53 Ga. App. 145 | Ga. Ct. App. | 1936
Lead Opinion
Eatonton Oil and Auto Company brought suit against Greene County to recover for the cost of gas, oil, etc., which the plaintiff had furnished to E. S. Taylor Incorporated, and which went into the construction of a road which E. S. Taylor Incorporated was building under a contract with Greene County and Oconee County. The plaintiff brought the suit in three counts as will hereinafter be more particularly set out. The undisputed facts were about as follows: Greene County made a contract with the State Highway Board for the construction of a road designated as Project 228-A on Route No. 15. One of its terms required the county to work twenty convicts (with two guards) on the proposed road. The county then contracted with R. S. Taylor Incorporated to do certain excavating, clearing and grubbing, top-soiling and concrete work, according to the plans and specifications of the highway board and under their direction. Taylor further agreed to employ in the "work, on every day that work was done, twenty convicts and two guards, each convict to be paid at the rate of $1.50 per day and each guard at the rate of $2.50 per day; and to furnish a surety bond conditioned on compliance with the terms of the contract, etc., "which bond shall be construed to be a compliance with the acts of the legislature approved August 19th, 1916,” and that the county should have the option to pay each estimate of work done (made by the highway board) on the first of each following month, at a discount of eight per cent.; and that the county should have the option to furnish money to meet pay rolls, pay for material, etc., before estimates were made, such sums to be deducted
After this the Eatonton Company continued to supply gasoline, etc., to the Taylor Company. On February 1, 1932, Eatonton Company solicited of the county a part payment on the order of January 14. After considerable discussion between the parties in which some question was raised as to the liability of the county, the county paid $1800 to the Eatonton Company itpon receiving from it a paper acknowledging payment of the $1800 as a credit on the
The Eatonton Company continued to supply gasoline, etc., to the Taylor Company until March 23, 1932, when the total amounted to $5433.81. The Eatonton Company rendered a bill to the county, payment of which was refused, and suit was brought against the county and the county commissioners. The petition was in three counts, the first being predicated on the acceptance of January 14, 1932, on which it was alleged a balance of $1753.96 was due, after crediting the $1800 paid the plaintiff on February 1. The second count sought recovery of this $1753.96 on the ground of the liability under the act of August 19, 1916 (Ga. L. 1916, p. 94, Code of 1933, § 23-1705 et seq.) imposed on any county or other public body which contracts for a public work without taking bond from the contractor. The third count, based on the same statutory liability, alleged that $1879.85 worth of gasoline, etc., was supplied to the Taylor Company between January 1, and March 23, 1932, of which an amount worth $939.92 was used in an Oconee County project, leaving a balance due the plaintiff of $939.93. This count was amended, allegedly to correct an error, so as to claim that the amount of gasoline diverted to Oconee County was $474.42, whereby the amount due the plaintiff under this count was $1405.43. A further amendment of counts 2 and 3 claimed that the $474.42 collected by the plaintiff from Oconee County, if not allowed ás a credit to Greene County against the account sued for in count 3,
The county answered count 1, admitting that bond was not given by the contractor, admitting acceptance of the order of January 14th, denying that any sum was due thereunder to the plaintiff, and setting up the receipt of February 1, -as a complete release from liability of any sort on account of materials furnished by the plaintiff to the contractor except such sums as might be due under the original order; alleging that no amount had become due under such order, and denying that gas and oil were such materials as the county would be liable for by reason of failing to take bond from the contractor. Counts 2 and 3 of the petition were answered in substantially the same terms as count 1, with the additional claim that the order and acceptance of January 14, constituted a special contract by which the plaintiff waived the failure of the county to take bond from the contractor.
The case was referred to an auditor, who found $1278.86 for the plaintiff, arriving at this result by disallowing all of the account for gasoline, etc., except what was embraced in the order of January 14 ($3553.96), from which he deducted the $1800 paid by Greene County on February 1st and the $474.42 paid by Oconee County. The defendant county introduced an account of sums paid to or on behalf of the Taylor Company which nearly exhausted the contract price for the work, the balance due being $78.95. The auditor allowed this account, except the items for convict hire totaling $3145 which he held to be illegal. The parties filed numerous exceptions to the auditor’s findings. The plaintiff, on various grounds, moved also to dismiss the defendant’s exceptions. On the hearing of this motion the court allowed the defendants to amend their exceptions and overruled the motion to dismiss. When the exceptions of fact came up for trial the court having previously ruled on the exceptions of law, directed the jury to find a verdict for $78.95 in favor of the plaintiff. A motion for new trial was overruled, and the plaintiff excepted, assigning error on that ruling, on the rulings excepted to pendente lite, and on the overruling of various exceptions to the auditor’s report.
The paper of February 1, was claimed by the plaintiff to be a mere receipt for $1800 as a part payment on the liability that the county had already incurred, and therefore that this paper was not
The order or draft of January 14, was for the amount of materials furnished up to January 1. The defense against this part of the account rested wholly on the allegation that the county had paid out the entire contract price on debts of the Taylor Company which were entitled to payment ahead of the plaintiff’s claim, under the contracts of the county with the Taylor Company and with the plaintiff. The acceptance by the commissioners of Greene Comity of the order of January 14, contained a proviso “that this
A verdict can be upheld which rests on secondary evidence that
For the part of the plaintiff’s account which accrued between January 1, and February 1, recovery by the plaintiff is clearly barred by the agreement of February 1. It was argued in the briefs that the release of February 1, was not entered on the minutes of the county board and therefore never became a binding contract, under the decisions in Jones v. Bank of Cumming, 131 Ga. 614 (63 S. E. 36); Weathers v. Easterling, 153 Ga. 601 (113 S. E. 152); Murray County v. Pickering, 42 Ga. App. 739 (157 S. E. 343). But this question does not appear to have been raised in the court below, and will not now be considered. Early County v. Fielder, 4 Ga. App. 268 (63 S. E. 353); Hall County v. Smith, 178 Ga. 212 (5) (172 S. E. 645).
Regarding the portion of the plaintiff’s account which accrued after February 1, the defendants contend that there can be no recovery, because the agreement of that date provided against liability of the county for materials furnished thereafter. There is no such agreement in the writing, and only by a very forced construction can the meaning be made to include possible future liability. The terms of the writing refer to present and past liability; it is not ambiguous, and certain testimony as to conversa
Furthermore, the county could not relieve itself of its statutory liability by notice to the materialman that it would not be liable to him for materials furnished to the contractor. Nor would such notice estop the materialman from asserting his right. Board of Education v. United Supply Co., 34 Ga. App. 581 (131 S. E. 292). Estoppel to be relied on must be pleaded. Irvine v. Wiley, 145 Ga. 861 (3) (90 S. E. 69). No estoppel was pleaded in this case. The court erred in overruling the plaintiff’s 8th exception of law to the auditor’s ruling that the paper of February 1, released the county from liability for materials furnished after that date.
The judge of the superior court held that the taking of the order of January 14, followed by the payment and the paper of February 1, constituted a waiver by the plaintiff of his rights under the statute. This view is not sound. The act of 1916 as pointed out by the Supreme Court, does not make tire county liable in any event, but only for the ultimate loss sustained by the materialman. Although the contract between the county and the contractor is declared to be invalid for any purpose, a relation arises in which the materialman must get his pay from the contractor if he can, and failing therein, he can go on the county for it. Consequently there is no inconsistency, no waiver and no exercise of an election, in the materialman trying to get or getting his payment out of funds due by the county to the contractor before they are paid to the latter. Such an effort is in the interest of the county as well as of the materialman, because it gives notice to the county and an opportunity to protect itself against paying twice for the same material.
It remains to notice the rulings of the court on the exceptions of law to the auditor’s report, (a) There are a number of exceptions by the plaintiff to the action of the auditor in admitting testimony. These objections can not be considered because the auditor’s report does not show what objections were urged against the admission of the testimony, nor does the report of the auditor show what the testimony was. The pages of the brief of evidence referred to by the auditor do not correspond in number with the pages in the record. It is true that counsel for the plaintiff in
The second exception of law by the defendants related to that part of the contract of the county with the Taylor Company which provided that twenty convicts should be employed in the road work and that the county'was to receive the pay for the use of the convicts. 'The auditor held this arrangement to be contrary to the law against hiring out or leasing convicts found in
Judgment reversed.
Rehearing
ON MOTION TOR REHEARING.
It is contended by the movant, Greene County, in the motion for a rehearing in ground 1 thereof, that this court overlooked the statute requiring the auditor to brief the evidence. Code of 1933, § 10-201. The record does not show that a brief of the evidence was made by the auditor. His report says: “The evidence substantially briefed is submitted herewith.” Dated July 4, 1933. There is in the record no brief certified by the auditor or appearing to have been filed with his report. Instead thereof, there is a brief agreed to by both parties to be correct, on February 2, 1934, approved by the trial judge as correct and ordered filed on February 3, 1934. Deferences in the auditor’s report to certain pages of the brief of evidence seem to refer to a brief made by him, but there is nothing in the record to show that he made the brief which was agreed on by the parties and approved by the trial judge seven months after the report was filed. Therefore the contention that the court overlooked the statute requiring the auditor to brief the evidence is without merit. Code of 1933, § 10-402, providing that the report of the auditor shall be taken as prima facie correct, can not have the effect of supplementing the brief of evidence. The brief is conclusive as to what evidence was introduced.
In ground 2 of the motion for rehearing it is alleged that the court overlooked a statement in the testimony of H. D. Goodwin, to the effect that “the payments shown on this ledger are correct.” He did not testify -that he kept the ledger, or otherwise disclose
The decisions cited in ground 3 are not in point. They relate to admissible books. The claim is made that the book in question was admissible, and that it is to be presumed that the necessary preliminary proof was made. Whether such a presumption would arise in connection with books declared by statute to be admissible under certain circumstances need not be considered. The book in this case was inadmissible, as it did not come within the statute. Bass v. Gobert, 113 Ga. 262 (38 S. E. 834); Blanchard v. Johnson, 142 Ga. 447 (83 S. E. 104). It was stated in the decision rendered that a book of this kind was no better than hearsay. It could have been said that it is hearsay. The section of the code dealing with the admission of books is in the part of the code which treats of hearsay evidence, and forms one of the exceptions to the rule against
There is no contradiction in rulings with regard to an order or acceptance not being binding on the county. The order of Eatonton Oil and Auto Company, because of becoming incorporated in the contract of February 1, was not held to be invalid. But the acceptances of the Bickers-Goodwin Company and Greene County Motor Company orders were held not binding on the county in accordance with the decisions of the Supreme Court in the Bank of Cumming case and in this case.
The request that this motion be heard by three judges can not be granted. Two judges are a quorum and can render a valid judgment. A demand should have been made for three judges before the case was submitted to the court for consideration. Had the case been argued, one of the judges would have disqualified and a demand could then have been made for a full bench. As the case was submitted without argument, counsel can not, after the rendition of a decision in which one judge was disqualified, demand, in a motion for a rehearing, a decision by a full bench.
In the motion it is alleged that counsel for the plaintiff in error did not raise any question as to proof of the account. In paragraph 3 of the reply brief for the plaintiff in error which was filed March 10, 1934, counsel distinctly raises the question that there was no testimony as to many of the charges on the account, that many of the items could not be classified as having priority over the plaintiff's claim, that the burden was on the defendant to show that all payments claimed as preference payments were such, and that the bare statement of their account with the contractor without further explanation does not carry this burden, etc. This fairly raises the question that the defendant did not establish its defense by sufficient evidence. However, it is not necessary that the party complaining of a verdict should have made the specific complaint that it was based on hearsay, in order to have it set aside. A general objection, such as that the verdict is unsupported by the evidence, gives the appellate court ground to set aside the verdict, if it is founded on hearsay. See decisions cited in the opinion.
When the case is retried, the defendant will have the opportunity to make legal proof of the disbursements made by the county for