Lead Opinion
In February of 2009, the town of Lincoln (town) solicited bids on a road paving project. The town eventually awarded the contract to Sunshine Paving Corp. (Sunshine), which had submitted the lowest bid. To award the contract to Sunshine, the town had to waive a prequalification requirement that had been included in the bid documents (regarding the scale of the projects on which bidders had previously worked).
E.H. Perkins Construction, Inc. (Perkins), a competitor of Sunshine, also bid on the contract. After the town stated its intent to award the contract to Sunshine, Perkins filed an action in Superior Court seeking to contest the town’s intended course of action. Its complaint, which remains pending in Superior
After a Superior Court judge granted Perkins’s request for a preliminary injunction staying the process, the town filed a petition for interlocutory review pursuant to G. L. c. 231, § 118, first par., seeking to dissolve the preliminary injunction (so as to allow the awarding of the contract and the paving project itself to move forward). A single justice of this court granted that petition on June 11, 2009, and Perkins now appeals that order pursuant to G. L. c. 231, § 118, second par.
The current appeal presents the narrow question whether the single justice abused her discretion in addressing the preliminary relief issues.
The initial question we face is whether the appeal before us is moot. “Ordinarily, litigation is considered moot when the party who claimed to be aggrieved ceases to have a personal stake in its outcome.” Blake v. Massachusetts Parole Bd., 369 Mass. 701,
This is not to say that the underlying merits do not warrant judicial review. Indeed, we agree with our concurring colleague that the substantive issues that Perkins seeks to raise are important ones that merit judicial examination. That review, however, should occur first in the trial court, with any appellate review to follow entry of final judgment.
Appeal dismissed.
Notes
Perkins moved to stay the single justice’s order, and the single justice denied that motion. Perkins has not challenged that ruling.
Answering that question would require us to examine not only the single justice’s assessment of Perkins’s likelihood of success on the merits, but other factors as well, including whether the preliminary relief “promotes the public interest, or, alternatively, that the equitable relief will not adversely affect the public.” Loyal Order of Moose, Inc., Yarmouth Lodge #2270 v. Board of Health of Yarmouth,
According to the town, most of the project had actually been completed by the time the town filed its brief on September 29, 2009.
As the concurring opinion highlights, Petricca Constr. Co. v. Commonwealth,
We see no reason why any remaining proceedings in the trial court could not be completed expeditiously, given that the case seems tailor-made for summary judgment. If there are material facts in dispute, that is even more reason why review should occur in the ordinary course. Nothing in our opinion should be read as tying the hands of the lower court judge in addressing the merits, and we respectfully disagree with the statement in the concurring opinion that without our addressing the underlying merits now, “it is unlikely that the trial court will award bid preparation costs.”
Concurrence Opinion
(concurring in the result). I agree with the majority that this appeal presents us with the question whether the single justice abused her discretion in dissolving the preliminary injunction. I believe that the order of the single justice should be affirmed. Ultimately, I also believe that the appeal is moot, and therefore, I concur in the result.
This case raises issues of significant concern to the public interest, and there is no guarantee that E.H. Perkins Construction, Inc. (Perkins), will pursue expensive litigation in the trial court for the sake of recovering its bid preparation costs and then pursue another appeal that has already been fully briefed. While Perkins is entitled to pursue recovery of its bid preparation costs in the trial court, it is possible, if not probable, that
In reviewing the ruling of a single justice acting under G. L. c. 231, § 118, first par., “[t]he essential legal question . . . [is] ‘whether the single justice abused [her] discretion by entering an order without having a supportable basis for doing so.’ ” Aspinall v. Philip Morris Cos.,
In her order, the single justice advanced directly to the likelihood of success prong because she considered the case law to be adverse to Perkins’s position on the merits. Citing to Gil-Bern Constr. Corp. v. Brockton,
I cannot agree with the single justice that the Gil-Bern and J. J. & V. cases preclude Perkins from demonstrating a likelihood of success on the merits. Those cases presented defects in the bidder’s submissions readily distinguishable from the defects posed here. In Gil-Bern, supra, and J. J. & V., supra, the noncompliance with nonstatutory prerequirements was in essence ministerial, not substantive, see Gil-Bern, supra at 505-506 (“[i]n matters of substance there must be strict compliance with the [bid] requirements,” whereas, “[o]n the other hand, minor
Here, according to Perkins’s allegations, the defect in Sunshine Paving Corp.’s (Sunshine’s) bid concerned a mandatory prequali-fication requirement that was essential to Sunshine’s ability to submit a bid under the provisions of the town of Lincoln’s (town’s) request for bids. The defect could not be cured during the bid process. It would not be unreasonable to assume that other firms chose not to respond to the town’s request for bids because of their inability to comply with this mandatory prequali-fication requirement. A primary objective of G. L. c. 30, § 39M, is to set up an open and fair bidding process. See Petricca Constr. Co. v. Commonwealth,
I also would not affirm the order of the single justice based upon the absence of irreparable harm. While, typically, “[e]co-nomic harm alone . . . will not suffice as irreparable harm unless ‘the loss threatens the very existence of the movant’s business,’ ” Tri-Nel Mgmt., Inc. v. Board of Health of Barnstable,
Nevertheless, I agree with the majority in the result because, at this point, after nine months of Sunshine’s performance under its contract with the town, “public construction has been started” and “the requested injunctive relief is now [practically] academic.” Id. at 395.1 am loath to unwind that contract now, because such an action, though technically within our discretion, would not “serve the public interest.” Tri-Nel Mgmt., Inc. v. Board of Health of Barnstable, supra at 219. Accordingly, though I disagree with the single justice’s legal conclusions, I concur with the majority because to do so is in the public’s interest.
Most of the case law in this area has been written in consideration of a single justice’s action regarding a preliminary injunction, including affirming an order dissolving a preliminary injunction. See Petricca Constr. Co., supra.
It is true that affording flexibility to cities and towns was an important objective in enacting § 39M. See LeClair v. Norwell,
