E. Amanti & Sons, Inc. v. R.C. Griffin, Inc.E. Amanti & Sons, Inc. v. R.C. Griffin, Inc.
This dispute concerns the specifications for the emergency vehicle exhaust system for a fire station in the town of Danvers. The plaintiff, E. Amanti and Sons, Inc. (Amanti), the successful heating, ventilation, and air conditioning (HVAC) subbidder, claims that the town’s interpretation of the specifications violated key provisions of
1. Procedural and factual background. The specifications at issue here were set out in a five and one-half page addendum to the invitation for bids for construction of the town’s new fire station. (There is nothing in the record concerning the specifications the addendum “replace[d].”) The specifications required the emergency vehicle exhaust system to be “the standard product of a U.S. exhaust system manufacturer” and consisted of eighteen detailed paragraphs. Paragraph 18 reads as follows:
“Emergency Vehicle Exhaust System shall be as specified and manufactured by PlymoVent, or approved equal by the Fire Department.”
Amanti, a Massachusetts corporation experienced in the relevant subtrade as well as in public sector work, submitted a subbid for the HVAC system. See
Shortly thereafter, however, the architect notified the general contractor that Amanti’s proposed exhaust system did not meet the “performance requirement” in the addendum. The letter set out specific failings of Amanti’s proposed system, required Amanti to “resubmit a revised vehicle exhaust system” meeting the town’s specifications, and noted:
“The Fire Department has researched and observed in operation a number of exhaust systems. Their requirements were used in preparing the specification. The performance and characteristics included in the specification are provided so as not to limit the system to a single manufacturer.”
Amanti responded by reminding the general contractor that the project was bid under
In response, the architect insisted that it had “provide[d] a performance type of specification . . . [and] the name of one manufacturer that . . . meets the performance requirements [while indicating it] would accept other manufacturers who [could] meet [those] criteria.” The architect’s letter directed the general contractor to submit shop drawings within two weeks and stated that failure to do so would constitute a default. Four days later, presumably in response to Amanti’s request, the architect wrote another letter to the general contractor which stated, “I have the names of suppliers of vehicle exhaust systems such as Tycon, Monoxivent and N.S.G.V. but I don’t know where they are located, I can’t get any technical materials
There being no privity between the subcontractor and the town, see Grande & Son v. School Hous. Comm, of N. Reading,
2. The applicable law. At the time of the events in this case,
“Specifications for such contracts [underG. L. c. 30, § 39M(a) ], and specifications of contracts awarded pursuant to the provisions of [G. L. c. 149, §§ 44A to 44L] shall be written to provide for full competition for each item of material to be furnished under the contract; except, however, that said specifications may be otherwise written for sound reasons in the public interest stated in writing in the public records of the awarding authority or promptly given in writing by the awarding authority to anyone making a written request therefor, in either instance such writing to be prepared after reasonable investigation. Every such contract shall provide that an item equal to that named or described in the said specifications may be furnished; and an item shall be considered equal to the item so named or described if (1) it is at least equal in quality, durability, appearance, strength and design, (2) it will perform at least equally the function imposed by the general design for the public work being contracted for or the material being purchased, and (3) it conforms substantially, even with deviations, to the detailed requirements for the item in the said specifications. For each item of material the specifications shall provide for either a minimum of three named brands of material or a description of material which can be met by a minimum of three manufacturers or producers, and for the equal of any one of said named or described materials.”
(The term “material” was defined as an “article, assembly, system, or any component part thereof.”
3. Standard of review, prior proceedings, and issues on appeal. “The standard for reviewing . . . [trial court action on] a motion for summary judgment is whether the record shows that there is no genuine issue as to any material fact and whether the moving party is entitled to judgment as a matter of law. See
The Superior Court judge ruled in relevant part that, despite the town’s insistence to the contrary, “[the town’s] exhaust system specification [was] not a performance [i.e. competitive] specification because ... [it was not] able to be satisfied by any manufacturer other than PlymoVent.” She concluded that the town “had a duty to disclose to bidders that PlymoVent was [a] sole source” and that having failed in that duty, the town was liable for Amanti’s lost profits.
On appeal, the town contends that its “bid specifications were compliant [with] the terms of c. 30,
Needless to say, Amanti’s view of the statute and its application to the facts of this case is different. Amanti argues that “[tjhrough its express language and by its operation [G. L.] c. 30,
4. Legal analysis. We reject the town’s argument that the nature of the specifications does not matter. The point of enacting
In order to determine what
Unfortunately there are several ambiguities in
As originally enacted,
“For each item of material the specifications shall provide for either a minimum of three named brands of material or a description of material which can be met by a minimum of three manufacturers or producers, and for the equal of any one of said named or described materials.”
St. 1967, c. 535, § 5. The 1967 amendment described the requirements for competitive specifications that had been missing before. It required the awarding authority to demonstrate that there are at least three sources from which a bidder could obtain essential items for the project. The amendment also made clear that both proprietary specifications (those that are “otherwise written”) and competitive specifications must allow substitution of a product deemed to be equal to those named or described in the specifications.
It is unclear precisely what action an awarding authority must take to ensure that proprietary specifications comply with
Nor is it the bidder’s responsibility to, in the town’s word, “uncover” three sources for materials subject to a competitive bid, although it is the bidder’s responsibility to locate an “equal” product. See St. 2000, c. 159, § 62 (recent amendment to
Here it is clear at least from the post-award correspondence and the town’s answers to interrogatories that, as the Superior Court judge found, the town’s specifications were proprietary, despite its persistent denial. A critical aspect of open and honest competition is that all participants should have complete and accurate information about the terms of the procurement, either a listing of acceptable sources of materials for a competitive bid or a clear indication that the specifications are proprietary. The mere addition of the words “or equal” to the designation of PlymoVent, which are required in any case, did not constitute a middle ground, as the town suggests, or otherwise satisfy the requirements of
In its brief, the town relies on a decision of the office of the Attorney General, see
5. Damages. While acknowledging the general rule that “strict adherence to the public bidding laws overrides equitable considerations,” the Superior Court judge rejected the town’s assertion that the plaintiff was not entitled to damages. She determined that the town had not entered a “no bid” contract and that “[t]o allow [the town] the double benefit of obtaining the PlymoVent emergency vehicle exhaust system and voiding the contract so that it will not have to indemnify [the general contractor] for Amanti’s loss because of [the town’s] wrongful
On appeal, the town relies on Phipps Prods. Corp. v. Massachusetts Bay Transp. Authy.,
The town is correct that the general rule focuses on the statutory goal of competitive bidding for public procurement contracts rather than on the equities of a particular bidding situation. See Phipps Prods. Corp., supra at 691. There is precedent, however, for requiring a city to pay a subbidder the extra costs of installing plumbing pipes described in the specifications. E.A. Berman Co. v. Marlborough,
Moreover, the cases the town cites are distinguishable. Phipps Prods. Corp., supra, involved a complaint for specific performance of a purchase and sale agreement where the Massachusetts Bay Transit Authority (MBTA) had reneged on the agreement. The MBTA had negotiated the sale without an advertisement of its intent to sell the property. Without such an advertisement, there was no basis for determining the highest bidder, as
In Majestic Radiator, supra, the president of the company solicited business from the Middlesex County Hospital. Ultimately the company supplied 293 radiator covers in a no bid contract, supposedly based on an emergency waiver. When the county treasurer refused to pay the bill, the company brought suit. The court held that the company could not recover. Not only was there no competitive bid, but there was also a failure to comply with the statutory emergency procedures. It was that failure that the court determined to be fatal, even in the absence of bad faith. 397 Mass, at 1004. Thus, both Phipps and Majestic involved what were essentially no bid contracts, one involving real property and the other radiator covers.
Most suits claiming that contracts made in violation of bidding laws are void have been brought by disappointed bidders or by taxpayers challenging the award of the contract pursuant to
There are “circumstances in which noncompliance with bidding requirements has been characterized as technical rather
“[T]he legislative goals of
We have found only two cases in which a contractor was denied recovery after having fully performed. In each of those, involving the purchase of goods rather than construction of a building, the parties circumvented the competitive bidding process altogether. See Adalian Bros. v. Boston, 323 Mass. 629 (1949) (rugs for the mayor’s office); Majestic Radiator, supra (radiator covers). Such is not the case here. Cf. East Side Constr. Co. v. Commonwealth, 329 Mass, at 353 (taxpayer suit holding
Therefore, in the circumstances of this case and on the record and argument before us, we conclude that the judge did not err in requiring the town to reimburse the general contractor for the damages the contractor was ordered to pay Amanti. We do not, however, endorse the basis of the judge’s decision — bad faith on the part of the town. See Schwartz v. Travelers Indemnity Co.,
6. Attorney’s fees. After a damages hearing, a second Superior Court judge ordered that Amanti recover of the general contractor $18,588.11 (the additional cost of the PlymoVent equipment), with interest, together with $5,981 in attorney’s fees, and court costs of $217.52. See
On appeal, the general contractor argues that it “should be able to recover [its] own attorney’s fees and interest and costs against [the town] as a pass through under [G. L. c. 149,] § 29.” The general contractor acknowledges, however, that “current law does not provide for such pass through.” It claims it is entitled to recover these expenses under the “theory” of breach of contract, compare Campbell Hardware, Inc. v. R.W. Granger & Sons, 401 Mass, at 280, and argues that leaving it to bear its own costs is inequitable, since the general contractor was a party only because there was no privity between the town and Amanti.
This issue was not squarely raised in the proceedings below. It is at best unclear whether the general contractor requested this relief in its third-party complaint. While prior to the hearing
In any case, as the general contractor acknowledges, the law does not authorize the relief it seeks. Under the “American Rule,” litigants bear their own expenses unless a statute or a contract or other agreement provides otherwise. Judge Rotenberg Educ. Center, Inc. v. Commissioner of the Dept. of Mental Retardation (No. 1),
Amanti, having requested in its brief attorney’s fees “in connection with the appeal as provided by
Order on assessment of damages and judgment affirmed.