Eastern Environ. Endeavor, Inc. v. Industrial Pk. Auth. of Calvert Cty.Eastern Environ. Endeavor, Inc. v. Industrial Pk. Auth. of Calvert Cty.
delivered the opinion of the Court.
Eastern Environmental Endeavor, Inc. (EEE) and Joseph Huang, president of EEE, appellants, appeal the order of the Circuit Court for Calvert County granting appellee’s, Industrial Park Authority of Calvert County (IPA), "motion to enforce settlement agreement.” Pursuant to the order, judgment was entered against EEE in the amount of $15,000 and against Huang in the amount of $5,000.
The settlement agreement between appellants and appellee arose out of litigation concerning cost overruns in the construction of a water purification plant, waste water treatment plant and control building upon property owned by IPA. EEE and Huang provided engineering services and construction supervision on the job. In November of 1977 the general contractor, Southern Maryland General Contractors, Inc. (SMGC), filed an amended declaration against IPA for sums due it pursuant to the construction contract and for extra work performed by SMGC. IPA then filed an amended third party claim against EEE and Huang claiming that the third party defendants, appellants here, were liable for any damages suffered by IPA as a consequence of SMGC’s suit.
Negotiations among the three parties’ attorneys ensued and two settlement agreements, one between SMGC and IPA and another between IPA and EEE and Huang, were reached sometime in November, 1978. According to the motion to enforce the settlement agreement, IPA and EEE and Huang agreed to the following: IPA was to release EEE and Huang from any liability arising out of the subject
On appeal EEE and Huang raise the following issues:
1. Did the trial court err in finding that a court of law possessed subject matter jurisdiction to rule upon a "Motion to Enforce Settlement Agreement”which sought only equitable relief — i.e., specific performance of an agreement?
2. Did the trial court err in ordering relief inconsistent with that requested in the pleadings?
3. Did the trial court err upon the facts in finding that the settlement between Plaintiff and Defendant was predicated upon the ability of counsel for Defendant to finalize a settlement agreement with Third Party Defendants and that the two settlement agreements were entered into contemporaneously?
3a. Did the settlement of the Third Party claim between the Defendant and the Third Party Defendants lack consideration in that the Plaintiff and Defendant had entered into a settlement agreement prior thereto?
(1)
IPA’s motion to enforce the settlement agreement contains the following prayers for relief:
"1) That this Honorable Court pass an order requiring third party defendants to comply with the terms and conditions of the settlement agreement;
3) And for such other and further relief that this Honorable Court might deem necessary and just.”
Appellants contend that the first prayer seeks specific performance, although it does not specifically characterize the relief as such, an equitable remedy which can only be granted by a Court of Equity, citing
Horst v.
Kraft,
Several notable differences distinguish the present case from
Horst.
In the first instance, the law action in this case was filed before the settlement agreement was reached; in
Horst
the matter allegedly was settled prior to the instigation of the law action. The plaintiff in
Horst
had her choice of forums for enforcement of the agreement, she simply did not choose the proper one. A different matter, however, is presented with the settlement of an ongoing law action. One year after
Horst
the Court of Appeals announced a favorable policy with regard to the compromise or settlements of law suits in the interest of efficient and economical administration of justice and the lessening of friction and acrimony.
Chertkof v. Harry Weiskittel Co.,
Although the Court of Appeals in
Chertkof
did not decide the precise question presented here, the Court apparently saw no difficulty with the entry of a money judgment based upon a settlement agreement between the parties.
Chertkof v. Harry Weiskittel Co., supra
at 549-50. A more recent Court of Appeals case involving a settlement agreement,
Clark v. Elza, supra,
while not directly addressing the propriety of a motion to enforce a settlement agreement in an underlying legal action,
"... while the agreement to compromise was binding and enforceable against a defaulting party — barring plaintiff from proceeding with his original action in breach of the agreement — plaintiff did not entirely relinquish his original cause upon entering into the agreement of compromise. The tort action would only be conclusively terminated when the $6,000 was paid against delivery of the releases and dismissal stipulation; until then it remained in abeyance and if defendant repudiated the settlement or committed a material breach of its terms, plaintiff could elect either to sue for $6,000 or to rescind and press forward upon the original cause.” [Emphasis added.] Id. at 683, quoted in Clark v. Elza, supra,406 A.2d at 927 .
(2)
Appellants also complain, much along the lines of their first argument, that the trial court erred in ordering relief inconsistent with that relief requested in the motion. Appellants insist that the prayer for an order requiring appellants’ compliance with the settlement agreement is strictly a prayer for specific performance. Appellants cite
Mills v. Zion Chapel,
That is not the case here. Even were we to conclude that a request for compliance with a settlement agreement is tantamount to a request for specific performance and cannot have any other meaning, we do not believe the trial court was precluded from awarding damages. Appellants overlook the third prayer for such other and further relief as the court might deem necessary and just, a prayer which was not present in Mills. Accordingly, the award of damages was entirely consistent with this prayer for relief.
(3)
Appellants also take issue with the following factual finding of the lower court:
"The testimony adduced at the hearing clearly indicates that a settlement had been made with the third party defendants (EEE and Huang)contemporaneously with the settlement between the Industrial Park Authority and Southern Maryland General Contractors, Inc.”
Appellants claim that this factual conclusion is not supported by the evidence and the trial court, therefore, clearly erred. Under
Md. R.
1086 this Court must assume the truth of all the evidence and of all the favorable inferences fairly deducible from it tending to support the factual conclusion of the trial court.
Jacober v. High Hill Realty, Inc.,
"We were negotiating both claims. As a matter of fact, the amount that was paid in that claim, part of the consideration that was' taken into consideration by the Industrial Park Authority and actually the County Commissioners were aware of it because they would have had to finance this settlement, was whatever we could get from Mr. Huang and his corporation.”
While the witness exhibited some confusion as to the exact date each settlement agreement was reached, this confusion relates to the credibility of the witness, which is a matter to be resolved by the trial court.
Md. R.
1086. We believe that the attorney’s testimony, despite confusion as to dates, constituted competent, material evidence which supports the trial court’s conclusion that the agreements were made contemporaneously.
See Staley
v.
Staley,
(3a)
Appellants claim that the third party litigation was terminated once SMGC and IF A settled and therefore, since
Judgment affirmed.
Costs to be paid by appellants.