MEMORANDUM OPINION AND ORDER
Before the court is the defendant’s motion for summary judgment, pursuant to Federal Rule of Civil Procedure 56. Plain
Facts
On or about July 13, 2004, defendant, the Town of Hempstead (the “Town”), awarded the plaintiff, East Coast Resources, LLC (“ECR”), contract number 34-2004, which governed the removal and transportation of certain agricultural waste from two Town-operated transfer facilities located in Oceanside and Merrick, New York to out-of-state recycling and composting facilities. (Def. R. 56.1 Statement (“Def.56.1”) ¶ 1; PI. R. 56.1 Statement (“PI. 56.1”) ¶ 1.) The initial contract period was a two-year term, from July 13, 2004 through March 31, 2006, with three one-year extensions available “at the Town’s option.” (Def. 56.1 ¶¶2, 4; PL 56.1 ¶¶ 2; 4; Riverso Decl., Ex. A at 5.)
While the contract did not provide for any minimum amount of agricultural waste to be shipped by ECR, expressly stating that “[n]o guarantee is given as to amounts of agricultural waste that will be available for shipping,” it did provide the estimated payments to be made each year that the contract was in effect. 1 (Riverso Deck, Ex. A at 5.) Nothing in the contract specifies whether either party is entitled to recover its lost profits in the event of a breach. (Def. 56.1 ¶5; PI. 56.1 ¶5.) On January 17, 2006, approximately two months prior to the expiration of the initial contract period, the Town exercised its option to extend the contract for one additional year, with the extension terminating March 31, 2007. (Def. 56.1 ¶6; PI. 56.1 ¶ 6.)
By letter dated March 24, 2006, ECR advised the Commissioner of Sanitation, Richard T. Ronan (“Ronan”), that the parties had “a few issues” that needed addressing. (Riverso Deck, Ex. D.) Specifically, ECR advised Ronan that although pursuant to the parties’ contract, “agricultural waste” is defined as “0% of contaminates in the material,” the waste ECR was collecting from the Town contained “15% contaminates on average.” 2 (Riverso Deck, Ex. D.) ECR informed Ronan that the presence of contaminates in the agricultural waste was “going to create a prohibitive situation from [its] recycling vendor,” and enclosed a letter from one of its vendors, Nature’s Choice, to demonstrate its point. (Riverso Deck, Ex. D.) ECR further advised Ronan that it had been notified by its other “organic recycler” that the product was “unacceptable,” and enclosed that letter as well. (Riverso Deck, Ex. D.) ECR requested “a more stringent ‘calling’ of the material into proper contractual classifications.” (Riverso Deck, Ex. D.)
ECR continued to perform its waste removal services for the Town until March 31, 2007. (Def. 56.1 ¶ 9; PI. 56.1 ¶ 9.) On January 8, 2007, the Town exercised its option to renew the parties’ contract for an additional year, terminating on March 31, 2008. (Def. 56.1 ¶ 10; PI. 56.1 ¶ 10; River-so Deck, Ex. E.) However, by letter dated February 9, 2007, ECR advised Ronan that due to certain circumstances outlined in the letter, it “must decline [the Town’s]
On April 17, 2007, the Town Council of the Town of Hempstead passed a resolution declaring that ECR was in breach of the parties’ contract and recommended that the Town commence litigation to recover damages sustained as a result of ECR’s purported breach. (Def. 56.1 ¶ 15; PL 56.1 ¶ 15; Riverso Decl., Ex. G.) Before the Town could do so, however, ECR commenced the instant litigation in the Eastern District of Virginia, alleging that the Town had breached the parties’ contract by commingling agricultural and non-agricultural waste. (Def. 56.1 ¶ 16; Pl. 56.1 ¶ 16.) ECR seeks lost profits for the last two years of the contract extension options that ultimately did not come to fruition, from April 2007 to March 2009. (Def. 56.1 ¶ 20; Pl. 56.1 ¶ 20.) ECR also seeks lost profits stemming from an oral agreement it had to act as a subcontractor for the agricultural waste removal vendor for the County of Westchester (the “Westchester Subcontract”), which ECR asserts it was forced to abandon as a result of the termination of its contract with the Town. (Def. 56.1 ¶ 21; PL 56.1 ¶ 21.) ECR did not file a written verified claim with the Town Clerk regarding its breach of contract claim against the Town prior to instituting litigation. (Def. 56.1 ¶ 17; PL 56.1 ¶ 17.)
The Town now seeks summary judgment on the ground that ECR’s failure to file a written verified claim against the Town before commencing litigation, as required under New York Town Law § 65(3), is fatal to this action. The Town further asserts that even if the Court excuses ECR’s failure to file a notice of claim, ECR cannot recover its lost profits under the parties’ contract because there was no contract in place for the time period for which ECR is seeking damages. Finally, the Town asserts that ECR cannot recover its lost profits under the Westchester Subcontract because such damages were not foreseeable to the parties at the time of contracting.
Discussion
I. Legal Standard
Summary judgment is appropriate when “the pleadings, the discovery and disclosure materials on file, and any affidavits show that there is no genuine issue as to any material fact and that the movant is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(c). The burden is on the moving party to establish the lack of any factual issues.
See Celotex Corp. v. Catrett,
The inferences to be drawn from the underlying facts are to be viewed in the light most favorable to the non-moving party.
See Matsushita Elec. Indus. Co. v. Zenith Radio Corp.,
When considering a motion for summary judgment, the district court “must also be ‘mindful of the underlying standards and burdens of proof ... because the evidentiary burdens that the respective parties will bear at trial guide district courts in their determination of summary judgment motions.”
SEC v. Meltzer,
Summary judgment should not be regarded as a procedural shortcut, but rather as an integral part of the Federal Rules of Civil Procedure, which are designed to “secure the just, speedy and inexpensive determination of every action.”
Celotex,
II. The Notice of Claim Requirement
Pursuant to New York Town Law Section 65,
[N]o action shall be maintained against a town upon or arising out of a contract entered into by the town unless the same shall be commenced within eighteen months after the cause of action thereof shall have accrued, nor unless a written verified claim shall have been filed with the town clerk within six months after the cause of action shall have accrued, but no such action shall be brought upon any such claim until forty days have elapsed after the filing of the claim in the office of the town clerk.
N.Y. Town Law § 65(3). “A properly verified notice of claim is a condition precedent to maintaining an action to recover damages for breach of contract against a town.”
ADC Contracting & Constr., Inc. v. Town of Southampton,
There is no dispute in the within action that plaintiff failed to file a notice of claim prior to commencing litigation. Plaintiff asserts, however, that its failure to do so should be excused on the grounds of waiver or estoppel. The Town contends that plaintiffs failure to file a notice of claim is fatal to its breach of contract claim, which is the only claim at issue herein, and therefore the entire action should be dismissed.
“To successfully invoke the doctrine of equitable estoppel, ‘[t]he plaintiff must have relied on the defendant’s actions, and that reliance must have been justifiable.’ ”
Drake v. Laboratory Corp. of Am. Holdings,
No. 02-CV-1924,
Several New York cases have applied estoppel to preclude the defendant from asserting the lack of a notice of claim as a defense, particularly where, as here, “defendant received actual notice of the claim and did not raise the issue of lack of formal notice for over two years, instead allowing the case to proceed through discovery. ...”
Lebanon Valley Landscaping, Inc. v. Town of Nassau,
In a similar action,
Town of Smithtown v. Jet Paper Stock Corp.,
The same result is warranted here. In the more than two years that this action has been pending, The Town of Hemp-stead never once raised the issue of ECR’s failure to file a notice of claim as a defense to liability until practically the eve of trial when the parties appeared before the Court for a pretrial conference. It is not asserted in the Town’s Answer; nor is it contained in the parties’ joint pre-trial order. Moreover, when advised by ECR that it would no longer perform under the contract after March 31, 2007, and that ECR considered the Town to have breached the parties’ contract, the Town Council passed a resolution authorizing the commencement of litigation against ECR for breach of the same contract. Since the Town planned to pursue claims under the same contract as ECR' — but just so happened to have lost the race to the courthouse — its “reliance upon the notice of claim requirement is more in the nature of a sword than a shield.”
Jet Paper Stock Corp.,
As stated
supra,
notice of claim statutes are “intended to foster early investigation of claims and to facilitate settlements prior to the initiation of litigation.”
Steimel,
For the foregoing reasons, the Town is estopped from raising ECR’s failure to file a notice of claim as a defense to liability in this action and that portion of the Town’s summary judgment motion is denied.
III. Lost Profits
“Contract damages are ordinarily intended to give the injured party the benefit of the bargain by awarding a sum of money that will, to the extent possible, put that party in as good a position as it would have been in had the contract been performed.”
Goodstein Constr. Corp. v. City of New York,
Here, it is undisputed that the contract between the parties expired on March 31, 2006, with three one-year extensions available, solely at the election of the Town. (Riverso Deck, Ex. A at 5.) It is further undisputed that the Town opted to use the first of those extensions, with the contract therefore terminating on March 31, 2007. While the Town sought to exercise its second option to extend the parties contract in 2007, by letter dated February 9, 2007, ECR stated that it was declining the Town’s extension request. (Riverso Deck, Ex. E.) In March 2007, ECR further advised the Town that it would not perform under the parties’ contract after its expiration on March 31, 2007. (Def. 56.1 ¶ 12; PI. 56.1 ¶ 12; Compl. ¶ 53.) Accordingly, as of April 1, 2007, there was no longer a valid, enforceable contract between the parties.
Notwithstanding the absence of a contract, and ECR’s refusal to further perform, ECR seeks to recover its lost profits for the two option years that ultimately never came to fruition, from April 1, 2007 through March 31, 2009. In a similar case cited for support by the Town,
Marketing & Management Information, Inc. v. United States,
ECR argues that “where there is ‘no contractual right to a renewal term, ... the question is purely one of fact, and should be submitted to the jury only if there [i]s evidence in the record that renewal was reasonably likely under the circumstances.’ ” (PI. Mem. of Law 23) (citing
Koufakis v. Carvel,
Based on the foregoing, the Court finds that the contract between the parties ceased on March 31, 2007. ECR refused to perform under the additional option year sought by the Town and therefore, ECR cannot recover on its claim of lost profits from April 1, 2007 to March 31, 2009. Accordingly, the Town is granted summary judgment with respect to ECR’s claim for lost profits for the two option years that were not fulfilled and such damages claims are hereby dismissed.
IV. The Westchester Subcontract
ECR also seeks to recover its lost profits under the Westchester Subcontract on the grounds that as a result of the Town’s breach of the parties’ contract, ECR was forced to abandon the Westchester Subcontract. The Court notes that a claim for such damages is not included anywhere in ECR’s Complaint. According to the Town, and which ECR does not dispute, this claim was asserted for the first time in ECR’s expert disclosure. (Def. Mem. of Law 4.)
In addition to general contract
damages
— ie., damages that flow from the natural and probable consequences of the breach — a plaintiff asserting a breach of contract claim may also recover “special” or “consequential” damages, which compensate for “additional losses.”
Lorena Int’l N. Am., Inc. v. Vican Trading,
No. 08-CV-2686,
In the within action, the parties’ contract is completely silent with respect to damages, including consequential damages. “Where the contract is silent on the subject of consequential damages, the court must take a ‘common sense’ approach, and determine what the parties intended by considering ‘the nature, purpose and particular circumstances of the contract known by the parties ... as well as what liability the defendant fairly may be supposed to have assumed consciously.’ ”
Lorena Int’l,
In support of its claim, ECR argues that the Town was aware of the Westchester Subcontract because it was listed in the “Information Schedule F” that was annexed to the parties’ contract. (PI. Mem. of Law 25.) ECR further argues that its “Westchester contract was what brought the parties together and a focus of their discussions leading into the contract.” (PI. Mem. of Law 25.) According to ECR, the Town sought it out because it knew of “ECR’s experience performing a similar contract specifically for the County of Westchester ... and heard good things from Westchester about ECR’s performance.” (Appelget Aff. ¶ 6.) ECR maintains that the Westchester Subcontract was “prominently featured” in its negotiations with the Town “as support for ECR’s bid and qualifications.” (Appelget Aff. ¶ 7.)
While the Town may have indeed been aware of ECR’s Westchester Subcontract, awareness is not the same as reasonable contemplation that the Town would be responsible for any damages incurred by ECR with respect to that contract. There is no evidence in the record before the Court that the parties ever discussed lost profits liability whatsoever, let alone with respect to ECR’s separate and distinct Westchester Subcontract. “No case has been found to suggest that defendant ] should be held responsible for
other
contracts that plaintiff would have made [or did make] with
other
parties.... ”
David v. Glemby Co., Inc.,
Moreover, assuming that the Westchester Subcontract was the incentive for the within contract, as ECR maintains, this does not constitute evidence that if the within contract should fail, the Westchester Subcontract would also fail. In fact, ECR has not proffered any evidence whatsoever to support its claim that the Westchester Subcontract “rose or fell” with the within contract. (PI. R. 56.1 Counter-Statement ¶ 19.) Rather, ECR offers
For the foregoing reasons, the Court finds that ECR’s lost profits under the Westchester Subcontract were not reasonably foreseeable or within the parties’ contemplation at the time of contracting. Additionally, ECR has failed to establish adequate facts from which a jury could reasonably infer that the termination of the within contract was the proximate cause for loss or termination of the Westchester Subcontract. Accordingly, as a matter of law, ECR is not entitled to damages with respect to the Westchester Subcontract and the Town’s motion for summary judgment with respect to any claim for damages arising from ECR’s loss of the Westchester Subcontract is granted.
Conclusion
For the foregoing reasons, defendant’s motion for summary judgment is granted in part and denied in part.
SO ORDERED.
MEMORANDUM OPINION AND ORDER
Before the court is the plaintiff, East Coast Resources, LLC’s (“ECR”), motion for reconsideration of the Court’s prior Memorandum Opinion and Order, dated April 21, 2010, in which it granted summary judgment to the defendant, the Town of Hempstead (the “Town”). ECR only challenges that portion of the prior decision that pertains to ECR’s claim for lost profits for the two option years of the parties’ contract that were ultimately not exercised. ECR does not seek reconsideration of the remaining portions of the prior decision. For the following reasons, ECR’s motion is denied.
Facts
Familiarity with the facts of the underlying action is presumed. By Memorandum Opinion and Order dated April 21, 2010, the Court granted the Town’s motion for summary judgment and found that, as a matter of law, ECR was not entitled to seek lost profits for the two option years of the parties’ contract that were not exercised. (Mem. Op. and Order 13.) The Court based its decision on the fact that although the Town sought to exercise the second of the three option years in January 2007, ECR refused to do so and formally advised the Town by letter dated March 28, 2007 that it would not continue to perform under the parties’ contract as of March 31, 2007. (Mem. Op. and Order 11-13.) Accordingly, the Court found that the contract between the parties ceased— at ECR’s direction-as of March 31, 2007 and therefore ECR was not entitled to seek damages for lost profits for the two option years that were not exercised, since it had refused to perform. (Mem. Op. and Order 13.)
ECR now seeks reconsideration of that decision on the grounds that the Court overlooked controlling legal precedent by the Second Circuit,
i.e., Koufakis v. Carvel,
Discussion
I. Legal Standard
Motions for reconsideration in this district are governed by Local Civil Rule
“To prevail on a motion for [reconsideration], the movant ‘must demonstrate that the Court overlooked controlling decisions or factual matters that were put before it on the underlying motion.’ ”
Church of Scientology,
II. ECR’s Motion for Reconsideration
A. Submission of New Evidence by ECR
As a threshold matter, the Town asserts that ECR has submitted new evidence in connection with its motion for
B. Basis for ECR’s Motion
The basis for ECR’s motion for reconsideration is that the Court overlooked controlling legal precedent when rendering its decision on summary judgment,
i.e., Koufakis v. Carvel,
Moreover, ECR repeatedly asserts that its decision to terminate the parties’ contract was in response to the earlier alleged breach by the Town, whereby the Town mixed agricultural and non-agricultural waste together in violation of the contract.
2
However, the alleged breach by the Town occurred as early as 2005 and was communicated to the Town by ECR by letter dated March 24, 2006. (Mem. Op. and Order 2.) When advising the Town of the alleged contamination of the waste, ECR only informed the Town that it had “a few issues” that needed to be addressed and requested that the Town follow the provisions of the contract more closely. (Mem. Op. and Order 2-3.) At no point prior to its termination of the contract in 2007 did ECR inform the Town that it already considered the contract to have been breached. In fact, ECR continued to perform waste removal services for the Town for
Where one party breaches a contract, the other party has two choices: (1) it can “elect to allege a total breach, terminate the contract and bring an action;” or (2) it can “elect to keep the contract in force, declare the default only a partial breach, and recover those damages caused by that partial breach.”
Carco Group, Inc. v. Maconachy,
Here, ECR elected to continue the parties’ contract after the alleged contamination by the Town and continued to receive payment from the Town for its waste removal services. Accordingly, ECR did not assert its right to terminate the contract based on the Town’s alleged earlier breach. Thus, ECR was obligated to fully perform its duties under the contract, which included three renewal terms, exercisable solely at the Town’s discretion. When the Town sought to invoke the second of the three renewal terms, ECR refused to comply and therefore terminated the parties’ contract. As held in the previous decision, ECR’s termination of the contract resulted in there being no valid contract in effect upon which ECR could assert a claim for lost profits for the two unexercised option years. (Mem. Op. and Order 11-13.)
Accordingly, ECR’s motion for reconsideration is denied.
Conclusion
For the foregoing reasons, plaintiffs motion for reconsideration is denied. The Clerk of the Court is directed to enter judgment in favor of the defendant and to mark this case as closed.
SO ORDERED.
Notes
. The contract expressly stated that the "tonnage amounts [were] ESTIMATES ONLY," which would be used "for evaluation purposes” and "[did] not represent actual amounts anticipated to be received by the Department of Sanitation.” (Riverso Deck, Ex. A at 6.)
. Prior to this letter, in June 2005, plaintiff sent photographs and a video to the Town depicting the mixing of agricultural and non-agricultural waste by the Town. (Def. 56.1 ¶ 8; PL 56.1 ¶ 8.)
. ECR asserts that the Town had already breached the parties’ contract by mixing agricultural and non-agricultural waste together prior to ECR’s rejection of the contract extension. (PL 56.1 ¶ 11.)
. The Court notes that ECR makes much of the fact that the Town did not move for summary judgment until "the eve of trial,” after "ECR spent years developing its damages theory for the benefit of a jury.” (PL Mem. of Law 2.) ECR repeats this refrain throughout its motion for reconsideration. However, it is black letter law that "[s]ummary judgment is properly regarded not as a disfavored procedural shortcut, but rather as an integral part of the Federal Rules as a whole, which are designed to 'secure the just, speedy and inexpensive determination of every action.’ ”
Celotex Corp. v. Catrett, 477
U.S. 317, 327,
. This is the same argument ECR advanced in response to the Town's motion for summary judgment.