This case involves an action brought by the plaintiff, Eastern Bus Lines, Inc., against the defendants, the city of Norwich and its board of education, claiming damages resulting from the breach of a contract for the transportation of school children during the academic year of 1981-82.
The facts are not in dispute. The defendant solicited bids by advertising its invitation to bid for the school transportation contract fоr the three year period commencing in the fall of 1981. The invitation to bid set forth contract specifications and estimated transportation requirements for the 1981-82 school year. In prebid conferences, it was indicated by the defendant that these were estimates of its transportation requirements. The plaintiff submitted a bid which contained its own specifications and which was ultimately accepted by the defendant. The parties entered into a contract in April, 1981.
The contract provided, inter alia: “Base bid for a total of 2,000 miles for thirty-two (32) plus three (3) spare, sixty-six (66) passenger rated capacity buses. . . . The [defendant] reserves the right to fix the schedules and routes and to reduce or increase existing routes оr to change the schedules and number of routes. . . . The [defendant] will purchase a maximum of 90,000 gallons of gasoline or 2,650 gallons per vehicle, whichever is less and will have it delivered to the tank provided by the contractor. The cost of any gаsoline in excess of 90,000 gallons or 2,650 gallons per vehicle will be the responsibility of the contractor. . . . [The defendant’s charges for mileage adjustments for the first year will be:] $.90 per mile for mileage in excess of 2,000 miles per day plus an added аllowance of 1 gallon of gasoline for each 4 miles added. No credit for mileage reductions. ...”
The defendant made all the monthly payments for charges specified by the contract. The plaintiff subse
The trial court concluded that any mileage over 2000 miles per day was to be compensated and that additional payment for extra runs or mileage could be allowed even if the 2000 mile limit was not exceeded. The trial court found that the defendant was liable for an amount totalling $19,630.80, based on the following: extra kindergarten runs, the community school shuttle bus, St. Bernard’s high school schedule change, and a gasoline allowance for the spare and аdditional buses.
The defendant has appealed from the judgment claiming that the trial court erred: (1) in ruling that a contract should be construed against the party who drafted it; (2) in concluding that the omission of a provision in the contract specifiсations was intentional and designed to lull the plaintiff into making a lower bid by leading it to believe that it would be compensated for extra runs; (3) in implying terms in the contract specifications requiring extra compensation to the plaintiff; (4) in construing a сontract where only a portion was introduced into evidence; and (5) in considering other contracts made between the defendant and third parties.
On appeal, this court must determine whether the trial court’s conclusions, based on thе facts and on the law applied to those facts, are correct and fully supported by the evidence and the record. Practice Book § 3060D; Pandolphe’s Auto Parts, Inc. v. Manchester,
The general rule is that when contract language is ambiguous or susceptible to different interpretations, “the language is to be construed against the [party] who drew it . . . and for whose benefit it was inserted.” Sturman v. Socha,
In its first claim of error, the defendant maintains thаt the trial court committed three fundamental errors in applying the contra proferentem rule: (a) by finding that the defendant alone drafted the contract; (b) by failing to find the requisite ambiguity; and (c) by resorting to the rule without first looking to the language of thе contract itself to determine the intent of the parties.
The defendant claims that because the plaintiff had participated actively in drafting the contract terms, the
In a case involving a building contract, our Supreme Court rejected a claim by the state that since the contract contemplated a complete building which would not be complete without wiring, the general contractor should be held responsible for the wiring whether or not it was included in the contract plаns and specifications. The court rejected this contention and applied the contra proferentem rule against the state. Southern New England Contracting Co. v. State,
There is no Connecticut authority to support the defendant’s next claim that the contra proferentem rule is to be applied only as a last resort. 1A Corbin, Contracts § 268. The court in its memorandum of decision indicates that it reviewed the contract and testimony of the parties in great detail as well as the background of the сontract. The omission of payment for extra runs was noted. Hence, even if Connecticut did follow the last resort application, it would appear that the contra proferentem rule was applied in this case as strengthening the trial court’s finding concerning the intent of the parties. We do not find that the trial court erred in applying the contra proferentem rule against the defendant.
The defendant challenges the trial court’s conclusion that the defendant intentiоnally omitted to provide for payment for extra bus runs in order to lull the plain
The defendant next claims that the trial court erred in implying a contract term requiring compensation for the performance of the extra work. “ ‘A term not expressly included will not be read into a сontract unless it arises by necessary implication from the provisions of the instrument.’ Texaco, Inc. v. Rogow,
The defendant’s claim that the trial court failed to construe the written agreement in its entirety was not properly preserved at trial for review on аppeal. Here, we will enforce the rule that claims not made at the trial court will not be considered on appeal. Practice Book § 285A; Latimer Point Management Corporation v. Anderson,
There is no error.
In this opinion the other judges concurred.
Notes
The contract involved a three year period commencing in September, 1981. In this casе we are concerned only with the first year of the contract.
We will refer to the named defendant, the Norwich board of education, as the “defendant,” as it has been agreed that any judgment rendered in favor of the plaintiff would be entered against the defendant city of Norwich rather than against the board of education.
