*1 95%, not showed schedule the revised calling three technical revision by completed 100%, to be of the work manuals, between issued Franklin to ac- if one were January 1963. Even June 1963. December 1962 and value, it cept plaintiff’s át face forecast production final It asked to furnish a was necessary unlikely work all the plans within These schedule two weeks. by 19. June finished have been submitted, timely and a second were not normally Board, there found February As request 1963. made on was up “carry-over” clean for “final that, was a project replied Plaintiff’s director target completion date organization after the work” received “At time this was schedule. Government work assignments person- these no submit- to review also allowed two weeks provi- place nel them available to into returned ted If a manual had work. sioning. However, time, per- since contractor, corrective work sonnel has become available and probably beyond the term have extended schedules will be as indicated submitted contractor and there then be new below.” The belated work schedules went proper at the site. for the Govern- beyond expiration Franklin’s contract contingencies. ment to consider these 19,1963 (one date of June ended schedule determining The Board did err in August 1963) rejected. and were On reassign decision cancel and February 7, Franklin resubmitted the responsible was within the bounds of schedules, planning now to have 95% discretion under the contract. completed the work June The Government found the schedules un- reasons, For- cannot acceptable projects. and cancelled the recover. The defendant’s motion Cancellation, however, only the affected summary granted judgment requirements parts narrative since the petition is denied. portion, work, as well as other had been dismissed. completed paid for. The ASBCA justified. found the cancellations agree. assigned normally
Even as to work
Marion, contract, Franklin’s as we noted, pro- did not it the exclusive make
ducer of the En- technical manuals for gineer certain Maintenance Center. circumstances, could Government SCHOOL, partnership con prepared have such manuals other EASTERN Benjamin Eiz sisting Simon, of Frank means. These included situations when Phillip Goldman, Laster enman, Oscar assignment the work “in excess and Samuel Frank capacity complete this contractor’s v. contract, under the or where the neces- sary UNITED STATES. capabilities technical cannot be equaled under this contract.” No. 229-57. provisions supports Either of these of Claims. Court States reassign-
Government’s cancellation and July many ment. These were indications that completed by the work would not be June 19, 1963—the contract termination date. project spoken
Plaintiff’s director had personnel
of the firm’s difficulties. The schedules, submission of the work them-
selves, completion was late. The date for rejected the first placed schedule was Then,
much period. the contract
prudence
produced
the G.I. Bills
enacted for
the benefit
which were
returning
servicemen after World War
typical
II
Korean
and the
War.
case,
primary
“schools”
issue
a school
entitled to
whether
*3
higher
instruc-
tuition rate for veterans’
has
allowed
the Vet-
tion than it
been
(VA).
has
erans’ Administration
(although
largely
inquiry
factual
legal standard,
governed
e.,
“fair
i.
compensation”)
and reasonable
presented
problems
ac-
of
difficult
counting
There have
and cost allocation.
Douglaston,
Benjamin Eizenman,
N.
subsidiary issues;
example,
for
also been
Y.,
plaintiff.
point
proper
accrual of the
Paige,
and Louis
Frances L. Nunn
S.
meaning
action,
terms
cause of
Washington,
C.,
Asst.
whom was
D.
“customary
and “fair and
cost
tuition”
Sanders,
Atty.
de-
Gen. Barefoot
compensation,”
pres-
and the
reasonable
fendant.
presentation
ence
fraud
present
case
claims
to the VA. The
COWEN,
Judge,
Chief
Before
primary
raises
issue
both
LARAMORE, DURFEE, DAVIS, COL-
extremely
subsidiary
on an
issues
NICHOLS,
LINS,
SKELTON
confusing,
lengthy,
record.
and at times
Judges.
gratitude
this time our
We note at
M.
Trial Commissioner Franklin
Stone
OPINION
thorough findings
very
prepared
who
Judge.
trying
LARAMORE,
fact
case under difficult
this
transcript
circumstances.2
counsel
are told
We
plete
Com-
with instances
in which the
last
the so-called
patience
missioner acted with admirable
Thus,
opinion is
“schools”
cases.1
judicial
juris-
body
restraint.
our
to a
final contribution
;
(1958)
F.Supp.
637,
States,
g.,
143
416
Ct.Cl.
E.
v.
National Schools
United
Northwest-Broadcasting
(1966) ;
Sawyer,
578,
F.2d 250
175 Ct.Cl.
361
d/b/a
610,
States,
F.Supp.
Chicago
Trades,
161
School v. United
Inc.
School of Automotive
Little,
;
(1958) ;
(1964)
States,
142
169
Ct.Cl.
v.
student-hour based estimated the ably expense related be com- operation. 31, costs 1949, On December regulation pensable. was effect supplemental the contract and January 1, con- 1950 when agreement expired leaving the rate for tract, covering preceding months Technology the Radio course undeter- providing per a for rate of $.50 mined. student-hour, expired. point history helpful. At some particularly treat- This scheme— expired, After the initial contract a new “customary ment cost of tuition”— rate had to be established as veterans entirely satisfactory to either was not through continued to enroll in the course Congress schools, or re- VA the so fact, 1950—in until 1957. The adminis- sponded with two remedial bills. procedure origin trative had its Independent appended to the was 400(b) 1944 G.I. Bill. Section 1950, Appropriation Act of Offices Readjustment 1944, Servicemen’s Act of 631, (1949). provided It Stat. 284, 289, provided 58 Stat. as follows: subject for two for courses to contract years pay shall tuition rate [VA] Administrator successive by training to tion, recent the educational or be the the most institu- rate established person for a “cus- each courses without enrolled full contract. For part tomary cost,” time' or “fair and reasonable” time course of education a training, by customary or Ad- cost' tui- rate would be fixed VA. * * * ** tion, by *: ministrative was assured Provided review Appeals That if no creation Tuition such institution has “Veterans’ fee, bill, established Board.” The second enacted or if its estab- customary following year, preserved lished tuition fee shall found be changed first, inadequate Administrator cost definition of the compensation to the name of administrative board to such institution for furnishing Appeals Board” training, Education such education “Veterans*' (VEAB), provisions to provide pay- and elevated authorized to for the permanent Educa- fair and rate for status. Veterans’ reasonable law 1950, Training year calendar 1950 was stu- tion Amendments $.419 accordingly 336, history of dent-hour. 338-339. The Plaintiff was Stat. thoroughly year provisions paid is more at the rate $.419 Schools, plain- Hemphill Inc. v. Unit- 1950. For treated (1955). paid ed 465-468 rate 133 Ct.Cl. at the same because tiff end became the cus- $.419 Thus, at the time VA tomary of tuition. Plaintiff cost negotiating rate new right payments served its to contest Technology Radio calendar course for the in court. year 1950, interpreted the VA the law petition3 here filed Plaintiff prerequisite to mean that a cus- claiming difference May 15, tomary 2-year history, rate awas paid per student-hour the $.419 between customary that where there no rate of veterans instruction the VA a fair and reasonable rate would have to Technology course Radio in the enrolled contracting be determined officer. is al- per student-hour and $.533 contracting On October rate.4 legedly fair and reasonable officer determined that a $.3127 dif- Alternatively, plaintiff for the asks per student-hour was fair and reason- and $.50 ference between $.419 able, and offered a contract on alleges customary allegedly rate. objected basis. *5 arbitrary, decision was the VEAB rejected Thereafter, rate and the offer. supported sub- capricious, and not 1, 1950, on November the VA renewed its charges evidence; specifically it stantial per offer with a rate of student- $.36 capri- “arbitrarily Board with appealed hour. Plaintiff de- second disregard [ing] sub- data ciously the cost termination VEAB on November fix[ing] School, Eastern mitted Appeal 10. Its Notice of contended that fair, reasonable neither rates that were per $.533 student-hour the minimum was equitable.” nor rate, alternatively, fair and reasonable or ptem customary that a cost of of government tuition on $.50 answered The Se per apply. student-hour should A hear- 13, 1957, the statute and raised ber ing year later, followed. one Almost defense. an affirmative as limitations 1, alleged 1951, hearing November a Ed.). VEAB ex- (1964 It 2501 28 U.S.C. § holding aminer announced his decision ac portion the claim which Technology 4, Radio course had not time- was 1951 June crued before acquired customary 1960, July later, cost of tuition be- years Three barred. cause it had not been under contract court leave obtained the defendant years, two successive so fair and three counter to add answer amend its reasonable tuition rate had be deter- second counter first and The claims. mined; this he set at student- $.51 False Claims on the founded claims were ap- hour. The any latter person determination was who provides that Act which pealed by making the Administrator of Veterans’ claim a false or aids submits January which, pay Affairs to the Board the United forfeit “shall 15, 1953, and, holding $2,000, in addi- issued a final decision the sum States erroneously Law 3. which was Public G.I. The Trial 1944 Bill Commissioner They (1944). re- are found that was 284 June 1957 the date of 58 Stat. day plaintiff filing. Also involved students. On to as “346” filed its first ferred students, petition printed “550” are so-called amended form. in this case The filing required although be- on their is made second original petition no claim because the They typewritten; who 550, veterans are Korean half. War rule 1(e) permits filing typewritten pe- Public Law benefits under received (1952). printed copies is Their titions on condition 66 Stat. 663 defendant’s be relevant in connection with filed within 20 thereafter. second counterclaim. higher The students whom the tuition is claimed under received benefits damages government tion, double the amount of under the standard Nager contract. States, Electric v. United the United States have sus- Co. (cid:127) —(cid:127) doing (1966). F.2d tained reason or com- Ct.Cl. We held together right mitting act, disputes action on the costs aris such ing (1964 Ed.). (disputes under the contract suit”. 31 clause U.S.C. § The based on the first accrues when the claims) first counterclaim is adminis * * * language: final, “Any person trative action who a like * * * upon shall make against or result should claim obtain “a claim’ ‘breach spawned under a of the United contract which has also * * * * * knowing litigation' ‘disputes-type’ States such claim items * false, fictitious, principle *.” because of or fraudulent indi one normally gives visible relates to “346” students whose tui- contract rise directly F.2d, tion from the received to one cause of action.” showing VA after it submitted vouchers Supreme adopted ap Court the attendance each student. sec- proach disputes as to clause claims ond based on lan- counterclaim is Crown Coat Front Co. v. United * * * who, guage person “Any : 386 U.S. L. 87 S.Ct. aiding purpose obtaining for the or (1967); Ed.2d 256 it did not reach the payment approval obtain the of [a question of time first accrual for * * * false to be causes claim] breach claims. * * * used, any made or false cer- * * tificate *.” It to “550” relates here for This case review whose, students6 rendered under administrative decision ceived from the students after the VA disputes 321- clause. See U.S.C. §§ paid them; plaintiff prepared the at- Ed.). (1964 Nor is it as here Nager tendance records the students sub- Electric breach claim. So mitted third counter- thought application. VA. How- no be ever, to have predicated reasoning claim section 266 of Pub- ex- used there is *6 lic and establishing Law 550 1503 of 28 tremely section U.S.C. what instructive (1964 Ed.), allegedly applied would entitle case. formula in this should be overpayments Nager to recover starting point Electric was of An veterans’ benefits. additional general first accrual should rule that counterclaim raised in the trial. oc- be “the time all events have when It based on alleged section 2514 of 28 U.S.C. curred the Government’s to fix (1964 provides Ed.) for- entitling for the liability, de- claimant to any claim of claim- payment feiture entire mand sue here for his and practices prosecu- ant who fraud money.” F.2d, 851. It was fur- at tion of the claim. prerequisite that ther “[t]he stated that lawfully plaintiff de- be able to must We address ourselves first to stat- early payment goes mand back to the problem, ute of limitations to .then points of this court.” Ibid. Both higher of merits claim for a supported by were numerous citations. rate, finally to and defendant’s analysis of There then an followed counterclaims. rule in manda- contract cases before the I. STATUTE LIMITATIONS OF tory disputes era clause and discussion (1964 Ed.) by agreements, Section 2501 of 28 U.S.C. of aberrations caused bars pe- a claim special statutes, in this court “unless the and other factors. The tition years through running analysis thereon is filed within six thread single after such prin- claim first accrues.” Recent- “that there no inexorable ly the ciple litiga- court appli- reviewed detail the of limitations contract language cation terms, of accrual” “first tion but the individual con- disputes ditions, breach always practices claims and clause claims must be 4, supra. 5. See n. 6. Ibid. 1951; April 30, 1950; January 1 to F.2d, From at 852-853. studied.” 1,1951 also de- May This letter on. from off into
there the court branched
covering
procedures
forth
fined and set
analysis
special rule
for a
of the reason
make-up
absences,
in-
attendance,
judicial
of
where
“first
accrual”
procedures which had thereto-
ripen
claim
administra-
cannot
until
struction —
fore been undetermined.
stop
remedy
short
tive
is exhausted. We
here, confining
inquiry
ourselves
suggests
us
pattern
This fact
contracting
to a
review
situation
position
plaintiff
in a
plaintiff
between
VA which
higher
rate
payment
until
demand
proper
should indicate
for de-
course
prob
July 17, 1952,
earliest, and
at the
termination
time of first accrual.
appears
ably September
on,
plaintiff
It should be recalled that
the contract
and the
that from 1950
both
anticipated
covering
Technology
VA
the Radio
course
would establish
rate
contract which
31, 1949,
terminated
on December
but
retroactively
apply
prospectively
plaintiff
continued to instruct vet-
govern
procedure for de
would
plain-
erans thereafter.
The VA advised
termining
compensable
number
September 6,
tiff on
it
1950 that
would
fact,
parties
hours of instruction.
pay an “interim
rate” of
[tuition]
$.30
agree
a formal
never
able
(as compared
student-hour
with $.50
unilaterally
had to
contract and the VA
contract).
under
the old
The letter as-
procedure
substan
establish
plaintiff
payment
sured
in-
tiating
for veteran stu
tuition claims
prejudice
terim rate would be “without
importantly,
* * *
*
dents,
perhaps
*
*
more
right
[its]
absences.
reasonable
standards
receive such rate as
established
September
Before
it did
the final contract.”
rate
interim
de
perhaps have
plaintiff could
date
was boosted to
on November
$.375
higher
of a
payment
manded
plaintiff
appeal
filed its
refusal,
upon any
sued
time,
plaintiff
offer. At
$.36
arrange
with the
inconsistent
have
set-
was instructed to submit vouchers
contracting
contemplated
ment
ting
total number
hours
forth
knew,
the VA
parties.
For
furnished,
instruction
without
given
every
ultimately
it
designation
individual students
desired;
not un
thing
least was
it
it
number
hours
furnished
to them.
negotiate for
reasonable
These
also advised
instructions
arrange
years, hoping
the final
two
ultimately
prepare
have to
*7
short,
satisfactory.
In
ments
listing each veteran
itemized schedule
the
is a case
think this
applicable fees,
and all
be submitted
oc
accrual
principle
familiar
In
of a final
rate.
determination
perform
completion
only upon
curs
January
1951,
30,
a letter dated
the VA
individual
“the
bend to
ance should
arrangement.
billing
continued this bulk
practices”
conditions,
of the
terms,
17,
July
1952, the
its
On
VA reversed
situation,
point here
particular
method;
position
billing
it
bulk
26,
time when
September
1952 “as
given
two
notified
it would be
*
* *
to fix the
occurred
all events
prepare
in de-
months to
final vouchers
Nager
liability”.
alleged
Government’s
for
tail and with
to each veteran
F.2d,
Co., supra,
at 851.
368
Electric
period
payments,
and that
interim
therefore
entire
claim
Plaintiff’s
payments henceforth
interim
be
timely.
billings
only
made
on the
detailed
basis
government
attention
our
directs
September
Then,
for each
veteran.
Tailoring,
v.
Inc.
Empire
26, 1952,
spec-
Institute
letter
the VA sent another
409,
F.Supp.
Ct.
States,
142
ifying
procedure
pay-
161
interim
(1958),
schools
similar
regard
a rather
Cl. 165
ments
of the follow-
each
time-
31,
a claim
ing
court held
periods:
January
which the
case
1 to December
brought
being
per
six
tuition rate
for not
within
student-hour
$.419
barred
Technology
years
performance
of the services.
Radio
of the
course was fair
rejected
tolling argument
reasonable,
(2)
A
was there
the esti-
grounds
administrative
mated annual
on the
instructional hours for the
mandatory.
148,720 hours)
appeal proceeding
course
not
should
was
be
was
411,
capricious,
F.Supp.,
Ct.Cl.,
“arbitrary,
erroneous,
at
at
168:
and not
supported by
A more recent case referred to us
substantial
evidence.” On
Congress,
admittedly in
conflict with
basis
record
administrative
Empire
Chicago
and the
Institute.
of Au-
record made in a
School
trial de novo
Trades,
him,
tomotive
Inc. v. United
before
he determined that
the fair
(1964).
them to
differ
on
terclaim because
somewhat
YA
application
Specifically,
proper
defend-
of the burden
“346” students.
test;
alleges
knowingly
proof
per-
ant
over-
defendant
not
that
eight
convincing
stated
suaded us
evi-
the attendance of
veterans
partners
overpayment
that
or
or
in the
dence
resulted
agents
hours,
knowingly
213.5
false claims.
or
Under the False
submitted
$89.33.
Act,
(1964 Ed.),
Claims
31 U.S.C.
§
convincing
most, there is clear and
At
proof
allegation
of this
entitle de-
eight
evidence that
five of the
veterans
(double
fendant
$178.66
$89.33
they
periods
absent for
when
were
were
damage suffered) plus
(five
$10,000
for-
present,
the five
marked
and that four of
$2,000 each, representing
feitures of
Simon,
who were absent
informed
Eizen-
falsely
five vouchers or claims
they
be
man or an
that
instructor
ported
eight
the attendance of the
vet-
absent. As the
of the five vet-
sketches
erans) . The Commissioner
on the
found
show,
erans below
these facts do
will
testimony
eight
basis of
vet-
prove
Equally
fraud.9
consistent with
erans and other evidence
that
there
explanation
fraud
facts is the ex-
convincing”
“clear and
that five
evidence
planation
sys-
attendance
eight
longer
of the
pe-
were absent
deficient,
rec-
tem
have been
or its
riods than their
in-
attendance vouchers
ord-keeping practices
possibly
were
inac-
dicated and that Frank Simon
Ben-
sloppy.
prove
or
curate
To
fraud
jamin
knowledge
Eizenman had
of this
defendant would
circumstances
fact
so that
the vouchers “constituted
or Eizenman
show that Simon
payment
false
fraudulent
claims for
management
person
group
another
presented
against
agency
an
only
“knew” these students
ab-
the United States.”
sent,
wilfully
but also
decided to mark
present
VA-required
on
them
vouch-
agree
We
with the Commissioner
ers,
policy
or that
mis-
was a
prove
has the
defendant
burden
report,
or Eizenman
that Simon
convincing”
“clear and
evidence
made no effort
certain that
stu-
question
knew
claims
they
whom
dents
knew were absent
false, fictitious,
here were
or fraudulent.
reported
absent. The evidence
778,
States,
See Klein v. United
285 F.2d
required
showing might
for this
be the
(1961);
Ct.Cl.
Kamen
testimony
regarding
employee
his
Soap
Co. v.
Products
United
instructions
from Simon or Eizenman
F.Supp. 608, 620,
619, 642
129 Ct.Cl.
prom-
or the
of students that a
(1954);
Grannis,
States
v.
present.
ise
made
them
to mark
cert,
Cir.),
(4th
denied,
F.2d 507
337 U.S.
record
the “346” students is barren
(1949);
69 S.Ct.
The double
by
posed
ex rel.
United
States
conclusion,
plain
we hold that
537,
Hess,
Marcus
v.
317 U.S.
S.Ct.
timely filed,
tiff’s
claim
(1943),
379,
quittal criminal action means no As I read section it was intended prosecution more than was not prac- claim if the forfeit claimant guilt prove beyond able to reasonable thereof, prosecution ticed fraud prose doubt. It does not mean that only Congress Ex- before the or the cution could not have obtained a con branch, ecutive but before court also. prove guilt viction had Clearly, therefore, plead the failure pre evidence or a section 2514 at the outset would not bar ponderance. Supreme Court cases its invocation if the fraud occurred show False Claims Act is not pleadings Clearly too closed. Accordingly, criminal in nature. hold falsity, though begun earlier, con- *17 acquittal the of and that Simon Eizen pleadings tinues after if have closed proceeding man in can the criminal have the claimant in or othewise no actually effect in this not case. continues to assert what is (This only subject to defendant be entitled The is the matter course. claim.) govern- Claims Act. “costs of suit” under the False of the affirmative item, counterclaim, how- is made for this No allowance in its first ment asserts ever, students, plain- has not offer- because the defendant “346” that which relates to any costs, concerning over-reported ed for 213.5 evidence tiff attendance any adopted claim therefor. nor has it made We have Commission- hours. plaintiff over-re- er’s that agree parties show 15. The the vouchers Accordingly, ported have 119.0 hours. we 1,043,019.3 plaintiff provided of a total compensable hours the number of reduced compensable to “346” hours of instruction 1,042,900.3. Technology to in the Radio students enrolled
439
Congress
I think the
theory
19
U.S.C. §
invok-
The Government’s
true.
ing
rely
the Executive branch
intended to
implying
I
this.
2514
as
section
read
pro-
apply all
such
and on
courts
in
I believe that
circumstances
manner related
in a reasonable
here,
visions
spelled
but which
not
need
out
legislation,
purpose
apparent
occur,
may
any
it
time
at
language.
just
Church
to its literal
duty
2514
section
of this court to invoke
States,
Holy Trinity
of
v.
spcmte,
position of the
sua
whatever
457,
511,
L.Ed.
U.S.
S.Ct.
law officers.
Government’s
(1892).
forfeit
To
the entire claim
hold
in
Coal
v. United
We said
Pewee
Co.
falsity
out
in two items
on account of
States,
F.Supp.
958,
Ct.Cl.
discourage
thousands would do more to
cert,
(1958),
denied 359 U.S.
doing
persons
with
from
business
honest
(1959):
