E-L ENTERPRISES, INC., Plaintiff-Respondent, v. MILWAUKEE METROPOLITAN SEWERAGE DISTRICT, Defendant-Appellant-Petitioner.
No. 2008AP921
Supreme Court of Wisconsin
Decided July 2, 2010
2010 WI 58 | 326 Wis. 2d 82 | 785 N.W.2d 409
Oral argument October 21, 2009.
For the plaintiff-respondent there were briefs by Jerome R. Kerkman, Susan A. Cerbins, Joseph R. Cincotta, and Kerkman & Dunn, Milwaukee, and oral argument by Jerome R. Kerkman.
An amicus curiae brief was filed by Daniel M. Olson and the League of Wisconsin Municipalities, Madison, on behalf of the League of Wisconsin Municipalities.
¶ 2. The Sewerage District filed a motion for judgment notwithstanding the verdict on the grounds that the damages E-L suffered to its property were consequential damages resulting from governmental action and therefore were not compensable under the takings clause of the
¶ 3. The Sewerage District appealed, and the court of appeals affirmed. The Sewerage District petitioned this court for review, and we accepted. We now reverse the decision of the court of appeals.
¶ 4. This case presents the following issues: (1) whether the Sewerage District‘s conduct constituted a taking of E-L‘s property without just compensation in violation of
¶ 5. As a preliminary matter, we need not decide today the panoply of issues that relate to an alleged
I. FACTUAL BACKGROUND AND PROCEDURAL POSTURE
¶ 6. In the 1980s, the Sewerage District constructed the Deep Tunnel System, a 19 mile long system of sewers across Milwaukee County “that help[s] reduce water pollution by storing excess wastewater 140 to 330 feet underground” until the wastewater can be treated at reclamation facilities.7 The Deep Tunnel included the 1987-88 construction of the Crosstown 7 sewer (the sewer), a “near-surface collector sewer” that collects sewage overflow and diverts it away from the Menomonee River and into storage in the Deep Tunnel. The sewer was constructed for the Sewerage District by Bowles Contracting Inc./Tomasini Construction Inc. Joint Venture (BCI/TCI). Pursuant to the Sewerage District‘s contract with BCI/TCI, the means and methods of the construction were left to BCI/TCI‘s discretion. The contract required BCI/TCI to avoid damage to neighboring buildings and to repair any damage caused by the removal of water from the construction site. Under the contract, BCI/TCI was responsible for any resulting damage to surrounding properties.
¶ 7. To construct the sewer, BCI/TCI dug a trench, installed sewer pipes, and restored the surface. A portion of the sewer was constructed in the Sewerage District‘s easement under a private alley adjacent to the subject building owned by E-L on North 12th Street in Milwaukee.8 E-L‘s building was built in 1928 on “wood piles,”
¶ 8. However, in order for BCI/TCI to properly lay the sewer pipe and pour concrete, the trench had to be dry. Accordingly, BCI/TCI pumped groundwater from the trench for 17 days. When the sewer was completed in 1988, groundwater measurements showed that the level of groundwater near E-L‘s building had been significantly reduced. It took two years for the groundwater level to recover.
¶ 9. In 1998, about ten years after the sewer project was completed, E-L‘s owner, Joseph Loftus, noticed that cracks in the foundation of his building appeared to be worsening, so he started to monitor the building‘s settlement rate. In 2001, an engineer examined the building‘s wood piles and determined that the caps of 14 wood piles had rotted and were no longer able to support the building. Those particular wood piles were under the south wall of E-L‘s building, nearest to the 1987-88 sewer construction site. In September 2003, E-L notified the Sewerage District of the building damage, and in October, E-L repaired the building. To repair the building, the damaged portions of the wood piles were sawed off and replaced with concrete. The repairs cost a total of $309,388, which includes E-L‘s attorney fees incurred in litigation with a neighbor who owned the adjacent alley and refused E-L access to make the building repairs. It is undisputed that E-L continued to lease the building throughout this entire period.
¶ 10. On June 23, 2004, E-L filed suit against the Sewerage District and CNA Insurance Companies (CNA), the insurer for the now defunct BCI/TCI. E-L
¶ 11. As to the inverse condemnation claim, E-L‘s complaint alleged that the Sewerage District‘s operation and maintenance of the Deep Tunnel System and the pipes constructed as a part of the sewer “physically took portions of the wood piles which rendered them unusable and damaged the E-L Building.” E-L alleged that the Sewerage District‘s acts constituted a taking:
[The Sewerage District‘s] conduct constitutes a taking of E-L Enterprises’ property for public use.
Specifically, [the Sewerage District‘s] conduct constitutes a physical invasion that deprived and continues to deprive E-L Enterprises of all beneficial use of the wood piles in violation [of] the Fifth Amendment of the United States Constitution andArticle I, Section 13 of the Wisconsin Constitution .. . . .
[The Sewerage District] took E-L Enterprises’ property without paying E-L Enterprises its just compensation.
In addition to damages, E-L‘s complaint demanded attorney fees and costs relating to E-L‘s claim for inverse condemnation.12
¶ 12. E-L‘s takings claim under
taking, the jury was required to answer whether the removal of groundwater from E-L‘s property caused E-L‘s building to settle. If the jury answered that question in the affirmative, the jury had to determine the sum of money that would “justly compensate E-L for the taking of the groundwater beneath the south end of [E-L‘s] building.”
¶ 14. In its November 7, 2007 order, the circuit court denied the Sewerage District‘s motion for judgment notwithstanding the verdict or, in the alternative, a new trial and granted E-L‘s request for attorney fees and costs under
¶ 15. The Sewerage District appealed, and the court of appeals affirmed, concluding that the jury verdict supported E-L‘s inverse condemnation claim under
¶ 17. In concluding that the Sewerage District‘s conduct constituted an “occupation” under
¶ 19. We now reverse the decision of the court of appeals.
II. STANDARD OF REVIEW
¶ 20. Whether government conduct constitutes a taking of private property without just compensation is a question of law that this court reviews de novo. R.W. Docks & Slips v. State, 2001 WI 73, ¶ 13, 244 Wis. 2d 497, 628 N.W.2d 781; Howell Plaza, Inc. v. State Highway Comm‘n, 92 Wis. 2d 74, 80, 284 N.W.2d 887 (1979) (hereinafter Howell Plaza II). In addition, whether an inverse condemnation claim has been established under
III. ANALYSIS
A. Takings Claim
¶ 21.
¶ 22. Under the
¶ 23. In this case, E-L does not claim that the Sewerage District‘s conduct constituted a regulatory
¶ 24. E-L‘s takings claim must fail. E-L‘s claim morphed from a complaint that the Sewerage District “physically took portions of the wood piles which rendered them unusable and damaged the E-L Building” into a special verdict form that asked the jury to determine the sum of money that would “justly compensate E-L for the taking of [the] groundwater.” The groundwater was indeed that which was extracted by the Sewerage District, but E-L introduced no proof as to the value of the extracted groundwater. Therefore, whether E-L owns the extracted groundwater is inapposite in this case.16 E-L instead seeks damages for the cost to repair its building and for the loss of use of its wood piles. However, the Sewerage District did not physically occupy the property for which E-L seeks compensation, and no government-imposed restriction deprived E-L of all, or substantially all, of the beneficial use of its property. What remains are mere consequential damages to property resulting from governmental action, which are not compensable under
1. Whether E-L owns the extracted groundwater is inapposite in this case.
¶ 25. To determine whether a taking occurred, E-L argues that “the first question that must be addressed is whether property owners have a property right in groundwater.” As E-L correctly points out, there can be no takings claim if that which the Sewerage District allegedly took is not E-L‘s property. However, E-L introduced no proof as to the value of the extracted groundwater. Instead, E-L seeks damages that flow from the allegation that when the Sewerage District pumped groundwater from the trench, the groundwater level beneath E-L‘s building was lowered, causing the wood piles to dry out and the building to settle. E-L‘s opening and closing arguments at trial make clear that instead of seeking damages for the value of the extracted groundwater, E-L seeks damages for the cost to repair the wood piles and E-L‘s building.
¶ 26. In its opening argument, E-L claimed that the Sewerage District took E-L‘s groundwater but consistently spoke of damage to E-L‘s wood piles and building:
[The Sewerage District] knew that its partial taking of the property, taking of groundwater would result in a lower value of E-L‘s building. You take the groundwater, the piles rot, your building sinks, your building is not worth what it was.
. . . .
As a result of [the Sewerage District] taking groundwater, E-L‘s property lost value, the entire property. We believe the value of the building lost the value equal to the amount of the repairs that had to be done.
If I‘m going to sell a house and you think it‘s worth $400,000, and I know the roof needs to be repaired for
$30,000, somebody buying that is going to say, no, it‘s not $400,000, it‘s worth 370. They‘re going to take out the value. And that‘s what E-L contends is the amount taken. The loss in the value of their property. And the amount that we‘re seeking on that is just the amount E-L paid out of pocket.
. . . .
Everything we show you at trial is for you to see why E-L should be compensated for the taking of the groundwater by [the Sewerage District]. And how much money will equal the value of the groundwater taken by [the Sewerage District] and the harm caused to E-L from the damage to its piles.
¶ 27. Similarly, in its closing argument, E-L reiterated to the jury that E-L was seeking damages for the cost to repair its building:
The next question [on the special verdict form] asks what amount should E-L be paid for its just compensation. And here‘s where we‘re going on this.
. . . .
The reduction in the fair market value was what were the repairs that had to be done on this place.
And the repairs that had to be done are summarized in Exhibit 5117 for you. There‘s multiple exhibits that have all the invoices, but if you look at Exhibit 51, you‘re going to find a summary.
... The number we‘re asking for when you add up all the number [sic] for the 2003 work, the 2004 work, and the attorney fees, we had to fight, you know, we had an easement that was a very standard easement.18 We had an [sic] to get permission to go underneath and dig under that building....
....
So, ladies and gentlemen, when you add to the 2,300 from Dahlman, the 2003 expenses, the 2004, and legal fees, the number I come to is 309,388, and that‘s what I‘m going to ask that you find as compensation for the amount of the taking.
¶ 28. It is clear from E-L‘s opening and closing arguments that instead of seeking damages for the value of the extracted groundwater, E-L seeks damages for the cost to repair the wood piles and E-L‘s building.
¶ 29. Because E-L introduced no proof as to the value of the extracted groundwater, the court of appeals’ reliance on Dahlman is misplaced.19 It is true, as noted
We reject E-L‘s and the circuit court‘s characterization of Dahlman and Price. In Dahlman, this court concluded that because a property owner, as against the city, is entitled to the lateral support of the soil underlying the owner‘s property, there was a taking of the soil when the city removed the lateral support in the course of street grading. 131 Wis. at 439-40. Our conclusion that the city‘s actions constituted a taking hinged on the property owner‘s right to the lateral support of the soil, id., not on the foreseeability of the property loss. Likewise, in Price, this court held that the plaintiff established a claim under the then-existing inverse condemnation statute when the construction and maintenance of dams across the Menominee River caused the river to overflow onto the plaintiff‘s land, moistening the soil to the point of destroying the land‘s agricultural value. 197 Wis. at 26, 28. In that case, our conclusion that the plaintiff stated a takings claim centered on the plaintiff‘s allegation that the flood waters physically invaded the plaintiff‘s property and entirely destroyed its value, id.; again, the foreseeability of the property loss played no part in the analysis.
2. Mere consequential damage to property resulting from governmental action is not a taking thereof.
¶ 30. Both the United States Supreme Court and this court have consistently recognized that “government action outside the owner‘s property that causes consequential damages within” does not constitute a taking. Loretto v. Teleprompter Manhattan CATV Corp., against the Sewerage District on the basis of governmental immunity. As we previously noted, supra note 10, E-L did not appeal the dismissal of those tort claims.
Despite the dismissal of E-L‘s negligence and nuisance claims against the Sewerage District, the jury was nevertheless asked to determine if the Sewerage District‘s removal of groundwater from E-L‘s property was “unreasonable.” As we have just explained, the withdrawal of groundwater in a manner that causes unreasonable harm to another‘s property may give rise to a tort claim. Because the circuit court dismissed the tort claims against the Sewerage District, the jury should not have been asked to evaluate the reasonableness of the groundwater removal.
Likewise, the jury was erroneously asked to determine whether the Sewerage District‘s removal of groundwater from E-L‘s property was a taking. Whether government conduct constitutes a taking of private property without just compensation is a question of law. R.W. Docks & Slips v. State, 2001 WI 73, ¶ 13, 244 Wis. 2d 497, 628 N.W.2d 781. While a jury may properly be asked to determine questions of fact pertinent to a takings claim, e.g., the amount of damages that will justly compensate a property owner for a taking, see Stelpflug v. Town Bd., Town of Waukesha, Cnty. of Waukesha, 2000 WI 81, ¶ 26, 236 Wis. 2d 275, 612 N.W.2d 700, the ultimate determination of whether government conduct constitutes a taking is a question of law that is not properly placed before a jury.
In this case, the special verdict form, which questioned the jury as to reasonableness and causation, was framed in terms of a negligence claim rather than a takings claim.
¶ 31. In Wisconsin Power & Light, this court recognized that under the
¶ 32. Like E-L‘s damaged building and wood piles in this case, the damaged tower “was not taken for public use in the usual sense of those words.” Id. at 4. Just as E-L‘s building and wood piles were not used in connection with the sewer installation, the tower in Wisconsin Power & Light was not used in connection with the county‘s highway project. Id. Rather, the tower “was merely damaged by accident” as a result of the highway project. Id. Because the issue was one of “only damage, without appropriation to the public purpose,” id. at 6, this court concluded that the utility company was unable to recover its damages on the theory of a constitutional taking for public use, id. at 7.22
10. Wisconsin Power & Light.” E-L Enters., 316 Wis. 2d 280, ¶ 10. The court of appeals first reasoned that “unlike the situation in Wisconsin Power & Light, the Sewerage District had ‘reason to anticipate that damage would result from its acts.’ ” Id. Specifically, evidence “indicated that the Sewerage District was aware of a potential groundwater problem in connection with buildings near the project and, indeed, had directed its contractor to be careful to avoid damage to those buildings as the result of ‘removal or disturbance of groundwater....‘” Id. The court of appeals further reasoned that “unlike the situation in Wisconsin Power & Light, where ‘the public obtained no benefit from injuring’ the tower,... draining the groundwater facilitated the Sewerage District‘s construction” and therefore had utility to the sewer project. Id.
The court of appeals’ reasoning is flawed in two respects. First, the fact that this court recognized in Wisconsin Power & Light that “the county had no reason to anticipate that damage would result from its acts,” 3 Wis. 2d at 7, does not establish that foreseeability of damages supports a takings claim. To the contrary, we expressly declined to place significance on any of the Wisconsin Power & Light facts standing alone. Id. Rather, we concluded that the facts “collectively” negated a taking in the constitutional sense. Id. Second, the court of appeals’ distinction between this case and Wisconsin Power & Light presupposes that E-L is seeking damages for the extracted groundwater. As we pointed out previously, E-L is seeking damages for the cost to repair its building and the loss of use of its wood piles. Accordingly, the issue here is not whether the public obtained a benefit from the draining of the groundwater but instead whether the public obtained a benefit from the damaged wood piles. The public did not.
¶ 34. The court of appeals relied upon our decision in Damkoehler for authority that the Sewerage District‘s diversion of groundwater that supported the structural integrity of E-L‘s building constituted a compensable taking, as opposed to mere consequential damage to property for which there is no remedy. See E-L Enters., 316 Wis. 2d 280, ¶¶ 9, 11. In Damkoehler, this court recognized that a landowner has the right to have her property protected against an excavation that causes her property to subside. 124 Wis. at 151. In that case, for purposes of improving the highway, the city of Milwaukee excavated a street adjacent to the plaintiff‘s property and caused “a considerable part of her land to subside and fall into the street.” Id. at 150. We held that the city‘s actions, in removing the lateral support of the soil of the plaintiff‘s property, amounted to a compensable taking.
[T]he court [in Alexander] expressly declare[d] that it [did] not wish “to be understood as asserting the doctrine that there must be an actual taking or appropriation of the property itself in order to entitle the owner to compensation for damages done him. The city might so build a bridge, or open a street, or excavate a canal along or upon a lot, only appropriating a small amount of it, or perhaps none of the land itself, and yet entirely destroy the value of the property for all purposes.” The instant case, in its facts, comes within the exception so distinguished by the court, and cannot be held to be ruled by the decision of that case.
Id. (quoting Alexander, 16 Wis. at 253) (emphasis added). Accordingly, in Damkoehler, the city‘s actions amounted to a compensable taking because the city, by removing the lateral support of the soil of the plaintiff‘s property, caused a substantial part of the plaintiff‘s land to subside and fall and ” ‘entirely destroy[ed] the value of the property for all purposes.’ ” Id. at 150 (quoting Alexander, 16 Wis. at 253).
¶ 35. The distinction between Damkoehler and this case is significant. In this case, E-L does not claim that by diverting the groundwater beneath E-L‘s building and thereby reducing the building‘s structural integrity, the Sewerage District deprived E-L of all, or
B. Inverse Condemnation Claim
¶ 36.
If any property has been occupied by a person possessing the power of condemnation and if the person has not exercised the power, the owner, to institute condemnation proceedings, shall present a verified petition to the circuit judge of the county wherein the land is situated asking that such proceedings be commenced.... The court shall make a finding of whether
the defendant is occupying property of the plaintiff without having the right to do so. If the court determines that the defendant is occupying such property of the plaintiff without having the right to do so, it shall treat the matter in accordance with the provisions of this subchapter... assuming the plaintiff is not questioning the right of the defendant to condemn the property so occupied.
.. (Emphasis added.) By its terms,
¶ 37. To state a cause of action under
¶ 38. Still, when a property owner alleges a constitutional taking, the remedy provided by
¶ 39. In this case, E-L has failed to establish an inverse condemnation claim under
IV. CONCLUSION
¶ 41. In summary, we need not decide today the panoply of issues that relate to an alleged taking of groundwater. In this case, E-L introduced no proof as to sation for the acquisition of that strip of her property. Id. However, according to the plaintiff‘s petition, in connection with the construction of the retaining wall, the DOT caused structural damage to her residence, rendering her property valueless. Id., ¶ 4. As the court of appeals recognized, ” ‘Land may be taken for public purposes, within the meaning of the constitutional provision, without actual occupancy or seizure by the taker.’ ” Id., ¶ 12 (citing Wis. Power & Light, 3 Wis. 2d at 4; Eberle v. Dane Cnty. Bd. of Adjustment, 227 Wis. 2d 609, 621, 595 N.W.2d 730 (1999)). The court of appeals rejected the DOT‘s argument that the plaintiff‘s petition was insufficient because it failed to establish either that the government occupied the alleged damaged property or that the property was valueless. Wikel, 247 Wis. 2d 626, ¶ 11. The plaintiff was “entitled to the opportunity to prove her allegation that the [DOT‘s] actions rendered her property ‘uninhabitable and unsaleable’ and therefore, constituted a ‘total, permanent taking.’ ” Id., ¶ 17. Wikel is readily distinguishable from this case. In Wikel, the plaintiff claimed that the DOT‘s construction of the retaining wall rendered her property “uninhabitable and unsaleable” and therefore constituted a “total, permanent taking.” Id., ¶ 4. As discussed supra Part III.A.2, in this case, E-L does not claim that the Sewerage District‘s diversion of groundwater beneath E-L‘s building, which reduced the building‘s structural integrity, rendered E-L‘s building valueless. E-L cannot so claim because it is undisputed that E-L continued to lease the building throughout this entire period.
By the Court.—The decision of the court of appeals is reversed.
¶ 42. ANN WALSH BRADLEY, J. (concurring). I agree with the majority that mere consequential damage to property resulting from government action is not a taking. Majority op., ¶ 24. I also agree with the majority that the essence of this case sounds in tort. Id., ¶ 5. Given the circuit court‘s conclusion that the District is immune from tort liability, I conclude that the District is not liable for these damages to E-L‘s property.
¶ 43. Over three decades ago, this court established that a property owner‘s remedy for unreasonable interference with its use of groundwater sounds in tort. State v. Michels Pipeline Constr., Inc., 63 Wis. 2d 278, 217 N.W.2d 339 (1974). The Michels Pipeline court adopted the portion of the then-existing draft of the Restatement
A possessor of land or his grantee who withdraws ground water from the land and uses it for a beneficial purpose is not subject to liability for interference with the use of water by another, unless
(a) The withdrawal of water causes unreasonable harm through lowering the water table or reducing artesian pressure....
Restatement (Second) Torts, Tentative Draft No. 17, April 26, 1971, § 858A.1
¶ 44. Under the circumstances presented here, the withdrawal of groundwater may have caused unreasonable harm to E-L. But the remedy for this wrong sounds not in takings, but in tort.2
¶ 45. Indeed, as this case was presented to the jury, E-L‘s “takings” claim strongly resembled a tort claim. E-L argued that the District should have foreseen the harm and could have taken measures to avoid it. Additionally, E-L sought as damages the amount of money that it lost in rent and the amount of money that it paid out of pocket to repair the building.3
The burden is on E-L to satisfy you by the greater weight of the credible evidence, to a reasonable certainty, that the District‘s use of E-L‘s groundwater was unreasonable. In determining whether the District‘s use of E-L‘s groundwater was unreasonable, you should consider the District‘s need for the groundwater, E-L‘s need for the groundwater, the cost to E-L, if any, of the District‘s use of the groundwater, the cost to the District, if any, of not using the groundwater or of replacing the groundwater and whether the District‘s purposes for using E-L‘s groundwater could have been achieved through other means.
The reasonableness or unreasonableness of the District‘s actions is not a takings question—it is a tort question.
¶ 47. The circuit court determined that the District is immune from tort liability. E-L‘s attempt to dress up its tort claim in takings clothes to circumvent the District‘s immunity is unavailing. Accordingly, I respectfully concur.
roughly $309,000 is what it‘s cost E-L, plus loss of rent, what it‘s cost E-L because of the removal of the groundwater outside the trench by the District.” When there has been a partial taking, compensation is typically measured as either (1) the fair market value of the portion of the property that was taken; or (2) “severance damages,” measured as the difference between the fair market value of the property before the taking and the fair market value of the remaining parcel after the taking. Russell M. Ware, The Law of Damages in Wisconsin § 19.12 (5th ed. 2010); Arents v. ANR Pipeline Co., 2005 WI App 61, ¶ 14, 281 Wis. 2d 173, 696 N.W.2d 194.
¶ 49. Put in context, this ruling not only overturns a reasonable jury verdict but also deprives E-L of any meaningful remedy for its injury. This case, then, is important beyond the specific issues decided. It exposes the chasm between government wrongdoing and citizen redress. For the reasons stated below, I respectfully dissent.
I
¶ 50. In the 1980s, MMSD undertook construction of deep tunnels to hold sewage until it can be treated, thereby reducing water pollution. As part of this project, MMSD constructed the Cross Town 7 Collector System (CT-7) tunnel, which was located next to E-L‘s property. Before construction, MMSD detected the presence of groundwater in the vicinity. To construct the tunnel, project managers deemed it necessary to remove groundwater from the trench that would house the tunnel.
¶ 51. In the process of removing groundwater from the soil around the tunnel, MMSD also removed groundwater from E-L‘s property. The loss of groundwater caused 14 wood piles that were supporting E-L‘s building to rot. The jury determined that $309,388 was just compensation for E-L‘s costs to repair the piles.
¶ 53. E-L did not enumerate five causes of action to increase its damages. E-L pled five causes of action because it was confronted with the challenge of grounding its claim for recovery in traditional legal theory. Because the facts of the case were unusual, the appropriate theory for the case was uncertain.
¶ 54. In its complaint, E-L presented its inverse condemnation claim as follows:
51. MMSD‘s operation and maintenance of the Deep Tunnel and the 48 inch sewer pipes which were constructed as a part of the Cross Town 7 Collector System physically took portions of the wood piles which rendered them unusable and damaged the E-L Building.
52. MMSD‘s conduct constitutes a taking of E-L Enterprises’ property for public use. Specifically, MMSD‘s conduct constitutes a physical invasion that
deprived and continues to deprive E-L Enterprises of all beneficial use of the wood piles in violation of the
Fifth Amendment of the United States Constitution andArticle I, Section 13 of the Wisconsin Constitution .
(Emphasis added.)
¶ 55. By the time the case went to the jury, E-L had shifted the theory of its takings claim: MMSD did not “take” E-L‘s wood piles; MMSD “took” E-L‘s groundwater, thereby causing damage. The jury ultimately answered “yes” to the verdict question: “Was the District‘s removal of groundwater from E-L‘s property a taking?”
II
¶ 56. E-L also claimed negligence and nuisance. Both of these claims were dismissed by the circuit court. Initially, in March of 2006, the circuit court refused to dismiss these claims on grounds of governmental immunity. At the summary judgment stage, MMSD argued that its acts were “discretionary,” not “ministerial,” and therefore it was immune from liability. E-L, on the other hand, pointed to DNR-approved and -mandated groundwater depletion specifications, which prohibited MMSD and its contractors from lowering groundwater below existing levels.
¶ 57. Based on E-L‘s argument, the circuit court initially concluded that “the act for which E-L seeks to hold MMSD liable—exceeding the groundwater depletion limitation—constitutes a transgression in which MMSD had no discretion to engage.” Relying on Lister v. Board of Regents of the University of Wisconsin System, 72 Wis. 2d 282, 301, 240 N.W.2d 610 (1976), the court concluded that “nothing remain[ed] for judgment or discretion.” The court, therefore, denied MMSD‘s summary judgment motion.
¶ 59. Query: Isn‘t the natural remedy for the wrong in this case to be found in the law of negligence? Not if the court persists in unreasonably broad notions of governmental immunity and unreasonably narrow exceptions for tort recovery.2 In any event, because the jury awarded E-L damages under a different legal theory from negligence, questions about governmental immunity were not raised in the petition for review, and the case before us involves only questions pertaining to the inverse condemnation claim.
III
¶ 60. In the absence of an adequate remedy in tort law, the only remedy available to E-L comes from the
¶ 61. In Luber v. Milwaukee County, 47 Wis. 2d 271, 276, 177 N.W.2d 380 (1970), this court rejected the argument that consequential damages arising from a taking were “to be suffered in legal silence.” The court noted that the rule against consequential damages in eminent-domain cases had been attacked on the grounds that the rule ignores the “economic implications of the situation.” Id. at 279 (quoting Frank A. Aloi & Arthur Abba Goldberg, A Reexamination of Value, Good Will, and Business Losses in Eminent Domain, 53 Cornell L. Rev. 604, 631 (1968)). The court held:
The importance of allowing recovery for incidental losses has increased significantly since condemnation powers were initially exercised in this country. During the early use of such power, land was usually undeveloped and takings seldom created incidental losses. Thus the former interpretation of the ‘just compensation’ provision of our constitution seldom resulted in the infliction of incidental losses. The rule allowing fair market value for only the physical property actually taken created no great hardship. In modern society, however, condemnation proceedings are necessitated
by numerous needs of society and are initiated by numerous authorized bodies. Due to the fact people are often congregated in given areas and that we have reached a state wherein re-development is necessary, commercial and industrial property is often taken in condemnation proceedings. When such property is taken, incidental damages are very apt to occur and in some cases exceed the fair market value of the actual physical property taken.
¶ 62. In this case, although E-L seeks recovery for damages beyond the value of the groundwater, it does not go so far as to seek the kinds of consequential damages sought in Luber. Luber dealt with consequential damages beyond the reduction in “fair market value” of the property—the landowner sought lost rent. In this case, however, the jury awarded E-L the reduction in fair market value of its property. The circuit court instructed the jury:
If the government takes private property for a public use, the government must pay the owner the fair market value of the property that is taken. If only part of an owner‘s property is taken, and if taking part of the property reduces the value of the property that remains, the government must pay the difference between the fair market value of the property before the taking and the fair market value of the property after the taking.
¶ 63. Based on this instruction, the jury determined that E-L should be compensated in the amount of $309,388. Even though E-L presented this evidence in terms of the cost to repair the piles, the cost of these repairs amounted to the reduction in value to E-L‘s property that resulted from MMSD‘s taking. The majority now reverses the decision of a properly in-
¶ 64. This point is further emphasized by E-L‘s initial claim that the “taking” was the taking of “portions of the wood piles” supporting the building. Whether MMSD “took” the wood piles or “took” the groundwater, the result was the same: MMSD took a portion of E-L‘s property, causing a reduction in fair market value to the remainder of that property.
¶ 65. Two early Wisconsin cases support the conclusion that damages are available in the circumstances here. In Damkoehler v. City of Milwaukee, 124 Wis. 144, 145, 151, 101 N.W. 706 (1904), the city removed the lateral support for a building when grading an adjacent street, causing portions of the lot “to subside and slide into the excavated street.” The court rejected the argument that the damages caused by the excavation of highways were “purely consequential,” and permitted recovery under the Takings Clause. Id. at 152. The same situation arose in Dahlman v. City of Milwaukee, 131 Wis. 427, 439-440, 111 N.W. 675 (1907), and the court adopted the holding in Damkoehler for the proposition that “where a substantial part of the adjoining owner‘s land falls into the street by reason of the removal of its lateral support in the course of grading, there was a taking of the soil for public purposes and not a mere consequential damage.” Id.
¶ 66. In upholding the jury verdict in the present case, the court of appeals correctly saw “no logical basis to distinguish between the removal of soil providing lateral support and the diversion of groundwater performing essentially the same function—that is, supporting the structural integrity of a building like that owned by E-L Enterprises.” E-L Enters., Inc. v. Milwaukee Metro. Sewerage Dist., 2009 WI App 15, ¶ 11, 316
¶ 67. The majority distinguishes Damkoehler on grounds that the landowner lost the entire value of the property. The court in Damkoehler, however, did not limit its holding in that way. It required that the city, in grading a street, “cause no unnecessary damage to an adjoining landowner,” and asserted that the city‘s actions resulted in a taking “to the extent of such injury.” Damkoehler, 124 Wis. at 150-51 (emphasis added).
¶ 68. Furthermore, the court in Dahlman held that a takings claim could be maintained “where a substantial part” of the property fell into the street. Dahlman, 131 Wis. at 440-41. In Dahlman, the jury found that the loss of soil “caused no depreciation in the value of the premises.” Id. at 439. Yet the court permitted the landowner to recover nominal damages against the city. Id. at 440. This case is legally indistinguishable from Dahlman, save that the jury here determined that the fair market value of E-L‘s property was reduced by $309,388.
¶ 69. The Damkoehler case has been cited in other jurisdictions, including South Carolina. In White v. Southern Railway Co., 140 S.E. 560, 564 (1927), the South Carolina court wrote:
The word “taken” in the constitutional provision cited is not limited in its meaning and application to cases in
which there is an actual physical seizure and holding of property, but is broad enough to include cases in which the access to abutting premises is obstructed by the change of grade of a highway or there is such physical injury to property as results in destruction or substantial impairment of its usefulness. See 20 C.J. 697, and the following cases therein cited: Nevins v. Peoria, 41 Ill. 502, 89 Am. Dec. 392; Tinker v. Rockford, 36 Ill. App. 460; Hendershott v. Ottumwa, 46 Iowa 658, 26 Am. Rep. 182; Offutt v. Montgomery County, 94 Md. 115, 50 A. 419; Vanderlip v. Grand Rapids, 73 Mich. 522, 41 N.W. 677, 3 L.R.A. 247, 16 Am. St. Rep. 597; Broadwell v. Kansas, 75 Mo. 213, 42 Am. Rep. 406; Mosier v. Oregon Nav. Co., 39 Or. 256, 64 P. 453, 87 Am. St. Rep. 652; Stearns v. Richmond, 88 Va. 992, 14 S.E. 847, 29 Am. St. Rep. 758; Kincaid v. Seattle, 74 Wash. 617, 134 P. 504, 135 P. 820; Damkoehler v. Milwaukee, 124 Wis. 144, 101 N.W. 706; Forbes v. Orange, 85 Conn. 255, 82 A. 559; Walters v. Baltimore & Ohio R.R. Co., 120 Md. 644, 88 A. 47, 46 L.R.A. (N.S.) 1128; Coyne v. Memphis, 118 Tenn. 651, 102 S.W. 355; Hamilton County v. Rape, 101 Tenn. 222, 47 S.W. 416.
IV
¶ 70. At the end of the twentieth century, the United States Supreme Court observed that the Takings Clause of the
We are not unmindful that other jurisdictions hold that damages resulting from landslides caused by excavations on highways in the course of improving them for public use are purely consequential, and not recover-
able by the owner. We find the doctrine of liability under such circumstances more consonant with reason and justice....
Damkoehler, 124 Wis. at 152 (emphasis added).
¶ 71. Because the majority expects E-L to suffer in legal silence, I respectfully dissent.
Notes
At closing arguments, E-L‘s attorney explained: “And the cost to E-L in the District‘s use of that groundwater... it‘s SeeIf any property has been occupied by a person possessing the power of condemnation and if the person has not exercised the power, the owner, to institute condemnation proceedings, shall present a verified petition to the circuit judge of the county wherein the land is situated asking that such proceedings be commenced. The petition shall describe the land, state the person against which the condemnation proceedings are instituted and the use to which it has been put or is designed to have been put by the person against which the proceedings are instituted. A copy of the petition shall be served upon the person who has occupied petitioner‘s land, or interest in land. The petition shall be filed in the office of the clerk of the circuit court and thereupon the matter shall be deemed an action at law and at issue, with petitioner as plaintiff and the occupying person as defendant. The court shall make a finding of whether the defendant is occupying property of the plaintiff without having the right to do so. If the court determines that the defendant is occupying such property of the plaintiff without having the right to do so, it shall treat the matter in accordance with the provisions of this subchapter assuming the plaintiff has received from the defendant a jurisdictional offer and has failed to accept the same and assuming the plaintiff is not questioning the right of the defendant to condemn the property so occupied.
E-L did not appeal the circuit court‘s dismissal of its negligence and nuisance claims against the Sewerage District; accordingly, that issue is not before this court.No suit may be brought against any volunteer fire company organized under
ch. 213 , political corporation, governmental subdivision or any agency thereof for the intentional torts of its officers, officials, agents or employees nor may any suit be brought against such corporation, subdivision or agency or volunteer fire company or against its officers, officials, agents or employees for acts done in the exercise of legislative, quasi-legislative, judicial or quasi-judicial functions.
[The Court]: . . . [The Sewerage District] deleted the sentence or propose to delete the sentence, “Groundwater is considered property of the person who owns the land under which it flows.”
That statement is true. It‘s not their exclusive property. They don‘t have the right to exclude others from using it, but they do have the right to use it, and Michels [State v. Michels Pipeline Constr., Inc., 63 Wis. 2d 278, 217 N.W.2d 339 (1974)] recognizes that they have a property interest in it.
So as a matter of fact, it is E-L‘s property, not its property alone, but it is E-L‘s property. Otherwise if E-L doesn‘t have any property interest in here, game over. This case ends. If it has no property interest in it, they cannot make a claim for just compensation.
[Attorney James H. Petersen, counsel for the Sewerage District]: Your Honor, I guess that‘s precisely the point the District is getting at. Groundwater is a common good. If you have property, you have a right to use the groundwater that passes underneath your land, and even some of the groundwater that‘s under your neighbor‘s land, by virtue of your property ownership.
But it doesn‘t mean that that groundwater is yours to the exclusion of others.
[The Court]: I‘m not saying that either, and my instructions don‘t say that either.
[Atty. Petersen]: These instructions allow that. They allow that to be argued.
[The Court]: First of all, it doesn‘t matter whether they allow that or not. The jury is not being asked to find that this was E-L‘s property exclusively.
In fact, the jury is being instructed to the opposite, that both the District and E-L and anybody else in that neighborhood had the right to use that property as long as they used it reasonably.
Wis. Power & Light, 3 Wis. 2d at 7. Here, the court of appeals erroneously distinguished those facts from the facts in this case to conclude that the Sewerage District‘s conduct “is on the ‘taking’ side of the line recognized by[T]he tower had no utility, direct or indirect, to the highway project, that the county did not need or desire the tower or the land on which it rested and did not intend to acquire or affect either the tower or the land, that the public obtained no benefit from injuring it, that the county had no reason to anticipate that damage would result from its acts, and that the injury to the tower was purely accidental.
