Case Information
*1 #26776-aff in pt & rev in pt-GAS
IN THE SUPREME COURT
OF THE
STATE OF SOUTH DAKOTA
* * * *
EAST SIDE LUTHERAN CHURCH
OF SIOUX FALLS, SOUTH DAKOTA,
а South Dakota Nonprofit Corporation, Plaintiff and Appellant,
v.
NEXT, INC.,
a South Dakota Corporation, Defendant, Third-Party
Plaintiff and Appellee, v.
FIEGEN CONSTRUCTION CO.,
a South Dakota Corporation and
BROWN ARCHITECTURE & DESIGN
CO. n/k/a STUDIO 360 ARCHITECTURE,
INC., a Nebraska Corporation, Third-Party Defendants,
Fourth-Party Plaintiffs and Appellees, v.
M.J. DALSIN CO. OF S.D., INC., Fourth-Party Defendant,
Fifth-Party Plaintiff and Appellee, v.
JEFF PRINS d/b/a AJ CONSTRUCTION, Fifth-Party Defendant.
* * * *
APPEAL FROM THE CIRCUIT COURT OF THE SECOND JUDICIAL CIRCUIT MINNEHAHA COUNTY, SOUTH DAKOTA * * * *
THE HONORABLE STUART L. TIEDE
Judge
* * * *
ARGUED APRIL 29, 2014 OPINION FILED 08/06/14 *2 RONALD A. PARSONS, JR.
Johnson, Heideprim &
Abdallah, LLP
Sioux Falls, South Dakota
and
WILLIAM D. KUNSTLE
SAMUEL M. GOODHOPE
LAURA T. BRAHMS
Kading, Kunstle & Goodhope, LLP
Sioux Falls, South Dakota Attorneys for plaintiff and
appellant.
PAUL W. TSCHETTER
ROGER A. SUDBECK
Boyce, Greenfield, Pashby & Welk, LLP Attorneys for d efendant, third-
Sioux Falls, South Dakota
party plaintiff and appellee Next, Inc .
DEREK A. NELSON
WILLIAM P. FULLER
Fuller & Williamson, LLP
Sioux Falls, South Dakota Attorneys for third-party
defendant, fourth-party plaintiff and appellee Brown Architecture & Design Co.
MICHAEL L. LUCE
Murphy, Goldammer &
Prendergast, LLP
Sioux Falls, South Dakota Attorneys for third-party
defendant, fourth-party plaintiff and appellee Fiegen Construction Co.
GREGORY J. ERLANDSON
Bangs, McCullen, Butler,
Foye & Simmons, LLP
Rapid City, South Dakota Attorneys for fourth-party
defendant, fifth-party plаintiff and appellee M.J. Dalsin Co. of S.D., Inc.
SEVERSON, Justice
[¶1.] East Side Lutheran Church (East Side) appeals from a summary judgment ruling that barred its claim for failing to timely file suit within the applicable six-year statute of limitations. We affirm in part and reverse in part.
Background
[¶2.] In April 2002, East Side contracted with NEXT, Inc. (NEXT) for construction of a new addition to East Side’s church and renovation to its existing structure. NEXT worked as East Side’s representative for the project and contracted with third-party defendants Brown Architecture & Design Company (Brown) and Fiegen Construction Company (Fiegen). Brown provided design and architectural work on the project and Fiegen served as the general contractor. Fiegen subcontracted with fourth-party defendant M.J. Dalsin Company (Dalsin) to complete the roof construction associated with the project. 1 The project was substantially completed in August 2003.
[¶3.] In the months immediately following the project’s completion, East Side experienced a variety of problems throughout the structure. The problems included ice dams, bats in the church, chipping concrete, hail penetration, and drainage issues, but the overriding problem was water infiltration. 2 The water infiltration persisted and resulted in this litigation.
1. Dalsin in turn sub-subcontracted with fifth-party defendant AJ Contracting to provide work on the roof construction. Dalsin obtained a default judgment against AJ Contracting prior to the circuit court’s summary judgment ruling.
2. Water was found in the west entrance, east vestibule, Pаstor’s office, quilting
room, prison ministry office, furnace room, north-side basement, kitchen, pre- (continued . . .) *4 [¶4.] East Side and NEXT communicated about, and NEXT attempted to eradicate, the water infiltration from the date of the project’s completion until May 2009. On January 23, 2009, NEXT’s attorney sent a letter to East Side explaining that Fiegen and Dalsin were “unwilling to perform any additional work[,]” and that NEXT had, without admitting liability, “notified its insurance carrier of a potential claim.” Later that spring, on May 28, 2009, NEXT’s attorney informed East Side’s attorney that NEXT “will be undertaking no additional repairs to” the church. The letter further stated that East Side “will need to either undertake its own repairs and proceed with litigation or contact Fiegen and Dalsin regаrding any such repairs.”
[¶5.] In March 2010, East Side hired Michael Ollerich of American Technical Services. Ollerich’s reports confirmed that the church was experiencing water infiltration. Ollerich’s reports further indicated the project’s design contained structural errors; the work completed contained construction errors; and the structure was experiеncing ventilation and insulation problems. East Side filed suit against NEXT in July 2010. 3
[¶6.] NEXT, Brown, Fiegen, and Dalsin (Defendants) moved for summary judgment on the basis that East Side filed its suit outside of the six-year statute of ________________________
(. . . continued)
kindergarten room, kindergarten room, storage room, second-floor altar-guide room, and second-floor south furnace room. In addition, hail was found in the narthex. Gigi Rieder, East Side’s office manager, testified that the water infiltration was “throughout the structure.”
3. In addition to defending the lawsuit, NEXT sued third-party defendants
Brown and Fiegen, Fiegen sued fourth-party defendant Dalsin, and Dalsin sued fifth-party defendant AJ Contracting.
limitations. See SDCL 15-2-13. The Defendants argued that because East Side knew of the water infiltration immediately after construction was completed, the six-year statute of limitations began to run as early as August 2003. As a result, the statute of limitations lapsed in 2009 and East Side’s July 2010 lawsuit was not timely filed.
[¶7.] East Side opposed summary judgment and argued that its lawsuit is based in part on the project’s structural design errors and construction errors. Because it did not know of the structural design errors and construction errors until Ollerich’s 2010 reports, it argued its claims did not accrue until 2010, mаking its suit timely. East Side also argued that equitable estoppel tolled the statute of limitations.
[¶8.] The circuit court granted summary judgment to Defendants on the statute of limitations issue because East Side “had actual or constructive notice of a cause of action immediately after the substantial completion [of the project] in August of 2003.” The circuit cоurt also granted summary judgment to Defendants on the issue of equitable estoppel because there was no “genuine issue of material fact regarding whether or not any of the [D]efendants misrepresented or concealed material facts from [East Side] in order to induce [East Side] to change its position in reliance upon either those misrepresentations or that concealment.” East Side now appeals to this Court arguing the circuit court’s rulings on the statute of limitations and equitable estoppel were error. 4
4. Our review of a summary judgment ruling is clear:
(continued . . .)
Decision
Statute of limitations
[¶9.] The parties agree that the six-year statute of limitations prescribed by SDCL 15-2-13 controls East Side’s claims. East Side commenced this action in July 2010. Thus, any claims that accrued before July 2004 аre barred. As a result, we must resolve if there are any genuine issues of material fact as to whether any or all of East Side’s claims accrued before July 2004. A claim accrues when a plaintiff has actual or constructive notice of a
cause of action.
Strassburg v. Citizens State Bank
,
(. . . continued)
We must determine whether the moving party demonstrated the absenсe of any genuine issue of material fact and showed entitlement to judgment on the merits as a matter of law. The evidence must be viewed most favorably to the nonmoving party and reasonable doubts should be resolved against the moving party. The nonmoving party, however, must present specific facts showing that a genuine, material issue for trial exists. Our task on аppeal is to determine only whether a genuine issue of material fact exists and whether the law was correctly applied. If there exists any basis which supports the ruling of the trial court, affirmance of a summary judgment is proper.
De Smet Farm Mut. Ins. Co. of S.D. v. Busskohl
,
[¶11.]
“Because the point at which a period of limitations begins to run must
be decided from the facts of each case, statute of limitations questions are normally
left for a jury.”
Strassburg
,
notice of the water infiltration prior to July 2004. It is undisputed East Side knew
water infiltration existed throughout the building almost immediately after
construction was completed in August 2003. Because East Side’s actual notice of
the water infiltration gave rise to a situation where East Side could have filed suit
and sought relief, any claim with a sufficient relationship to the water infiltration
so as to put East Side on constructive notice of that claim (water infiltration claim)
accrued and statutorily lapsed prior to East Side’s July 2010 lawsuit.
See Spencer
v. Estate of Spencer
,
claims encompasses all of East Side’s alleged design and construction error claims, and whether that is a factual or legal question. 5 East Side contends this case presеnts “different acts constituting breaches of contract,” which result “in separate or different damages” that “give rise to separately accrued claims.” East Side argues that “[m]any of the structural deficiencies and defects [discovered in 2010] had nothing to do with water infiltration[,]” and as a result, there is a factual dispute as to when the different claims acсrued. Defendants argue that the water infiltration places East Side, as a matter of law, on constructive notice of any other defect in the building. Defendants contend there have not been different acts constituting separate breaches of contract, but only East Side learning the full extent of its damages. 6
5. East Side’s complaint alleges breaсh of contract and negligence causes of
action. Defendants argue East Side cannot maintain an action for negligence
because all of East Side’s causes of action arise from under the contract.
See
Fisher Sand & Gravel Co. v. S.D. Dep’t of Transp.
,
6. Defendants also point to East Side’s complaint that only pleaded two causes
of action: (1) breach of contract for nоt “performing the construction in a good
and workmanlike manner[;]” and (2) NEXT’s negligence “in its construction
and supervision of its subcontractors on the work completed[.]” Defendants
argue that because the complaint did not outline each separate cause of
action East Side presents to this Court, it cannot raise those separate аctions
on appeal. We disagree. “South Dakota still adheres to the rules of notice
pleading[.]”
Gruhlke v. Sioux Empire Fed. Credit Union, Inc.
,
building prior to July 2004. Whether that actual notice is enough to put East Side
on constructive notice of its structural design error and construction error claims
(making the structural design error and construction error claims accrue prior to
July 2004), and whether that determination is a question of fact or law, is the heart
of this case. Because what a reasonably prudent person should inquire into when
learning of water infiltration can differ depending on the circumstances, we
conclude there is a genuine issue of material fact as to when East Side’s structural
design error and construction error claims accrued.
Huron Ctr.,
(. . . continued)
аre generally to be tried on the proofs rather than the pleadings . ” St. Pierre v. State ex rel. S.D. Real Estate Comm’n ,2012 S.D. 25 , ¶ 20,813 N.W.2d 151 , 157 (citation and internal quotation marks omitted). East Side adequately put Defendants on notice of its claims and presented evidence in support of its claims. Both in its response to NEXT’s statement of undisputed facts and at the summary judgment hearing, East Side claimed structural design errors and construction errors as reported by Ollerich. We conclude the issue was properly raised.
11,
Equitable Estoppel
[¶17.]
Equitable estoppel will only be applied when all four elements are
proven by clear and convincing evidence: (1) Defendants made false representations
to or concealed material facts from East Side; (2) East Side did not have knowledge
of the real facts; (3) the misrepresentations or concealment was made with the
intention that it should be acted upon; and (4) East Side relied upon those
misrepresentations or concealment to its prejudice or injury.
See Wilcox v.
Vermeulen
,
[¶20.] In conclusion, we reverse the circuit court’s ruling that barred East Side’s claims of design error and construction error, concluding that a genuine issue of material fact exists to determine when those claims accrued. We remand for further proceedings in line with this opinion. Furthermore, we affirm the circuit court’s grant of summary judgment on the equitable estoppel claim. GILBERTSON, Chief Justice, and KONENKAMP, ZINTER, and
WILBUR, Justices, concur.
7.
“A manufacturer’s efforts at repair subsequent to delivery do not extend the
contract statute of limitations.”
Jandreau v. Sheesley Plumbing & Heating
Co., Inc.
,
