E. M. MELAHN CONSTRUCTION COMPANY et al., Plaintiffs, v. THE VILLAGE OF CARPENTERSVILLE, Defendant-Appellant. - (E. M. MELAHN CONSTRUCTION COMPANY, Plaintiff-Appellee.)
Second District No. 80-152
Second District
Original opinion filed May 28, 1981.
Rehearing allowed July 27, 1981.
Original opinion adhered to October 30, 1981.
100 Ill. App. 3d 544
Richard W. Husted, of Elgin, for appellant.
Gary L. Griffin, Barry A. Spevack, and Cornelius Riordan, all of McNella & Griffin, Ltd., of Chicago, for appellee.
Mr. JUSTICE NASH delivered the opinion of the court:
Defendant, Village of Carpentersville, seeks to appeal from judgments entered following directed verdicts and jury verdicts in favor of plaintiff, E. M. Melahn Construction Co., on both plaintiff‘s complaint and defendant‘s counterclaim. Defendant has also appealed from an order awarding prejudgment interest to plaintiff. Plaintiff cross-appeals from an order denying it attorney‘s fees and other relief sought pursuant to section 41 of the Civil Practice Act (
This action was commenced by plaintiff to recover for services performed under a roadway and sewer installation contract it had entered into with defendant. The primary controversy between the parties centered upon plaintiff‘s claims for extra work it alleged it was required to perform and its claim for prejudgment interest pursuant to section 2 of the Interest Act (
Plaintiff has filed a motion in this court to dismiss defendant‘s appeal from the jury verdicts for its failure to file a post-trial motion, asserting that defendant may not seek review of issues not specified in such a motion. (
We note first that plaintiff filed a timely notice of cross-appeal from the order denying its claim for attorney‘s fees under section 41 of the Civil Practice Act but, as it has not argued that issue in its brief, we will not consider it further. See
Defendant failed to file any post-trial motion following the judgments entered December 7, 1979, which directed verdicts as to certain issues and entered judgment on the verdicts of the jury, nor did it file a post-trial motion following entry of the final judgment in this case on January 25, 1980. Claimed error generally will not be preserved for review unless it has been specifically raised in a post-trial motion pursuant to section 68.1(2) of the Civil Practice Act. (Wilson v. Clark (1981), 84 Ill. 2d 186,
A different question is presented where defendant seeks to appeal from the verdicts which were directed by the trial court and its award of prejudgment interest. A narrow exception excusing the failure to present a post-trial motion in a case tried before a jury is recognized where a verdict has been directed by a trial court and, also, where the order for which review is sought was entered following discharge of the jury. (See Robbins v. Professional Construction Co. (1978), 72 Ill. 2d 215, 223-25, 380 N.E.2d 786, 789-90; Keen v. Davis (1967), 38 Ill. 2d 280, 282, 230 N.E.2d 859, 861.) As to these issues we conclude defendant‘s failure to file a post-trial motion does not bar review.
Although not raised by plaintiff we must also consider the sufficiency of defendant‘s two notices of appeal to confer jurisdiction on this court to review the judgments for directed verdicts and the judgment entered on the verdict of the jury on December 7, 1979. Defendant filed a notice of appeal from these judgments on December 19; however, it was premature as the judgments were not final. Supreme Court Rule 304(a) provides that judgments determining fewer than all of the rights and claims in issue are not appealable unless the trial court finds “there is no just reason for delaying enforcement or appeal.” (
We must then consider whether defendant‘s January 25 notice of appeal was sufficient to permit this court to review the judgments entered on December 7. Supreme Court Rule 303(c)(2) provides that a notice of appeal “shall specify the judgment or part thereof appealed from and the relief sought from the reviewing court.” (
Generally, when an appeal is taken from a specified judgment only, a reviewing court does not acquire jurisdiction to review other judgments which have not been specified in the notice of appeal. (Illinois Central Gulf R.R. Co. v. Sankey Brothers, Inc. (1979), 78 Ill. 2d 56, 61, 398 N.E.2d 3, 5; see also Mooring v. Village of Glen Ellyn (1978), 57 Ill. App. 3d 329, 331, 373 N.E.2d 35, 36.) In Burtell v. First Charter Service Corp. (1979), 76 Ill. 2d 427, 394 N.E.2d 380, our supreme court noted that a notice of appeal is to be liberally construed and that appellate jurisdiction will be conferred,
“* * * if the notice, when considered as a whole, fairly and adequately sets out the judgment complained of and the relief sought so that the successful party is advised of the nature of the appeal. [Citations.] Unless the appellee is prejudiced thereby, the absence of strict technical compliance with the form of the notice is not fatal, and where the deficiency in the notice is one of form only, and not of substance, the appellate court is not deprived of jurisdiction. [Citations.]” (76 Ill. 2d 427, 433-34, 394 N.E.2d 380, 383.)
In Burtell appellant‘s notice of appeal stated it “‘appeals from the decree and judgment entered against it on June 1, 1976 in the sum of $89,998.22‘” and asked it be reversed. (76 Ill. 2d 427, 431.) It failed, however, to include mention of an earlier decree entered December 19, 1975, in the same cause which had found that a joint venture existed between the parties and ordered an accounting. The judgment finally entered and described in the notice of appeal was for the sums found due under the accounting. The supreme court held that the notice of appeal was sufficient to confer jurisdiction to also review the decree of December 19,
In the present case, however, defendant‘s January 25 notice of appeal is directed only to the judgment for prejudgment interest and requests only that it be reversed. The issue of whether plaintiff was entitled to prejudgment interest under section 2 of the Interest Act (
In summary of the jurisdictional quagmire presented in this case, we have determined that plaintiff‘s cross-appeal will not be considered as it was not argued; the judgments entered December 7, 1979, will not be reviewed as they are not within the scope of defendant‘s limited notice of appeal; the judgments entered December 7 on the verdicts of the jury will not be considered for the further reason defendant failed to present a post-trial motion to the trial court. The issues of the case as they relate to the judgment for prejudgment interest will be reviewed.
The trial court awarded plaintiff prejudgment interest on the sum of the judgments entered December 7, 1979, for the two-year period preceding that date. Defendant contends the court erred for these reasons: (1) defendant withheld payment for claimed extra work in good faith and without unreasonable and vexatious delay in making payment; (2) the fact the parties contract required judicial construction bars interest; (3) plaintiff failed to satisfy a contract requirement of acceptance of the work by defendant prior to payment becoming due, and (4) the amount of interest should be reduced as all of the work was not completed during the period for which interest was awarded.
Section 2 of the Interest Act (
“Creditors shall be allowed to receive at the rate of five (5) per centum per annum for all moneys after they become due on any bond, bill, promissory note, or other instrument of writing; on money lent or advanced for the use of another; on money due on the settlement of account from the day of liquidating accounts
between the parties and ascertaining the balance; on money received to the use of another and retained without the owner‘s knowledge; and on money withheld by an unreasonable and vexatious delay of payment.”
Defendant relies on Watson Lumber Co. v. Guennewig (1967), 79 Ill. App. 2d 377, 226 N.E.2d 270, in arguing it withheld payment in good faith, without unreasonable or vexatious delay. This court has rejected the Watson court‘s reasoning in two cases in which we held that the existence of a good-faith dispute and the unreasonableness of any delay in payment “only affects that portion of section 2 of the Interest Act which relates to ‘unreasonable or vexatious delay’ and that it has no applicability to cases involving instruments in writing * * *.” (KFK Corp. v. American Continental Homes, Inc. (1979), 71 Ill. App. 3d 304, 314, 389 N.E.2d 232, 239; Haas v. Cravatta (1979), 71 Ill. App. 3d 325, 332, 389 N.E.2d 226, 231.) A building or construction contract is an instrument in writing within the meaning of the interest statute. (Smith v. Gray (1925), 316 Ill. 488, 499, 147 N.E. 459, 464; see Keeler v. Herr (1895), 157 Ill. 57, 41 N.E. 750.) While the recovery by plaintiff was for extras outside the scope of the construction contract, the cost of each extra was agreed upon by plaintiff and an agent of the village (its engineers) prior to the commencement of each project. These agreements were reduced to writing in change orders submitted by plaintiff to defendant and approved by its agents. Defendant has not included in the record a report of proceedings of the hearing on prejudgment interest; we cannot determine whether the issue of whether defendant reasonably delayed payments was presented to the trial court. In the absence of a report of proceedings it will be assumed that the court heard adequate evidence to support a determination that defendant‘s delay in payment was unreasonable and vexatious (Levy v. Dickstein (1979), 70 Ill. App. 3d 180, 184, 388 N.E.2d 97, 100; Dils v. City of Chicago (1978), 62 Ill. App. 3d 474, 479, 378 N.E.2d 1130, 1134), even if such a finding was required to support an award of interest in this case. Defendant cannot therefore be heard to complain there was a good faith dispute excusing delay in payment.
Defendant again relies on Watson as authority in support of its second argument. The court there held it error “to allow interest on an amount due when, as here, that amount depends largely upon the construction placed on the terms of a contract, * * *.” (79 Ill. App. 2d 377, 398, 226 N.E.2d 270, 280.) This determination is in accord with the general rule that interest may be awarded only when the sum due is liquidated or subject to exact computation. (Central National Chicago Corp. v. Lumbermens Mutual Casualty Co. (1977), 45 Ill. App. 3d 401, 409, 359 N.E.2d 797, 802.) In the present case the trial court did construe the construction contract, but only to determine whether the village was liable for the
Defendant next contends that plaintiff‘s failure to satisfy a final inspection meant no sum ever became due for extras under the contract, especially the retained funds the release of which was expressly made subject to such final inspection and acceptance of the work by the village. We believe John Kubinski & Sons, Inc. v. Dockside Development Corp. dispels defendant‘s argument. The appellate court there noted under similar circumstances that an owner cannot rely on issuance of a final certificate of satisfaction as a condition precedent to the release of retained funds where it has itself been in breach of contract. The court recognized that a contrary interpretation would allow the unacceptable result that an owner could withhold the certificate, and thus the payment, regardless of any breach. The extras and retained funds were due plaintiff, and an award of interest for the period these liquidated sums were withheld was proper.
Defendant‘s final contention is that plaintiff should not have received interest from December 1977 to December 1979 as it had not completed its work by December 1977. Defendant points to plaintiff‘s opening statement in which it referred to unfinished work; however, this statement was made by plaintiff in terms of what it expected defendant would attempt to show was uncompleted work justifying a set-off. Plaintiff‘s general superintendent did testify at trial, however, that all construction was not completed until sometime after July 1978. Plaintiff notes evidence the roadway was opened for traffic in December 1977 and that the construction contract was substantially performed then. Even assuming the contract was substantially performed at that time, however, this does not mean the extras were also, and defendant maintains that plaintiff was still submitting pay estimates for extras for village approval as late as February 1979.
In cases where there are a number of dates from which interest could be said to have accrued, this court has sought to find the most equitable date. (Rite-Way Plumbing & Heating, Inc. v. Wil-Freds, Inc. (1978), 63 Ill. App. 3d 643, 649, 380 N.E.2d 992, 996.) The important date (where as here defendant has not specified an alternate date) is when the money actually became due without regard to whether or when plaintiff made a demand for payment. (Haas v. Cravatta (1979), 71 Ill. App. 3d 325, 332, 389
For these reasons the judgment of the circuit court of Kane County will be affirmed.
Affirmed.
SEIDENFELD, P. J., concurs.
Mr. JUSTICE LINDBERG, specially concurring:
I specially concur in the affirmance of our earlier decision upon the granting of the defendant‘s motion for rehearing. Upon reconsideration of our holding that the judgments on the December 7, 1979, directed verdicts were not properly preserved, I now conclude that they were preserved and should have been disposed of on their merits in our opinion. However, in my original consideration of those issues I concluded, and remain convinced, that the judgments on the directed verdicts should be affirmed on their merits.
While appeal of the judgment on the jury verdict was clearly waived for the reason set forth in the opinion, I now believe the judgments on the directed verdicts were preserved under the supreme court‘s instructive decision in Burtell v. First Charter Service Corp. (1979), 76 Ill. 2d 427, 394 N.E.2d 380, also relied upon in the majority opinion.
I think we should be guided in the instant cause by the holdings of the court in Burtell that the appeal from a subsequent final judgment draws in question all prior nonfinal orders and rulings which produced the judgment; the notice of appeal serves the purpose of informing the prevailing party in the trial court that the unsuccessful litigant seeks review by a higher court; briefs, and not the notice of appeal itself, specify the precise points to be relied upon for reversal; a notice of appeal will confer jurisdiction on an appellate court if the notice, when considered
I respect the conclusion that the issue of the plaintiff‘s entitlement to prejudgment interest is only indirectly dependent upon the earlier judgments and the failure to include those judgments in the second, valid notice of appeal was of substance and not merely a form. However, I think we should read Burtell more broadly, particularly under a procedural fact situation where only through punctilious judicial research prior to oral argument was the questionable appellate jurisdiction discovered by this court. The appellee proceeded to the day of argument without awareness of this potential defect and therefore was not misled and, in fact, provided the court with a complete and vigorous argument on the merits of each of the issues embraced by both notices of appeal. I do not see how the prejudgment interest was any less substantive in its relationship to the earlier judgment than was the issue of the accounting as to its underlying judgments in Burtell.
Nevertheless, having considered the merits of the defendant‘s arguments attacking the December 7 directed verdict I would affirm the judgment of the trial court on those issues. Therefore, I specially concur in the original opinion of the court upon the granting of the petition for rehearing.
