*1 CORP., THE A OF CORPORATION FIRE PROTECTION EAGLE PLAINTIFF-APPELLANT, JERSEY, v. FIRST OF NEW STATE COMPANY, DEFEN- INSURANCE AMERICA INDEMNITY OF DANT-RESPONDENT. 29, 1996 July January
Argued Decided *3 Glavin, Jr., respondent. for Joseph C. argued the cause curiae, on of amicus Armen Shahinian submitted a brief behalf Samson, attorneys; (Wolff & Surety of America Association The Shahinian, Monaghan, on the Joseph D. Ferrucci James Mr. brief). of the court was delivered opinion
The GARIBALDI, J. question: deter- of one appeal concerns the resolution
This claimant must period under which a one-year limitation mining the bond, surety general institute a suit in a does a when contractor Specifically, “cease work” under a construction contract? we must determine if the work of subcontractors on a construction site general constitutes the work of the contractor.
I May Parkway In (Parkway), 185 Monmouth Associates a partnership, plans limited finalized its to renovate an office build- ing. plans, 1989, Parkway Pursuant to those hired Hassold, (Olsen), Olsen & Inc. charge as contractor Parkway the renovation. The contract between and Olsen envi- I, phases. sioned three In Phase Olsen was to remove the building. asbestos in the Phase II consisted of the reconstruction III, building, and restoration of the Phase Olsen was to partitions erect building. certain metal in the Olsen never reached III Phase due to its financial demise. obligations
One of Olsen’s under the contract was to hire a surety company guarantee that would perfor- Olsen’s successful result, mance of its contractual purchased duties. As a Olsen series of bonds from First of America Insurance Co. (First Indemnity), agreed guarantor. who to act as Olsen’s particular implicated in this case ais “labor and material provided bond.” Indemnity, That bond surety, as would pay Olsen, claims made principal, subcontractors of as where paid ninety contractors had not been in full days within of the completion bond, drafting subcontractor’s work. parties simply filled in the blanks of the American Institute of Architects’ standard payment-bond labor-and-material form. *4 Parkway
The Phase II building renovation of the included the sprinkler system installation of a in building. purchased the Olsen sprinkler system the Eagle Corp. from Fire (Eagle Protection Fire), $129,437.50. and system hired it to install Eagle the for working Fire started project mid-September on the in 1989 and completed it in July June or progress of 1990. Olsen made payments Eagle Fire early from October 1989 to 1990. Howev- bounced, by May er, Olsen a later installment check from Eagle stopped making payments to Fire. When Olsen had Yinsko, that he began William to sense Eagle president, Olsen, attempted difficulty collecting from he to con- have would under bond. Indemnity regarding obligation its' tact First However, Indemnity to return numerous calls made First failed Parkway Eagle then representative on Fire’s behalf. Vinsko a Massell, counsel, Esq., or to obtain from Olsen retained Gerald Eagle sprinkler for the Indemnity money First owed vice-president system spoke with an Olsen installation. Massell April May to elicit in or but was unable about Olsen’s debt similarly his payment Massell was unsuccessful from Olsen. Indemnity persuade pay eight month First Olsen’s effort Eagle debt to Fire. 11, 1990, Parkway September terminated its contract with
On bankruptcy. April filed for On Olsen. Olsen Indemnity, claiming that against First Fire filed suit Indemnity sprinkler- First liable for Olsen’s the bond rendered Indemnity First system The sole offered debt. defense timely manner, not its in a that Fire had commenced suit recovering First precluded under bond. and was thus from argument following provision on based bond: hereunder claimant:
No suit action shall commenced by any b) following [Olsen] date on which ceased one expiration year After being if limitation understood, it [the] Contract, however, any work controlling law the construction hereof embodied in this bond is any prohibited by minimum so as to be such limitation shall be deemed to be amended equal added). (Emphasis such law. period permitted by had, fact, suit commenced its Eagle Fire countered that it day that Olsen “ceased work” on within if argued suit had Eagle Fire in the alternative contract. manner, fault of timely that was the not been commenced representatives, employed delaying tactics Indemnity’s who bringing specified misled Fire into not suit within one-year window. *5 1) testimony trial on two the focused issues: date Olsen 2) contract; work” under the and actions
“ceased the taken Indemnity eight that suit led not to file until surety company. months after its initial contact with compliance period, To establish limitation its with bond’s prove Fire had to that Olsen “ceased work” Puth, agent Parkway, managing Edward for that testified working September was under Olsen the contract until Parkway of when terminated the contract because Olsen’s finan- inability support cial to fulfill its that contractual duties. conclusion, through presence Puth discussed the on the worksite September parti- 1990 of trailers Olsen had rented store tions that were used Phase III. Those trailers led Puth “working” conclude that Olsen was under contract until prior ultimate cancellation. Puth admitted that time at some contract, although the cancellation of he not remember could date, stopped exact paying company Olsen for the rental of trailers. The last Puth employee use time that saw an Olsen on employee LaHaye, site was “mid-1990.” That Edward was division, the Vice-President of Olsen’s asbestos removal with day whom met on that Puth Puth occasion. did not know the last employees physically working that Olsen were site. testified William Vinsko for Fire that Olsen was “still on job” January February as of working in different building. parts jury Defense counsel read to the Vinsko’s deposition testimony, in which he stated that Olsen had left by January site 1990. Vinsko testified that Olsen’s subcontractors working July August were site through at the perhaps even later. LaHaye Indemnity
Ed day testified for First the last employees physically Olsen worked at the under the site contract conceded, however, September 1989. He that when he position resigned from his in August with Olsen the metal partitions being were still stored in trailers on the site. attempted to that First
Eagle Fire also establish *6 on Eagle filing Fire not suit an misled or lulled into impermissibly attempt to that his first obtain earlier date. Massell testified 1990, 18, Indemnity September when payment from First was on company inform it had surety he to to that Olsen wrote the warned, He “If debt Fire. this matter defaulted to against twenty days, I file within will suit cannot settled September Massell received a Indemnity.” On First Alongi, Operations proof loss and a short note from Paul of form Indemnity. Alongi note informed Massell Manager at the First of form Indemni- receipt completed proof loss First that on validity ty investigation the of begin its into would 1990, 30, completed Massell returned the On November claim. days four later he had a proof Indemnity of to First loss regarding Although the claim. telephone Alongi with conversation Alongi, subsequent attempts reach Massell never made to Massell Alongi. from heard February Massell had several
From 1990 to December Galdieri, independent Frank an claims telephone discussions with Indemnity investigate Eagle Fire’s adjuster by to hired 10,1990 conversation, told Massell In a December Galdieri claim. stall, Indemnity attempting to if felt that First was that Massell in a he memorialized this conversation should file suit. Massell After a that he sent to Galdieri. December 1990 letter February in he had with Galdieri conversation that Massell employing stalling that First began to believe good filed suit negotiating not in faith. Massell tactics and was testified for First three months later. Galdieri approximately and, dispute testimony. Indemnity, general, did not Massell’s testimony acknowledged his Galdieri never told Massell him not to suit. file parties made a motion for of all the evidence both
At the close trial court judgment. trial denied both motions. The court part: jury, pertinent instructed the If find the filed it’s action than one Protection, more you plaintiff, general contractor, Hassold, site, after the Olsen & ceased work at then enter a should verdict for defendant of no cause of action. you I instruct that the work done subcontractors Hassold you Olsen & by further does not constitute work done Olsen and themselves. by Hassold And therefore site absence such subcontractors at the is not 2S, presence May relevant Unless find First Indemni- you any representative defendant, design filing misled accident or Mr. Massell him so as cause ty, delay suit under he did not the bond and do should return a for the timely so, verdict you added). (Emphasis defendant. following special The court also interrogatories submitted jury: 1) project Did the work Hassold on Olsen and cease before 1990? 2) negotiations, Did conversations and communications between the plaintiff being filing and the defendant result in the caused of the suit plaintiff delay 23,1991? until May answering interrogatories jury Prior to those asked the court *7 site, “If there are subcontractors the does that mean Olsen and Hassold would be considered to the be on site?” The trial court that “[T]he stated answer is no.” Plaintiffs counsel who had objected original to regarding the court’s instruction the instruc- tion work that subcontractor’s should be deemed the of work Olsen, objected response jury’s also to the court’s question. the jury questions affirmative, The answered both in the returned a Fire, Eagle $63,414. verdict for damages and assessed at On stipulation of parties, the trial court reduced the award $60,825. rejected The Eagle ensuing trial Fire’s application court attorney’s for fees. Appellate
The
Division reversed.
Fire v. First Indemni
ty
Corp.,
430,
N.J.Super.
Insurance
655
(App.Div.
280
A.2d 939
1995).
proofs
The court
found that
“the
raised a
issue
factual
by
jury
for resolution
as to
working
whether
was still
or
Olsen
supervising
439,
Thus,
1990.” Id. at
353
tolling
of a
explained
A.2d
The court
that “the
655
939.
conduct, requires
statutoiy
due to
some
contractual or
limitation
part
the insurance
type
conduct on the
of
of unconscionable
Id. at
negotiations
not
and discussions.”
company and
mere
could not be said to
We (1995), 1363 and now reverse. A.2d II resulting relation from an “Suretyship is a contractual surety, be agreement whereby person, engages answer debt, another, miscarriage principal.” able for the default Co., Corp. v. Fed. Ins. Amelco Window surety, Indemnity, agreed (App.Div.1974). Olsen, principal. The answerable for debts entered into express language the Labor and Material Bond any granted also Fire and other and First Olsen standing provisions. to enforce the bond’s Olsen subcontractors Co., 17, 20, 206 Schlanger v. Ins. 44 N.J. A.2d 874 See Federal supra, N.J.Super. at Corp., 346- and Amelco Window A.2d 398. The bond defined a claimant as *8 having or of the a with with a subcontractor direct contract the Principal for use in the or or labor, both, for used material, reasonably required Principal of the Contract. performance Olsen, principal, with Fire had a direct contract the Because standing party beneficiary under it a third had as recognizes Indemnity. “The Olsen and First Law between surety promises in right if the party has an enforceable the third bond, by implication, to express or reasonable either in words 354
pay money
Corp., supra,
to him.” Amelco
127
Window
N.J.Su
346,
per. at
As
third
of
rights
are determined
terms of the bond.
“It
is well
party beneficiary’s rights depend upon,
settled that
third
‘[a]
by,
promisor
are measured
terms
contract between the
”
Constr.,
promisee.’
and the
&
Ribeira
Laurenco Concrete
Inc. v.
Associates,
16, 21,
N.J.Super.
Jackson Health Care
231
554 A.2d
o.b.,
(App.Div.1989),
1350
118
571
1311
N.J.
A.2d
aff'd
Lees,
(quoting
N.J.Super.
Roehrs v.
178
Ill provisions limiting parties Contract may bring time suit enforceable, have been held to be if reasonable. See Weinroth v. Jersey Co., New Ass’n Ins. 117 N.J.L. 189 A. Mfrs. (E. Ribeira, A.1936); 73 supra, 22-23, & N.J.Super. 231 554 1350; Orange A.2d A.J. Assocs. Tenwood v. Senior Citizens Co., 515, 523-24, Housing (App. A.2d 1280 Div.), denied, (1985); 101 N.J. Staehle v. certif. Co., Employers’ N.J.Super. 152, 154, American Ins. 246 A.2d (App.Div.1968).
Holding provision enforceable an insurance contract limit- ing the may bring year, time which claimants suit to one Weinroth, supra, Court in observed: determining whether in an provision insurance contract conflicts with any laws this test state, should be whether for, terms provide
355
unable to
any
statute
and
We are
observe
that which the
forbids
prohibit.
permit,
after six
as
in
that no suit can be instituted
conflict,
effect,
the statute provides,
agree
it
contract
that
but
not make
unlawful for
does
parties
years,
for a lesser
limitation shall be
period.
73].
at
189 A.
117 N.J.L.
[Weinroth,
supra,
Associates,
supra,
Appellate
Similarly,
A.J. Tenwood
one-year
period
limitation
contained in
Division
that a
found
200
unfair nor unreasonable.
construction contract was neither
that
N.J.Super.
491
1280. The court observed
at
A.2d
Jersey
limitations in
for contract
although
New
the statute
by express
may
limitation
be waived
years,
is
“such a
actions
six
Ibid,
omitted).
(citation
is funda
agreement
parties.”
“It
of the
barring
agreements, a
such
mental
in the absence of a statute
bringing
action
stipulation limiting the time for
an
contractual
period
prescribed
than
upon a
to a
less
contract
stipulated period is reasonable
foregoing
is valid if the
statute
523-24,
Finally, Concrete Ribeira & Lourenco that contained the payment involved a labor material case. limitation found in the bond this one-year provision same Appellate A.2d 1350. The Division N.J.Super. at 554 enforceable, id. and therefore provision found the reasonable 22-23, that decision. 118 N.J. A.2d and we affirmed (1990). 419, 571 A.2d1311
Indeed, routinely provisions contract upheld this Court has may one-year limitation in which claimants time that create a one-year provision in First bring Accordingly, limitation suit. Indemnity’s There surety bond reasonable and enforceable. depend on fore, Eagle ability bond will recover under the year within one date filed suit whether ascertaining the the contract. Olsen “ceased work” under work,” goal, as meaning the central the term “ceased generally, give effect to language interpreting contract Washington See Construction parties to the bond. intent (1951); Co., Town- Spinella, Inc. v. N.J. Wyckoff v. Sarna, 512, 516-17, .2d 16 *10 ship 136 347 A of (App.Div.1975). long surety chargeable
“It has
been settled law that a
is
only according
undertaking
the strict
terms of its
and
obligations
by implica
be
cannot
should not
extended either
by
beyond
or
the
tion
construction
confínes of its contract.” See
America,
Monmouth
Co. v.
N.
21
Lumber
Ins. Co. of
439,
(1956);
452,
Peoples
N.J.
122 A.2d604
Bank N.J.
National
Fowler,
88,
den,
101,
1096,
858,
v.
73 N.J.
372 A.2d
cert.
434 U.S.
182,
(1977).
rule, however,
98
54
131
been
S.Ct.
L.Ed.2d
That
has
modified,
language
ambiguous.
if the
in
the construction
Son,
Co.,
V. Petrillo &
Inc. v. American
148
Const.
denied,
(App.Div.),
the contract
reference
Olsen and
Inc.
Principal
agreement
has
written
dated
entered
into a contract with Owner for re-insulated structure & install
Therefore,
sprinkler systems____”).
ascertaining
meaning
provisions,
of the bond’s
the bond and
contract
must
integrated
E.g., Schlanger, supra,
considered as one
document.
874;
Corp.,
N.J.
206 A.2d
Amelco
supra,
Window
N.J.Super. at
procurement by removal services and certain construc- Company obligation tion work, which shall include Contractor’s to the supervision, furnish engineering, tradesmen, vehicles, tools, materials, identification, equipment, pack- aging, labeling, as the asbestos transportation disposal required perform removal services and construction work as in the applicable further defined (the “Work”) drawings and attached hereto or specifications in the referenced added). Agreement. (Emphasis orders to this placed pursuant language supports That Eagle Fire’s contention that Olsen First, May ceased its “work” on the contract after Scope Agreement section notes that “Work” is defined in the “drawings specifications” attached to the in contract and placed pursuant “Orders significant to” the contract. That is purchase calling partitions because a order for Olsen to “store site trailers” was attached to the contract as Exhibit A-l. Moreover, Parkway’s specifications, bid attached to the contract as Exhibit-C, general obligation also noted the contractor’s to store 23,1990. partitions past May the trailers well
A concluding second basis for working that Olsen ceased undisputed testimony is the that Olsen subcontrac- working July August tors were under the contract as late as or 1990. That the work of the subcontractors constituted work of the general gains support language contractor from the of the con- Agreement Scope of section in the
tract. As stated supervision” of contract, “furnish[ing] the included “work” Olsen’s Lahaye, vice-president, an Olsen construction work. Edward supervise contractual duties was part that of Olsen’s confirmed supported Section 34 That conclusion the subcontractors. contract, performed subcon- the “work” which discusses contract, which discusses Olsen’s 36 of the tractors and Section duty supervise its subcontractors. world, may determine today’s general contractor
In business instead any physical labor on the work site and not to undertake context, if out all of the work subcontractors. contract not include the work of general contractor does “work” of subcontractors, would be deemed to cease general contractor owner of the day signed its contract with the work the same that it (or its last day general contractor hired project subcontractor). longer took that one If the subcontractors’ work period expire before the subcon- year, the limitation would bond’s not be what the their That result could tractors finished work. parties to the bond intended. defining to exclude the work of the problems
The
with
“work”
are demonstrated
this
subcontractor of a
contractor
bars claimants from
provision
contains a
case.
days
expiration of 90
after the date on
bringing suit “before the
claimant’s work or labor was done
which the last of such
Thus,
Indemnity’s argument
accepts
if
performed.”
September
working
contract on
ceased
under the
that Olsen
*12
Fire,
of the
Eagle
completed the installation
then
which
sprinkler system
July
would have had at
June or
Eagle
completed
if
Fire
days
bring
Specifically,
most ten
to
suit.
1,1990,
day
the first
that it could have filed
its work on June
then
later,
ninety-one days
August 30.
complaint
its
would have been
8, 1990,
filing
September
Eagle Fire’s deadline for
suit was
Hence, Eagle Fire would
year
allegedly
after Olsen
ceased work.
only
days
ten
to file suit.
have had
completed
If
any
its work
time after June
ninety day period
then the
Septem
would have ended after
8,1990,
ber
any
Fire would not
opportunity
have had
complaint against
file a
Indemnity.
Such a severe restric
tion on
ability
bring
suit would be both unreason
Co.,
able and unenforceable.
Excavating
See Camelot
Inc. v. St.
Co.,
Paul Fire and Marine Insurance
410 Mich.
301 N.W.2d
(1981).
Camelot, supra,
Michigan
In
Supreme
Court, addressing what is a
provision
reasonable contractual
for a
suit,
time limitation in which all
bring
claimants must
observed:
general
The
boundaries
what
is reasonable under
rule
require
investigate
claimant have sufficient
and file an
opportunity
action,
the time
abrogation
right
not be so short as to work a
of the
action,
and that the
practical
damage
action not be barred
before the loss
can be ascertained.
(citations omitted)].
[Id.
Olsen’s work included the
work
its subcontractors.
Son, Inc.,
supra,
V. Petrillo &
a construction subcontractor
brought
against
general
an action
contractor
for amounts due
performed
for construction work
on a
housing
moderate-income
project partially
Jersey
financed
Housing
the New
Finance
Agency.
2-3,
trial,
The bond contained a time provision requiring limitation plaintiff against institute suit St. Paul within one American “ceased work” incorpo- under the contract. The bond *13 contract reference and the
rated the construction contract obligations upon the totality imposed as defined work “the at trial by all Ibid. The evidence contractor contract documents.” (1) plaintiff following: performed the the last work demonstrated (2) American, 1972; defendant, 17, property on the August on the 4, 1972; the performed project work the on Oct. last on by any Ibid. last work done subcontractor December 1974, eighteen per- after the months last subcontractor work, plaintiff the suit. The contract also formed instituted Ibid. final property the owner of to issue a certificate of directed the acceptance all Ibid. correction of construction defects. A certificate was never issued. Ibid. work,”
Construing
“completes
the term “ceases work” to mean
judge
acceptance
found
a
the trial
that because
certificate of final
issued,
general
been
had never ceased
had never
contractor
meaning
within the
of the contract.
at
Construction,
Inc.,
1350,
16,
supra,
N.J.Super.
231
554 A.2d
argument
supports
its
that
the actions of subcontractors
are
irrelevant
to the determination of when the contractor ceased
case,
general
In
its entire
work.
that
contractor subcontracted
Inc., which,
turn,
job
Enterprises,
to Green Cast
subcontracted
companies, including
plaintiff. Ri
the work to various other
beira,
19-20,
supra,
at
Ribeira can be
from this case.
recogni-
court’s refusal to look to the subcontractors’ work was a
subcontractors,
regardless of the actions of
a contrac-
tion that
working
project
could
said to be
on a
after its contract
tor
not be
and it
dismissed from
work site.
had been terminated
has been
case,
However,
terminated until
this
Olsen’s contract was not
23,
September
May
Fire filed this action on
Furthermore,
1991,
one-year
subcon-
within the
window.
Olsen
23, 1990, giving
May
after
working
project
on the
tractors were
May
to file suit.
subsequent
until a date
presented at trial
indicated
evidence
The uncontroverted
subcontractors
storing
partitions and that Olsen’s
metal
Olsen was
August
July
as
working under the contract as late
were
Therefore,
jury
could not
a reasonable
past
well
untimely. The trial court
suit was
conclude
jury’s
jury and in answer to the
in its instruction to the
erred both
by subcontractors
responded that “the work done
question when it
by Olsen and
not constitute work done
and Hassold does
Olsen
denying
the close of
It
erred in
themselves.”
also
Hassold
judgment as a matter of law.
Eagle Fire’s motion for
evidence
America,
See,
142 N.J.
e.g.,
v.
Ins. Co.
Brill Guardian Life
trial,
(holding that
send a case
“[t]o
is indeed
knowing
jury can reach but one conclusion
that a rational
*15
Ferdinand v.
”);
purpose’
no useful
and will ‘serve
“worthless’
Co.,
482, 493,
(1956)(noting
Agricultural Ins.
N.J.
IV Finally, attorney’s Eagle Fire is not entitled to fees. 4:42-9(a), legal Pursuant to R. “no fee for services shall be allowed except Upon or ... In an action the taxed costs otherwise insurance, liability indemnity policy in favor of a or successful 4:42-9(a)(6). question R. then claimant.” The whether obligation surety company pay of a under a labor and material liability indemnity policy of insur ment bond constitutes “a commentary following provides ance.” The R. 4:42-9 that “since permit intention of this rule an award of counsel the stated only indemnify fees where an insurer refused to or defend another, respect party liability of its insured’s third it should extended, terms, beyond express permit not be a counsel fee brings against an award to be made to insured who direct suit his Pressler, casualty coverage.” insurer to enforce or other direct Rules, (emphasis R. 4:42-9 Current N.J. Rules Court Comment added). parties litigation rule is that should bear their Bros., legal
own costs. Coleman v. Fiore 113 N.J. (1989). fact, ] A.2d 141 “our court rules ... the view embrace[ judicial by having that sound administration will best be advanced *16 litigant except in each bear his own counsel fee those few situa Cos., designated.” specifically tions v. Ins. Gerhardt Continental (1966). 291, 301, 48 N.J. 225 A.2d328 4:42-9(a)(6) “only express applies The terms of Rule state that it indemnify when ‘an insurer refuses to or defend its insured’s third party liability to another’ and does not authorize an award of against counsel fees to an insured ‘on a direct suit the insurer to 364 ” coverage.’ v. casualty first-party direct Giri a or other
enforce
Inter-Insurance,
N.J.Super.
The insurance contract in this case did not constitute a commit- Indemnity pay Eagle liability ment First to a third Rather, party indemnify Eagle or to liability. Fire for such simply required Indemnity pay Eagle First Fire for its if work Olsen did not do so. Because this is a case where the not R. agreed claims, protect third-party insurer the insured from 4:42-9(a)(6) inapposite. Accordingly, is given we hold that of R. 9(a)(6), scope Eagle legal narrow not entitled to 4:42— fees.
V Eagle Fire commenced suit within one of the date that Complying Olsen ceased work under the contract. with the terms bond, surety judgment of the against Fire is entitled to Indemnity not, however, First as a matter of law. Fire is attorney entitled to an award fees and must bear its own litigation judgment Appellate costs. We reverse the Divi- sion entry and remand the matter to the Law Division for judgment opinion. consistent with this
HANDLER, O’HERN, COLEMAN, JJ., join STEIN opinion. Justice GARIBALDI’s
POLLOCK, J., separate dissenting opinion. filed a WILENTZ, C.J., participate. did not POLLOCK, J., dissenting. dispositive plaintiff, Eagle issue is whether Fire Insurance Fire), defendant,
Company (Eagle against instituted this action (First Indemnity Company First of America Insurance Indemni- ty), one-year period required by Indemnity’s within the performance bond. First furnished the bond to a contractor, Hassold, (Olsen), guaranty Olsen & Inc. payment Olsen’s to subcontractors such as Fire.
The bond bars an action commenced year after Olsen responsibilities I accept premise that Olsen’s ceased work. *18 supervi only furnishing of also the “included not workers but Eagle Fire v. storing tradesmen and the of debris.” sion of the Ins., A.2d 939 280 655 jury that Olsen work before (App.Div.1995). The found ceased later, May commenced this 1990. Over a Fire May straightforward interpretation A action on leads to the that the action is time-barred. bond conclusion limitations, one-year period of Fire To circumvent urges by work contractors constitutes Olsen’s done Olsen’s purpose determining the for the time within which work may Indemnity. Eagle Fire sue First also asserts that presence by of trailers after it ceased work leased Olsen otherwise majority adopts The likewise constitutes work. both Olsen’s I arguments. respectfully dissent. “ jury T
In its instructions to the
the Law Division stated that
you
by
instruct
done
further
that the work
subcontractors
Olsen
Hassold,
does not
Hassold them
&
constitute work
Olsen &
presence
and therefore the
or absence of such subcontrac
selves
”
Id. at
23rd,
at the site after
1990 is not
tors
relevant.’
jury).
(quoting
trial court’s
instructions
Appellate
entry
Division
instruction
affirmed that
and directed
Id. judgment
a
of no cause for action
favor of defendant.
substantially
After contractor has itself would not impute unsupervised to it the work of subcontractors that remain job. “Any performs original work on the a subcontractor after the obligations surety’s contractor’s have ended should not extend the liability, original it is since the conduct of the contractor which Ins., Hayward v. W.F. Transamerica relates.” (1993). Cal.App.4th. 468, 471-72 Cal.Rptr.2d agree I likewise courts with lower that after Olsen ceased work, presence on the work site of trailers that Olsen had repos- equally The date on which a lessor rented is irrelevant. from a work site should not sesses a contractor’s trailers surety determine the time to sue under that contractor’s bond. I dissent. HANDLER, remandment —Justices
For reversal and O’HERN, GARIBALDI, STEIN COLEMAN —5.
Dissenting POLLOCK —1. —Justice
678 A.2d MILBURN, THE P. IN MATTER OF THOMAS AT AN ATTORNEY LAW.
July ORDER METUCHEN, P. who was admitted THOMAS MILBURN of 1978, having to the bar of this State in tendered his consent to Jersey, attorney of New disbarment as an at law State good appearing; cause by
It that THOMAS P. MILBURN is disbarred is ORDERED consent, immediately; further effective and it is respondent’s name stricken from the roll of
ORDERED enjoined attorneys permanently restrained and and that he be law; practicing from and it is further funds, any, currently existing any that all if New ORDERED MIL- Jersey financial institution maintained THOMAS P. BURN, 1:21-6, pursuant to Rule shall be restrained from dis- Court, application good except upon bursement to this for cause shown, be transferred the financial institution to the shall Superior deposit the funds Clerk of the Court who directed
