Edmonds v. StrattonEdmonds v. Stratton
Plаintiffs are partners engaged in the bulldozing business and defendants, husband and wife, are owners of the realty where plaintiffs undertook to ply their trade. Part of plaintiffs’ services were performed on an hourly basis and part were rendered under a $1200 lump-sum oral contract. Defendants have appealed from the judgment entered in this court-tried case which awarded plaintiffs $1587 on their petition and defendants $563.10 on their counterclaim. After off-setting the awards, a net judgment was entered for plaintiffs in the sum of $1023.90. The lone point made by defendants on appeal is that the trial court “erred by applying an improper measure of damages, that is, by allowing [plaintiffs] to recover on the contract and also allowing [defendants] to recover on the oral contract; the correct measure of damages should have been the loss of the bargain and applied in favоr of [defendants].” Three cases dealing with total failure of performance are cited to this point, namely, Norman v. Vandenberg,
Oral arguments by both parties are encouraged by appellate courts because they often assist the court to a fuller understanding of the theories of the parties and the issues on appeal. Quinn v. St. Louis Public Service Company, Mo.,
This case started as a suit on “a stated account.” Defendants’ answer denied the account and convoyed a counterclaim whiсh alleged that pursuant to the oral contract plaintiffs had agreed to bulldoze 15 acres of defendants’ land in accordance with certain specifications for $1200. The counterclaim also averred that while plaintiffs had partly accomplished the “bulldozing agreed,” the work did nоt conform to the contract and “was done in an unskillful and unworkmanlike manner,” all to defendants’ damages in the sum of $1973.10. Plaintiffs’ reply admitted the contract but generally denied the balance of defendants’ pleading. Thereafter, plaintiffs filed an amended petition wherein they adopted the oral contract “as outlined in defendants counterclaim.” Because of the construction of the amended petition and its commingling of averments anent the contract work and that performed on an hourly basis “at the agreed price of $14.00 per hour,” which was also said to be “the reasonable value of the work performed” by the plaintiffs, we are uncertain whether plaintiffs were declaring on the agreement to recover the contract price, in quantum meruit to recover the reasonable value of their services, or alternately (Civil Rules 55.06 and 55.12, V.A.M.R.; §§ 509.050 and 509.110, V.A.M.S.) on both the contract and in quantum meruit. It is to be noted, however, that although a plaintiff may not ordinarily declare upon an express contract and recover on some other agreement [Robson v. United Pacific Insurance Company, Mo.,
Defendants’ answer denied the material allegations of the amended petition, affirmatively pleaded and prayed for damages in the amount of $1973.10, reaffirmed the countеrclaim, denied that plaintiffs had been discharged, and alleged “that plaintiffs walked off the job and removed their equipment” before their task was finished. On the day of the trial defendants amended their answer and coun
*232
terclaim “by reducing amount claimed to $563.10.” Albeit was not done intentionally, it would seem thаt by generally denying plaintiffs’ petition and by pleading their damages affirmatively both by answer and counterclaim, defendants simultaneously pursued divergent courses. Under the general denial, defendants were entitled to establish, if they could, that the value of plaintiffs’ services was less than plaintiffs claimеd. Service Construction Company v. Nichols, Mo.App.,
Plaintiffs’ testimony was to the effect that they had fully discharged their contract obligations and had expended 87 or 88 hours of labor in so doing. It was demonstrated that plaintiffs’ claim for $1200 came “close to $14.00 an hour” for the *233 timе spent on the project and one witness opined that considering the type of equipment plaintiffs had used, they had done “a pretty good job.” Plaintiffs related that defendants had voiced no complaints concerning their efforts until “we finished the job” and then defendants “became completely unsatisfied with the work” and refused to pay for anything. To the contrary, the defendant-husband said “[i]t was * * * the most incomplete, horrible job I had ever seen” and that plaintiffs “never once stated that they had completed the job.” According to defendants and their witnesses, defendants were required to and did employ one Chris Johnson to do “the work as it should have been done originally” by the plaintiffs. Defendants paid Johnson $1763.10 for his services. It was Johnson’s expert opinion that “the reasonable bid for this [entire] job * * * would have been $3,000.” Early in defendants’ endeavors to prove their case, and uрon what now appears to be the ill-advised insistence of counsel, the defendant-husband was urged to and did agree that “[y]ou are asking the Court for the difference between [the $1763.10] you paid Mr. Johnson and what your [$1200] contract was [with the plaintiffs], which [is] $563.10.” Isolating this statement in the shadow cast by defendants’ single appeal point and the citations penned in their brief, we envision that defendants were then undertaking to establish that plaintiffs had wholly failed to perform the contract or that plaintiffs’ work was so defective as to be worthless and tantamount to a total failure of performanсe. This, of course, tacks in a direction different from the pleadings and other proof dealing with the degree and quality of plaintiffs’ actions. By their answer and counterclaim defendants acknowledged “that the plaintiffs did a portion of the bulldozing on said fifteen acre tract,” and, to say the lеast, the evidence produced by both sides attests to this fact. In addition, defendants argue in their brief that the $1763.10 paid to Chris Johnson “was the reasonable sum necessary to complete the job,” (our emphasis), and conclude that the “trial court felt that the work done by the [plaintiffs] was of some benefit to [defendants].”
When one party to a construction contract or to a contract for the furnishing of labor and services is compelled to relet the work to another because of the
total
failure of performance by the other contracting party, his measure of damages is generally the differеnce between the contract price and the reasonable price he is compelled to pay on the reletting. Noonan v. Independence Indemnity Co.,
In our attempt to analyze defendants’ position оn appeal, we conclude they have fallen into error by failing to distinguish between the fact of performance and the quality and quantity of performance. Brush v. Miller, Mo.App.,
Defendants’ assignment on appeal, though it lacks much to be desired under Civil Rules 83.05(a) (3) and (e), V.A.M. R., may have been proper had the proof and pleadings established total failure pf performance by plaintiffs. Such, however, was not the case. Defendants, in the circumstances shown, received all the relief they sought and defendants’ failure to ask for more, if they deserved it, was not the fault of the trial court.
The judgment is affirmed.