E3 Biofuels, LLC v. Biothane, LLC, successor in interest and liability to Biothane Corporation; Perennial Energy, Inc.
No. 14-1894
United States Court
March 25, 2015
GRUENDER, Circuit Judge.
Appeal from United States District Court for the District of Nebraska - Omaha. Submitted: November 13, 2014.
Before RILEY, Chief Judge, BEAM and GRUENDER, Circuit Judges.
GRUENDER, Circuit Judge.
I.
In 2005 one of E3‘s predecessors in interest began construction of an ethanol plant in Mead, Nebraska. The plant was to be powered, at least in part, by methane. To generate electricity from the gas, E3‘s predecessor contracted with Biothane for a boiler system. The Boiler Purchase Order explained that Biothane would supply two boilers and integrate them into the plant:
Biothane will supply, start-up, and warrant the boiler system and controls as well as manage and take responsibility for integration of the boiler into the biogas handling system for a lump sum price of $1,450,000. This lump sum price includes ... the design engineering services necessary to integrate the boiler into the overall biogas management system.
Biothane, an expert in systems integration but not in boilers specifically, subcontracted with PEI to install and integrate the boilers. Biothane retained overall responsibility. Both Biothane and PEI are engineering companies.
In February 2007, PEI engineer Ted Landers repeatedly tried and failed to light the main flame of one of the boilers. The repeated attempts caused gas to build up and eventually explode. E3 claims that the boiler never worked properly afterward and that the plant failed as a result.
The plant‘s owners eventually reorganized in bankruptcy. A company called AltEn, LLC ended up owning the plant, including the boiler. At the request of an appointed bankruptcy trustee, the bankruptcy court assigned the legal claims stemming from the explosion to E3.
In 2011—3 years and 364 days after the explosion—E3 sued Biothane and PEI, alleging various torts against both and breach of contract against Biothane. Rejecting a jurisdictional challenge by PEI, the district court first found that the parties were diverse. The court then granted summary judgment to Biothane and PEI. The court concluded that all of E3‘s claims were time-barred under
II.
On appeal, PEI again challenges the district court‘s subject-matter jurisdiction. E3 then argues that its suit was timely under any of five potentially applicable Nebraska statutes of limitations and that one of these statutes, not
A.
We review issues of subject-matter jurisdiction de novo. Slater v. Republic-Vanguard Ins. Co., 650 F.3d 1132, 1134 (8th Cir. 2011). Diversity jurisdiction “requires an amount in controversy greater than $75,000 and complete diversity of citizenship of the litigants.” OnePoint Solutions, LLC v. Borchert, 486 F.3d 342, 346 (8th Cir. 2007) (citing
For diversity purposes, E3, an LLC, is a citizen of Kansas and South Dakota; Biothane is a citizen of Delaware and Pennsylvania; and PEI is a citizen of Missouri. The amount in controversy is well over $75,000. Diversity jurisdiction is thus facially proper. See
PEI first argues that the citizenship of AltEn, the LLC that ended up owning the plant and the boiler, should be attributed to E3. PEI argues that AltEn and E3 are related because AltEn owns the property that is the subject of E3‘s claims and because E3, directly and indirectly, owns interests in AltEn. And PEI claims that AltEn, like PEI, is a citizen of Missouri. Thus, if AltEn‘s purported Missouri citizenship is attributable to E3, E3 and PEI are not diverse. But AltEn‘s citizenship is not attributable to E3 because E3‘s “citizenship is that of its members.” GMAC Commercial Credit LLC v. Dillard Dep‘t Stores, Inc., 357 F.3d 827, 829 (8th Cir. 2004). And E3‘s sole member is a citizen of Kansas and of South Dakota, not of Missouri. What AltEn owns and what E3 owns do not matter here. What matters is the citizenship of E3‘s member.
As its second point, PEI claims that E3 was assigned the right to sue from a related entity that, like PEI, was a citizen of Missouri. Such an assignment arguably suggests that E3 “improperly or collusively” invoked diversity jurisdiction.
B.
Satisfied with our jurisdiction, we turn to the merits of the grant of summary judgment to Biothane and PEI.
Before reviewing other statutes of limitations, we first conclude that the two-year statute of limitations for professional negligence,
The Nebraska Supreme Court has held repeatedly that engineers, including engineering companies, are professionals. Reinke Mfg. Co., Inc. v. Hayes, 590 N.W.2d 380, 388 (Neb. 1999); Lindsay Mfg. Co. v. Universal Sur. Co., 519 N.W.2d 530, 538 (Neb. 1994); Georgetowne, 430 N.W.2d at 38. Biothane and PEI are engineering companies. Accordingly, they are professionals. E3‘s only response to this syllogism is to argue that Biothane and PEI are not professionals because their personnel working on the ethanol plant were not licensed in Nebraska. The Nebraska Supreme Court, however, has never held that a Nebraska professional license is a prerequisite to professional status. Admittedly, it has suggested so in dicta. See Churchill, 830 N.W.2d at 58 (“A license strongly indicates that a person is a professional, but that is not the only prerequisite.“); Tylle v. Zoucha, 412 N.W.2d 438, 440 (Neb. 1987) (“[A] profession is far more than the mere possession of a license to ply one‘s trade.“). But the issue in those cases was whether licensure was sufficient for professional status, not whether it was necessary. We do not detect a rule in these peripheral dicta—especially not a rule that often would contradict the repeated and commonsense holding that engineers are professionals.
We next conclude that Biothane and PEI “provided professional services.” PEI, which actually attempted to integrate the boiler into the methane system, clearly provided engineering, and thus professional, services. Biothane, however, arguably did not. As E3 asserts, Biothane may have acted as a non-professional general contractor and, lacking experience installing boilers, subcontracted the actual engineering to PEI. We think, however, that E3‘s own pleading shows that Biothane provided professional services. See Knudsen v. United States, 254 F.3d 747, 752 (8th Cir. 2001) (“[F]actual statements in a party‘s pleadings are generally binding on that party unless the pleading is amended.“). Consistent with Biothane‘s expertise in systems integration, E3‘s complaint charged that Biothane, among other things, failed “to properly supervise and
Finally, we decide “whether the activity that caused [E3‘s] injuries was part of those professional services.” See Churchill, 830 N.W.2d at 56. E3 contends that in causing the explosion, Landers was merely lighting the boiler, not performing the engineering services of installation and integration. But whether Landers was lighting the boiler or installing it, he was still performing the professional services for which PEI was hired. In an analogous case, the Nebraska Supreme Court considered a patient‘s allegation that her doctor had hurt her by negligently adjusting his examination chair while she sat in it. Olsen v. Richards, 440 N.W.2d 463, 463-64 (Neb. 1989). The patient claimed that merely adjusting a headrest was “ordinary negligence,” not professional negligence governed by
Because Biothane and PEI were professionals that provided professional services to E3 and because Landers‘s activities that caused the explosion were part of those professional services,
C.
That, however, is not the end of our inquiry. In Nebraska, “where different statutes of limitations are equally applicable, the one allowing the longer period governs.” Georgetowne, 430 N.W.2d at 38-39. Accordingly, we must determine whether any other limitations period is “equally applicable” here. E3 proposes five alternatives: the five-year period for breach of contract,
None of these limitations periods are equally applicable. “Under Nebraska law, the two-year statute of limitations applies whenever a professional is sued for an action performed in a professional capacity.” Stumpf v. Albracht, 982 F.2d 275, 278 (8th Cir. 1992) (emphasis added). For example, in one Nebraska case, a plaintiff sued an engineering company for negligence
By alleging various theories of recovery, [the plaintiff] attempts to parse its claims in order to obtain the advantage of longer periods of limitation and avoid the statutory bar of
§ 25-222 . If all of [the plaintiff‘s] claims are based on a single professional relationship, however, they may not be separated into various parts to allow different periods of limitation to be applied. ... [W]e [have] explained that we do not believe that the Legislature in adopting the special statute of limitations for professional negligence, section 25-222, intended that the various aspects of the whole professional relationship should be separated. Therefore, if [the plaintiff‘s] claims are for professional malpractice, whether pled in tort or contract, the statute of limitations for professional negligence contained in§ 25-222 applies.
Id. at 387-88 (citations omitted) (internal quotation marks omitted). This rule is longstanding.3 As already discussed, E3‘s claims arise from alleged professional negligence. Accordingly, no other statute of limitations—none of E3‘s five alternatives—can be equally applicable.
We mention in particular one of E3‘s suggested statutes of limitations, the four-year statute for breach of a contract for the sale of goods. E3 plausibly argues that the Boiler Purchase Order was a contract for goods, not a contract for services. See Mennonite Deaconess Home & Hosp., Inc. v. Gates Eng‘g Co., Inc., 363 N.W.2d 155, 160-61 (Neb. 1985) (explaining that the primary purpose of a transaction determines whether it is a sale of goods). That argument, however, is ultimately irrelevant. The essence of the allegation against Biothane is not that Biothane failed to sell a boiler, but rather that Biothane failed to provide properly the engineering services of start-up and integration, or the supervision of those services. Regardless of whether this failure ultimately led to the breach of a contract, for goods or otherwise, E3 still sued Biothane “for an action performed in a professional capacity.” Stumpf, 982 F.2d at 278. Section 25-222 controls such suits.
We admit, however, that there is an arguable anomaly in Nebraska‘s case law. In Murphy v. Spelts-Schultz Lumber Co. of Grand Island, Spelts-Schultz designed, manufactured, and sold to Murphy custom roof trusses that eventually failed. Id. at 425. When Murphy sued based on negligence and breach of warranty, Spelts-Schultz responded that Murphy‘s suit was barred by the applicable statute of limitations, but it did not specify which statute that was. Id. The district court agreed and granted summary judgment for Spelts-Schultz, but it too did not explain which statute of limitations controlled. Id. The Nebraska Supreme Court
III.
E3 does not dispute that if
