79 N.Y.S. 17 | N.Y. App. Div. | 1902
Lead Opinion
The plaintiff contracted with the city of New York, through the commissioners of the department of public parks, for the construction of a boiler house and engine room for the Metropolitan Museum of Art.
The complaint contains two causes of action ; the first is to recover $669.30, the balance unpaid upon the contract; the second, for damages caused by the wrongful rulings, orders and directions of the architect and board of park commissioners in requiring the plaintiff to do over again certain work which it is alleged he completed in accordance with the contract, plans and specifications, and also compelling him to furnish extra work, labor and materials under the wrongful claim that the same were embraced within the contract.
The allegations of the complaint with reference to the first cause of action proceed upon the theory of complete performance by the plaintiff. The specifications forming a part of the contract expressly provide that the architect’s certificate that the contract has been faithfully performed with reference to the materials furnished and work done should be a condition precedent to the right of the plaintiff to payment for any part of the work. Upon the trial the plaintiff failed to show that the work was completed to the satisfaction of the architect, or that the latter had furnished a certificate to that effect. The complaint contains no allegation excusing the production of the architect’s certificate. Evidence was offered, however, tending to show complete performance by the plaintiff in accordance with the contract and specifications and that the architect unreasonably withheld his certificate, insisting that the work had not been properly performed. The plaintiff made no motion to amend his complaint to conform to the proof in this regard. The judgment entered upon the nonsuit cannot be reversed unless the plain
“ That among other things the defendant, its officers and agents, compelled the plaintiff to attempt to make a certain horizontal boiler flue under the cellar floor of the said boiler house watertight, which was an impracticable thing to do, and not required by the plans and specifications of said contract. * * * Compelled
plaintiff to take down and rebuild horizontal flue at boiler house
The plaintiff’s testimony shows that he constructed this flue literally in accordance with the contract plans and specifications; that early in the construction of the work he notified the architect that the flue, if constructed according to the plans and specifications, would not be watertight, as was evidently intended; that he was subsequently directed by the architect to complete the flue without any change or alteration of the plans and specifications therefor; that after completion it was ascertained that the flue was not watertight, and the architect thereupon materially altered the plans and specifications with reference to the manner of constructing it, and directed the plaintiff to take it down and remove it, and reconstruct it in accordance with such altered plans and specifications; that plaintiff, insisting that he had performed his contract in this regard and was under no obligation to do the work over again in a different manner, appealed to the board of park commissioners protesting against the action of the architect, and was by them directed to reconstruct the work as required by the architect; that he also notified the architect and the board of park commissioners that the flue would not be watertight if constructed according to the amended plans and specifications; that he did reconstruct it in accordance therewith, and that the reasonable value of this work was $1,604.51.
It is objected that the plaintiff cannot recover for this item for the reason that the flue as thus reconstructed was not watertight. The contract expressly provided that the work should be done “ to the satisfaction of the Commissioners of the Department of Public Parks and the architect appointed by them and in accordance with the drawings, details and directions given or which may be given by the architect and in conformity with the specifications.” The amended specifications require an excavation for the flue of sufficient width and depth to make it, when completed, of the size indicated on the plans, and further provided with reference to this flue as follows:
“ Mason Work :
“ Line up the sides of excavation with four inches of brick and cover the bottom of flue with not less than 4 inches of rough concrete, composed of 3 parts of broken stone, 1 part clean sharp
“Pave the flue throughout with brick grouted in in cement mortar.
“ Asphalt :
“ Cover the entire inside of flue, prepared as specified, with inch of Seysel rock asphalt, or equally good and approved brand, applied hot, so put on as to absolutely cover all crevices and joints, and render the same impervious to water.
“Generally:
“ The work is all to be performed in a thorough and mechanical manner, and rendered thoroughly watertight, all to be subject to the approval of the architect.”
The provisions of the original and amended specifications with reference to the flue being impervious to water and watertight were the same. The legal effect of this contract was that the contractor undertook to construct the flue in accordance with the plans and specifications, and he was to make it watertight so far as a construction in accordance with the plans and specifications would produce that result; but he did not guarantee the efficiency of the plans and specifications in this regard. (MacKnight Flintic Stone Co. v. Mayor, 160 N. Y. 80.)
The specifications contain the following clause : “ Such details on a large scale or full size as may be necessary to more fully explain the general drawings will be furnished to the contractor at the proper time during the progress of the work. * * *
“ The various drawings and this specification are intended to cover a complete and first class job in every respect. Anything omitted in' this specification and shown on the drawings, or vice versa, is to be done by the contractor without extra charge or expense.”
It is contended on the part of the city that these provisions authorized the architect to change the plans and specifications by detailed plans, and that they are authority for the changes which he made. This contention is untenable for two reasons. In the ■first place it was not intended to authorize the change of either the specifications or plans by enlarged detail plans or drawings, but only
It is further contended that this was extra work, and that, inasmuch as it was provided in the contract that the contractor should make no claim for extra work unless the same was agreed upon •between the parties in writing, no recovery can be had therefor. That provision of the contract relates to work concededly not within the contract, and not to changes and alterations in the work intended to be covered by the agreement. Furthermore, it is not contended that the board of park commissioners did not have authority to contract for this work even if it were extra work; and the board itself which made the contract, having authorized and directed the work, would be estopped from contending that the plaintiff could not recover therefor because the contract required that an agreement in writing should be made concerning the same. The architect wrongfully insisted that the plaintiff had not performed .his contract with reference to the construction of the fine, not because he had not followed the plans and specifications, but because ■of the architect’s blunder in preparing plans and specifications that would not accomplish the object desired, to wit, a watertight flue.
On this branch of the case the plaintiff was entitled to recover on the authority of Gearty v. Mayor (171 N. Y. 61). There is no basis for a distinction between that case and this. There, as here, the contract related to the performance of work for the park department, and the provisions of the specifications, so far as material, are almost identically the same, the only difference being that that ease related to a pavement and the engineer had supervision of the construction, and the word “ engineer ” appears in the specifications where the word “ architect ” appears in the case at bar.
It follows, therefore, that the plaintiff made out a prwna facie •case for a recovery with reference to the cost of reconstructing this Hue and it was error to dismiss the complaint. In this view it ■becomes unnecessary to consider the sufficiency of the complaint or proof with reference to the other items of damages claimed in the second cause of action.
O’Brien and Hatch, JJ., concurred; Van Brunt, P. J., and Ingraham, J., dissented.
Dissenting Opinion
The plaintiff made a contract with the defendant whereby he was to construct a boiler house and engine room in the Central Park in the city of Hew York for the use of the Metropolitan Museum of Art, for which the defendant agreed to pay the plaintiff the sum of $47,700. There are two causes of action alleged in the complaint. The first is to recover the balance alleged to be due under the contract, and the second is to recover the damages sustained by the plaintiff by reason of the refusal of the defendant to permit him to carry out the contract in a reasonable, proper and expeditious manner. As a first cause of action the complaint alleges the making of the contract; that the plaintiff had fully performed all the conditions and covenants of the said agreement and fully completed the work in accordance with the terms and conditions of the contract, “ and the same has been duly accepted by the defendant and its officers, and its acceptance duly certified in writing; ” that the amount to be paid by the contract is $47,700, of which the plaintiff has received the sum of $47,030.70, leaving a balance due from the defendant to the plaintiff of $669.30, for which sum plaintiff demands judgment. For a second cause of action the plaintiff alleges that while he was endeavoring in good faith to carry out the said contract in accordance with the terms and conditions thereof, “ the defendant, through its officers and agents would not permit the plaintiff to proceed and carry out the said contract in a reasonable, proper and expeditious manner, but by and through the wrongful act, neglect and default of the defendant, its officers and agents, the plaintiff was hindered and delayed and put to great loss and expense by reason of said wrongful act, neglect and default, and was compelled to do his (plaintiff’s) work at a largely increased cost by reason thereof.”
The answer admits the making of the contract; alleges that the plaintiff entered into its performance and, except as specified, has fully completed the said work in accordance with the terms and
By the contract which was introduced in evidence the plaintiff agreed that he would complete the entire work to the satisfaction of the commissioners of the department of public parks and in substantial accordance with the specifications and plans, and that he would not ask, demand, sue for, or recover for the entire work any extra compensation beyond the amount payable for the whole of the work in this contract stipulated which shall be actually performed
The second cause of action is for the damages sustained by the plaintiff by reason of the failure of the officers of the defendant to allow him to complete his contract. There is no allegation in the complaint that plaintiff has performed extra work. It is the damages sustained by the refusal of the defendant to permit the plaintiff to proceed and carry out the contract in a reasonable, proper and expeditious manner that plaintiff seeks to recover by this second cause of action. This allegation would seem to be sufficient under the principle established in Gearty v. Mayor (171 N. Y. 61), and we have to determine whether the evidence is sufficient to sustain a recovery thereon. The plaintiff testified that he entered into this contract in September, 1892, and commenced the performance of the contract; that on December 7, 1892, he wrote a letter to the architect in which he stated that he was building the horizontal flue for the boiler house, but was afraid that water would come through, causing the flue to be damp or wet all the time, and asking the architect if he desired a change of the construction so as to overcome this pressure. In reply to this the architect stated that the contract called for a construction which, if faithfully carried out, would make this flue watertight; and shortly afterward the architect wrote to the plaintiff directing him to stop work for the winter. Subsequently, in March, 1893, the plaintiff, having resumed work, wrote to the architect saying that he had partly built the flue in accordance with his contract, but that it was not and would not be watertight, and asking for advice in regard to the matter. The architect subsequently called the plaintiff’s attention to the water in this flue, directing him to cause it to be pumped out. In reply the plaintiff wrote that there was no special or general provision in the contract for taking care of this water and saying that it would be unjust to ask him to pump it out without compensation and refused to do so, and the plaintiff refused to do any further work in connection with the flue, telling the architect that he had constructed the flue in accordance with the contract and that he refused to take it down and construct it in a different way. Subsequently, and in November, 1893, the architect gave to the plaintiff. an additional specification for the building of this flue. The plaintiff testified
The case of Gearty v. Mayor (171 N. Y. 61) is not, I think, controlling. The contract there was essentially different from that in this case. The work there to be done was to pave a transverse road crossing Central Park at Ninety-seventh street from Fifth avenue west to Eighth avenue. The contract was to be entirely under the direction of the commissioners of the department of public parks, and the filing of the certificate of the engineer appointed by the commissioners was to be a condition precedent to the right of the plaintiff to payment under the contract, with a further provision that should any work be found defective or improperly done, such work was to be taken up, relaid or otherwise remedied to the satisfaction of the engineer; and if the contractor refused to correct such defective work when notified to do so, the commissioners of public parks were to employ the necessary men and material to do the work, with a further provision that the final certificate of the engineer should be conclusive as to the performance of the contract. The provisions of the contract and the nature of the work to be done in
Ho case is cited by counsel to sustain such a contention, except the case of Gearty v. Mayor (supra), and that, as I have shown, was upon an entirely different contract and for the performance of different work that did not involve the determination of an expert as to whether or not the plans and specifications had been complied with as in the case of a building such as the one in question. We are not dealing with a case where the city refused to accept the work as complete because the architect had not given a certificate where it was alleged and proved that the work was finished in accordance with the contract, and that the refusal of the architect to give a certificate was unreasonable, as in the case of MacKnight Flintic Stone Co. v. Mayor (160 N. Y. 80), but
This latter case seems to be in point. The contract in that case provided that the engineer should in all cases determine the amount or the quantity of the several kinds of work to be paid for under the contract; should determine all the questions in relation to the work and the construction thereof, and in all cases decide every question that might arise relative to the execution of the contract on the part of the contractor, and his decision should be final and conclusive. The engineer under this clause determined that only sixty-four cubic yards of cut stone masonry were to be paid for by the city, and it was held that that award was conclusive under the terms of the contract. Here the architect determined under the contract what the plaintiff was required to do to complete the work contracted for. He furnished plans and specifications for the work, and when the question as to this boiler flue arose he furnished some detail drawings, as the contract provided that he should furnish, and finally the plaintiff accepted those drawings and did the work required under the contract. There is no allegation of bad faith on the part of the architect or the park commissioners, or that this determination was not an honest decision as to the construction of the contract and the work required under it; and it seems to me that there is no basis for a claim that the city or its agents by an unreasonable or an improper action prevented the plaintiff from completing his contract and thus rendered the city liable for damages. The other items of damages which the plaintiff claims to recover under this second cause of action were all for work required by the architect to be done to complete the contract, and what
I think, therefore, that the action of the court below in dismissing the complaint at the end of the plaintiff’s case was correct and that the judgment appealed from should be affirmed, with costs.
Van Brunt, P. J., concurred.
Judgment reversed,.new trial ordered, costs to appellant to abide «vent.