services to be procured under the contract. See 48 C.F.R. § 16.503(a)(1) (1997).
Courts have held that even great disparities between estimated and actual quantities do not afford plaintiff relief. See Medart,
In the instant case, this court recognizes that plaintiff’s presentation of quantity variance (if believed) shows a significant gap between the estimated and actual requirements. Plaintiff, however, must go further than merely point this out to the court in order to establish a genuine issue of material fact that defendant acted inappropriately. See Medart,
This case is unlike those cited above in which the government withheld information from the bidders. Here, there is no evidence defendant knew of any information that would have affected its requirements. Even if the court were to conclude that defendant knew, prior to bidding, that a new counting method was to be instituted, this information would not have been material to the bidding process. The old method required plaintiff to count a three-part test as one test; the new method required plaintiff to count a three-part test as three separate tests. Even if defendant deliberately withheld this information, the fact that plaintiff would later be required to count the tests differently did not increase its workload. No matter how the tests were counted, plaintiff was still required to administer the same three-part test.
The court also recognizes that defendant acted reasonably when it calculated its estimates within the parameters of Federal Acquisition Regulation 16.503 and based its estimates on past requirements. See 48 C.F.R. § 16.503(a)(1) (1997); see also Medart,
The court also notes that, on the facts of this case, the disparity between estimated and actual testing quantity does not rise to the level of uneonscionability. An unconscionable contract is one “which no man in his senses, not under a delusion, would make, on the one hand, and which no fair and honest man would accept on the other.” Hume v. United States,
The parties raise an additional argument that is limited to transportation costs. Plaintiff contends that Mi’. Faires, a contracting officer representative, authorized additional transportation expenses. Defendant contends that Mr. Faires did not have actual authority to approve such expenditures, and, therefore, the government incurs no liability. For the government to be bound, the person who enters into or modifies the contract must have actual authority. See Janowsky v. United States,
Notwithstanding, the law discussing authority is inapplicable because the transportation expenses at issue did not necessitate contract modification. Pursuant to the contract terms, plaintiff was required to provide “transportation required to pick up and deliver publications, materials, and equipment used by the Testing Center, Learning Center, and CAI Center.” (Def. Mot. Summ. J., App. at 20, Contract ¶ C.4.1.3.) Neither plaintiff nor defendant provides any evidence that the actual transportation provided constituted anything other than requirements under the contract. The record reflects the following: plaintiff was required “to pick up mail and to travel to locations around Fort Campbell, which exceeded Educator’s courier requirements under the contract,” (PL Reply to Def. Mot. Summ. J., App. at 3, Bruce Wilson Aff.); it was required to “make distribution runs for the Education Branch,” (id.)-,
As to whether or not plaintiff sufficiently proved its economic damages, this court need not decide as plaintiffs claims fail for the above stated reasons.
CONCLUSION
For the reasons stated above, the court grants defendant’s motion to dismiss plaintiffs claim challenging the contracting officer’s decision to terminate the contract for default. Additionally, the court grants defendant’s motion for summary judgment pertaining to plaintiffs claims seeking compensation for testing, copying, and transportation expenditures.
IT IS SO ORDERED.
Notes
. Defendant contends, in its motion for summary judgment, that "the Court issued a bench ruling granting the Government’s motion to dismiss, in part.” (Def. Mot. Summ. J. at 2.) Review of the transcript, however, indicates that the judge issued no such order. Instead, the judge merely suggested, albeit strongly, that dismissal "would be my ruling in the mater (sic).” (Tr. at 18.) The judge suggested that the parties “come to some reasonable understanding on this so that the case can be completely disposed of” via stipulation of dismissal. (Id.) Again, the judge stated, ”1 won’t issue a decision in this case, because obviously if you can settle it, and you can get a stipulation for dismissal, that is all the Court would need.” (Tr. at 19.) Since neither an order nor stipulation of dismissal has been entered in this case, this court now considers defendant’s motion to dismiss in addition to its motion for summary judgment.
. The following chart summarizes plaintiff’s comparison of estimated and actual counts:
Estimated Count
Tests Administered 13,200 tests per year
Copies Provided 52,000 during the contract
Transportation 15 miles per day
(PI. Reply Def. Mot. Summ. J., App. at 2-3.)
. Federal Acquisition Regulation 16.503 states, in pertinent part:
For the information of offerors and contractors, the contracting officer shall state a realistic estimated total quantity in the solicitation and resulting contract. This estimate is
Actual Count (approx.)
27,300 (1st yr: Nov.’92-Oct.'93)
24.000 (2nd yr: Nov.'93-Oct.'94)
2,500 (3rd yr: Nov.’94-Dec.’94)
’"“contract terminated Jan. 1, 1995
126.000 during the contract
100 miles per day
not a representation to an offeror or contractor that the estimated quantity will be required or ordered, or that conditions affecting requirements will be stable or normal. The contracting officer may obtain the estimate from records of previous requirements and consumption, or by other means, and should
48 C.F.R. § 16.503(a)(1) (1997).