Lead Opinion
Opinion by
These appeals mark the third time in recent years that proposed rate increases sought by the Duquesne Light Company (hereinafter called Duquesne) have been before this Court. The litigation had its beginning on February 6, 1950, when Duquesne filed with the Pennsylvania Public Utility Commission (hereinafter called Commission) Tariff No. 10 superseding Tariff No. 9, and providing for increases in rates to become effective April 10, 1950, and designed to produce additional annual revenue of $7,720,612. Complaints were filed against the proposed tariff and hearings were held by the Commission. By its order of August 29, 1951, the Commission disallowed the full increase proposed, and allowed instead an increase of $3,556,924. The Commission found annual operating revenues to be $60,574,238 based upon the 1949 level of operations, and allowed a rate of return of 6 percent or $12,900,000 on a fair value of $215,000,000. On appeal to this Court the order was (July 17, 1952) reversed and the case remanded to the Commission. See City of Pittsburgh v. Pa. P. U. C.,
Meanwhile, on December 11, 1952, Duquesne had filed with the Commission its Tariff No. 12, proposing new rates resulting in a total increase in gross revenues of $4,732,022 to become effective March 1, 1953. The effective date of Tariff No. 12 was suspended by the Commission for a total period of nine months to December 1, 1953. By an order dated November 23, 1953, the Commission prescribed Tariff No. 11 as temporary rates to be in force until the final disposition of the proceedings involving Tariff No. 12. Complaints were filed by the City and by the St. Joseph Lead Company (hereinafter called St. Joseph). There were eighteen days of hearings with a considerable amount of testimony and numerous exhibits.
On January 11, 1954, Duquesne appealed from the order of December 22, 1953, to Nos. 78, 79, and 80
Preliminary Considerations
Commission Procedure. Duquesne contends that the Commission was in error “in reducing allowable revenues under existing rates where no complaint was filed against such revenues and the Commission did not institute any proceeding against them”. It is the position of Duquesne that the only issue before the Commission was the reasonableness of the proposed increase in revenues set forth in Tariff No. 12, and that, so far as the present proceeding is concerned, the Commission could not provide for any revenues below the levels established by Tariff No. 11; Duquesne relies upon §309 of the Public Utility Law, Act of May 28, 1937, P. L. 1053, as amended, 66 PS §1149, which provides that the Commission shall not impose a reduction in existing rates except “after reasonable notice and hearing”. Its position is that, since there was no complaint against, or investigation initiated concerning, existing rates, and no notice in connection
Section 309 concerns the fixing of rates by the Commission upon its own motion or upon complaint. It is §308 (66 PS §1148) which sets forth the procedure to be followed in cases where a utility has filed new tariffs proposing voluntary changes in rates. Du-quesne initiated the present proceedings by filing Tariff No. 12. Paragraph (c) of §308 provides in such event: “If, after such hearing, the commission finds any such rate to be unjust or unreasonable, or in anywise in violation of law, the commission shall determine the just and reasonable rate to be charged or applied by the public utility for the service in question, and shall fix the same by order to be served upon the public utility; and such rate shall thereafter be observed until changed as provided by this act”. There is thus imposed upon the Commission the duty of prescribing just and reasonable rates, and it is necessarily implied that such rates may be either higher or lower than the existing rates which the utility voluntarily seeks to change.
Duquesne cites West Penn Power Co. v. Pa. P. U. C.,
Court Function. In the words of Judge Head in the early case of Baltimore & Ohio R. R. Co. v. Public Service Commission,
In enacting tbe present Public Utility Law tbe legislature provided: “Tbe order of tbe commission shall not be vacated or set aside, either in whole or in part, except for error of law or lack of evidence to support tbe finding, determination, or order of tbe commission, or violation of constitutional rights”. Act of May 28, 1937, P. L. 1053, §1107, as amended, 66 PS 1437. See Pittsburgh v. Pa. P. U. C.,
Fair Value
Trended Cost. The City contends that the Commission should have rejected the evidence of trended original cost presented by Duquesne as measures of value. This evidence showed, inter alia, the original cost of Duquesne’s property trended to the cut-off date of December 81, 1952, and to three-year, five-year, and ten-year average price levels. In determining these trended prices, fifteen of ninety-one plant accounts were trended by the use of factors developed from Duquesne’s own experienced unit costs. The remaining accounts were trended by the use of various published index numbers from which trending factors were derived. The Commission found that the fifteen accounts were the only ones for which Duquesne’s experience costs were available. They had been considered reliable in the prior rate case and were so considered in this proceeding. By use of factors reflecting Duquesne’s own experienced costs, the original cost trended so far as these fifteen accounts were concerned, amounted to $118,419,399. By using published Handy-Whitman index numbers, the trended original cost of these same fifteen plant accounts amounted to $95,692,331. The City’s objection to the use of trend factors developed by Dusquesne is that they are unreliable since they do not take into account differences in quality of units of property installed in different years. There can be no question that any trended original cost study will contain certain inherent errors or inconsistencies arising out of changes in the nature of property, and the
The City also argues that Duquesne admittedly included in trended cost measures of value items which had previously been charged to expense. These items were amounts representing purchasing and warehousing costs which, prior to 1931, had been charged to expense. The Commission found that seven accounts included such costs and, accordingly, adjusted the various price levels by amounts to correct this error. This was in accord with our decision in Philadelphia v. Pa. P. U. C.,
Accrued Depreciation. The Commission found that the accrued depreciation applicable to original cost of Duquesne’s property on the cut-off date of December 31, 1952, amounted to 26.5 percent, that the accrued depreciation applicable to trended original cost amounted to 34.5 percent, and that the accrued depreciation applicable to reproduction cost amounted to 34 percent. Both Duquesne and the City object to these findings. Duquesne contends that they are too high while the City asserts that they are too low.
The Commission had before it the following: a reserve requirement study by the City, a reserve requirement study by Duquesne, the finding of the Commission in the prior rate proceeding, and the booh reserve. The Commission did not consider the book reserve controlling since it had not been accumulated on actual service life but from percentages of revenues and by lump sum appropriations from surplus. Duquesne’s witnesses stated that the company’s records were not adequate to enable it to prepare a reserve requirement study based on its own experience, and based the study presented upon the retirement experience of utilities in the State of New York. In the words of the Commission: “We quite agree that failing a utility’s own retirement experience, the second best measure would be the retirement experience of other comparable utilities”. The City contends that the estimated amount of accrued depreciation applicable to original cost based on Duquesne’s requirement study should have
Duquesne’s contention that the percentage figures are too high is based on a comparison of the percentages of accrued depreciation determined by the Commission in the order made on Tariff No. 11, and the percentages developed in the present proceeding. In so doing, Duquesne is attempting to treat the findings in the prior proceeding as res judicata. This it cannot do. See Philadelphia v. Pa. P. U. C.,
The duty of the Commission was to determine according to its best judgment the accrued depreciation from all the evidence presented: Blue Mountain Telephone & Telegraph Co. v. Pa. P. U. C.,
Investment in Elrama No. 2. On January 18, 1953, Duquesne placed in operation a generating plant, known as Elrama No. 2. This was after the cut-off date of December 31, 1952. However, since the first hearing did not take place until March 11, 1953, the Commission could properly take into consideration the construction costs of the plant and the expense savings which Duquesne expected as a result of more efficent operation. The Commission may not ignore recent information and evidence in the record which substantially affects the problem before it. See Pittsburgh v. Pa. P. U. C.,
It is apparent that the amount sought by Duquesne represents the total cost of proposed expansion and, on the basis of the quoted testimony, expansion which Duquesne felt should have been made earlier. The fact is however that, of this proposed expansion, only one portion (Elrama No. 2) had been completed and was in service. Duquesne concedes that “The Commission has allowed $14,500,000 which is substantially the amount required to be spent for the generator unit alone, with immediately related transmission facilities”. The Commission found that the remaining items making up the balance of $13,500,000 were proposed improvements to be made at some unascertained date, not related or essential to either the construction
Materials and Supplies. The City objects to the allowance of $9,250,000 comprising $5,500,000 for materials and supplies and $3,750,000 for coal inventory. There was no claim made by Duquesne for cash working capital, and the Commission made no allowance in this connection, which is in accord with the ruling of this court and the Pennsylvania Supreme Court in Pittsburgh v. Pa. P. U. C.,
Projected Revenues. In order to determine the projected revenues for the future it was necessary for the Commission to adjust the operating revenues and expenses of the test year so as to eliminate the effect of a strike in the steel industry, and also to annualize revenues received from, and expenses incurred in serving, customers during the test year. The Commission adopted the City’s study relative to the effect of the steel strike. Briefly, the computation to counteract the effect of the strike was measured by the difference between what the revenues would have been had the trend prior to May, 1952, been continued up to August, and by projecting the trend after August, 1952, back to May. The difference between these overlapping values was $1,902,000. No question is raised on this appeal challenging the Commission’s acceptance of this evidence. The City contends however, that there was error in rejecting the results of its study for annualization of operating revenues and expenses and in accepting Duquesne’s annualization study.
The City’s study was based on a mathematical projection on a total system basis, which did not distinguish between residential and industrial use. The Commission found that residential sales exert slight weight in the tabulations of total sales, and that the City’s calculations so weighted were unacceptable. Du-quesne’s study was based on an analysis of the number of new customers added in the residential, small commercial and small industrial classes, with the amount of kilowatt hours used by each. From this was determined the amount which would have been consumed had they been customers throughout the entire year. In the case of large industrial and commercial users the number of new contracts and the changes in old contracts were analyzed and the estimated additional
Excess Profits Tax. By Act of Congress dated July 16, 1953, the federal excess profits tax expired on December 31, 1953, or nine days after the entry of the Commission’s order of December 22, 1953. The order disallowed excess profits taxes. Duquesne objects on the ground that the tax was in existence during the entire base year of 1952. We recognize that, in practical application, the use of a test year and cut-off date in determining a rate case is not free from difficulty, since changes may become known before the order is entered. In strict theory perhaps, these subsequent developments should be ignored. However, this court has stated that the Commission “cannot be oblivious” to them: Pittsburgh v. Pa. P. U. C.,
On the other hand, Duquesne alleges that the Commission committed an injustice in disallowing the excess profits tax without taking cognizance of a wage increase which became effective October 1, 1953, over two and a half months before the order was made. We agree that an adjustment to reflect the elimination of the excess profits tax without a corresponding adjustment to reflect the wage increase is not only inconsistent but directly in conflict with the principle underlying our prior decisions. The wage increase “was called to the Commission’s attention at the oral argument on November 10, 1953, and was actually in effect prior to the writing of the Commission’s Order”.
Fuel Adjustment Clause. A fuel adjustment clause is a method designed to enable a utility to adjust its revenues either upward or downward to reflect changing fuel costs without having to resort to the cumbersome procedure of filing new tariffs. Tariff No. 12 provided a fuel cost adjustment applicable to certain
Duquesne argues that the Commission’s clause gives the rewards of efficiency to customers while the costs of efficiency must be borne by the company, and that a premium will thereby be placed on inefficient operation. The Commission answers that recovery of capital outlay should be by way of the demand charge, otherwise the Company will receive a double return. In Magee Carpet Co. v. Pa. P. U. C.,
We must agree that “the changing fuel cost to the utility” is determined both by the change in cost of fuel per million BTU, and the change in the efficiency of converting fuel into electric energy. The operation of the clause, like most questions dealing with the refinements of rate structures, is primarily a factual matter for determination by the Commission: Magee Carpet Co. v. Pa. P. U. C.,
Annual Depreciation Allowance. Duquesne complains that the order of the Commission is confiscatory in that the allowance for annual depreciation is not
In its 1951 Order, the Commission allowed Du-quesne the amount necessary to enable it to recover the full amount of the original cost of the property. The Commission, after pointing out that the annual accruals would produce an overall total of only $200,-817,528 said (29 Pa. P.U.C. 674, 758) : “This amount compares with $212,199,261 representing the original cost of depreciable and depletable plant and construction work in progress in service, as shown above in Table YI. So that respondent will be provided with this difference of $11,381,633, we will include in our finding of annual depreciation for the purposes of this proceeding, $443,555 which, over remaining useful service life, will accrue to that difference”. Although
In the present order the Commission has held that there can be no increase in the annual depreciation charges to enable the Company to recover the deficiency in the reserve requirement; It now takes the position that it was in error in the previous case involving Duquesne. Briefly, the Commission contends that Duquesne did not prove that its deficiency in book reserve in the past resulted from lack of earnings. Furthermore, it takes the position that (1) it is a practical impossibility in most cases to make a determination of whether past earnings were adequate or inadequate, and (2) the past must be forgotten if rates are to be based on the present cost of service to the utility. The Commission relies on Newport Home Water Co. v. P. S. C.,
We are of the opinion that the reasoning in Pittsburgh v. Pa. P. U. C.,
Conclusion
To summarize, we find no errors in the Commission’s order except with regard to (1) the making of an adjustment for the elimination of the excess profits tax without making. a corresponding adjustment for the wage increase; and (2) the allowance.for annual
Order
The order of the Commission is reversed, and the record is remanded to the Commission with instructions to proceed in a manner consistent with the views expressed in this opinion.
Notes
The record before ns consists of six volumes, four of testimony and two of exhibits, with a consolidated index separately printed. The briefs of counsel contain approximately 800 pages.
Schuylkill Valley Lines, Inc. v. Pa. P. U. C.,
This statement in appellant’s brief is not challenged.
In Rate “W” to that portion of the energy used per month in excess of 1,000 KWH, and in Rates “X” and “X” to all energy billed.
This figure does not include $339,190 for annual depreciation on the portion of Elrama No. 2 which the Commission included in the rate base.
Dissenting Opinion
Dissenting Opinion by
I dissent from the conclusion of the majority. I would affirm the order of the Commission. The majority opinion reverses the order of the Commission and remits the record with direction to apply the remainder life theory in computing Duquesne’s annual depreciation allowance. Having assumed the genuineness of the deficiency in the book reserve in a prior proceeding, the Commission might have allowed the additional annual depreciation of $412,000 under the remainder life theory in this case. The Commission, if it concluded the circumstances warranted, could have accepted the utility’s book estimate and this would have been within the sphere of its authority. Harrisburg Steel Corporation v. Pennsylvania Public Utility Commission,
Preliminarily it is well to remember that the regulation of public utilities, including the exercise of the rate making power by the Commission, is not an exact science, and calculations cannot always be made with mathematical precision. This is illustrated by reference to the recent history of this utility. The Commission in its order of March 9, 1953, in holding that tariff No. 11 was not unreasonable or discriminatory, found that allowable revenues were excessive in the amount of $652,739. The Commission nevertheless decided that it was impractical to design rates that would reduce revenues within such narrow limits; and Du-quesne has thereby been permitted to receive this excess in annual revenues. See City of Pittsburgh v. Pennsylvania Public Utility Commission,
In its order of August 29, 1951, the Commission allowed Duquesne $4,998,282 for annual depreciation on its plant. The annual depreciation allowance on Duquesne’s electric plant consisted of straight-line reserve allowance of $4,554,727, and a remainder life allowance of $443,555. Duquesne there contended that the Commission’s allowance for annual depreciation should be based upon replacement cost at current prices. We recognized that allowance for annual depreciation should be calculated to permit the utility to recover the original cost of its property; and we sustained the Commission’s calculation .of the allowance for annual depreciation, being necessarily a judg
In the present order of December 22, 1953, the Commission made an annual depreciation allowance to Du-quesne of $6,529,377, including Elrama No. 2 power plant. It is conceded that on the basis of the reserve requirement study there would be a deficiency in Du-quesne’s book reserve for depreciation. The Commission refused to amortize this deficiency by making provision for it in the annual depreciation charge. Du-quesne claims that this resulted in confiscation of $12,-000,000 of the original cost of its property.
The allegation of confiscation must be sustained by the evidence submitted by the utility, and the Commission is not obliged to establish the nature or validity of an inadequacy in the utility’s book reserve. It is only upon proof by the utility or upon an assumption that the deficiency in the book reserve was due to the utility’s insufficient past earnings or collections from consumers to compensate the utility for property consumed in rendering past service that it can be said that Duquesne will not receive over the expected service lives of the units of property their full original cost. Present rate payers are not to be charged for a failure of a utility to allocate adequate amounts to its book reserve for depreciation whether such bookkeeping entry is intentional or the result of erroneous methods. The correction of a utility’s book reserve for depreciation should be made through surplus in the
Depreciation is defined as the expense occasioned by the using up of physical property employed as fixed capital.
Briefly, the remainder life theory if applied requires that the Commission consider any deficiency (or excess) between the book reserve or any prior depreciation study and the present reserve requirement study, and add to the annual depreciation allowance (or in case of an excess to subtract) an amount sufficient to cover over the remaining service lives the deficiency or excess. In this illustration if the book reserve is to be accorded full weight due to the change in estimated service life from fifteen to ten years there is a deficiency in the book reserve of $2,500; $7,500 should have been accrued on the books in half the life of the property, to wit, five years, instead of $5,000 which the books actually show. Where the Commission applies the remainder life theory it makes an additional allowance (in this example $500 a year, $2500/5 yrs.) sufficient to permit the utility to amortize the deficiency, which it has created, over the remaining estimated service life of the property. On the other hand, if there was an excess of $2,500 between the book re
The Commission presents two reasons why it should not be compelled to apply the remainder life theory in any given case.
First, the Commission argues that application of the remainder life theory should depend on whether it is established, in a given ease, that the deficiency, or excess, between the present study and the book reserve is in fact genuine, as distinguished from a mere difference between the two estimates. The genuineness of the deficiency, or excess, in turn hinges upon the question whether the ptility in the past made more or less than a fair return (on fair value) over the years in question. If there is a deficiency and the utility has earned no more than a fair return on fair value then the deficiency would be genuine. Where there is a deficiency and the utility has in fact earned more than a fair return, to the extent that the utility has earned more than a fair return, the deficiency has no validity. Where an excess appears in the book reserve and the utility has earned at least a fair return on fair value the excess may be considered genuine. But where the utility has not earned at least a fair return the excess would to that extent be false.
Secondly, the Commission takes the position that, since it is a practical impossibility to try a rate case involving prior years, the Commission cannot be required to apply the remainder life theory in any given
I think the answer is obvious when the problem is thus analyzed. The Commission should give the utility everything to which it is entitled. This is done when it makes a reasonable annual depreciation allowance based upon a present reserve requirement study, which is a sufficient basis for recovery of full original cost. This conclusion is fortified when we consider the nature of an annual depreciation allowance in relation to accrued depreciation. In Clark's Ferry Bridge Company v. Public Service Commission,
A fundamental error in the majority opinion is an assumption, that the Commission’s. refusal to give weight to the deficiency between the book reserve and
Essentially, the problem is one of the weight to be given to evidence by the Commission. It can disregard the book reserve and base annual depreciation entirely on the present reserve study, or it can give some weight
The only logical rule, therefore, is that the Commission should have discretion as to what weight, if any, it will give to the book reserve in a given case as compared to the present reserve study. For instance, admittedly here the book reserve was computed
The majority opinion relies upon several erroneous grounds for directing the Commission to apply the remainder life theory in this case. In the majority opinion it is said: “. . . there is nothing to show that the Company was guilty of any faulty past practices in accumulating its book reserve, or that the conceded deficiency therein is not genuine. In fact, in 1937 the Commission expressly approved the Company’s reserve for depreciation and its annual accruals. . . . The present record shows no abuse of discretion by Duquesne, nor is any such abuse asserted. ... we are not to be understood as indicating that the remainder investment approach should always be followed. In the case at bar, however, we cannot now approve a complete change in policy to the Company’s prejudice.” .....
(1) Alleged approval of the utility’s reserve in prior proceedings was expressly limited to’and for the purposes of the particular proceeding. Assuming such approval was made in prior proceedings, it . does not bind the Commission here. Prior rate proceedings or the particular findings therein are not res judicata of
(2) The fact that the Commission applied the remainder life theory and allowed Duquesne to amortize an alleged deficiency in the book reserve in the 1951 proceeding does not, by any logic or reason, require this Court to direct the Commission to apply such remainder life theory here. In the 1951 proceeding the Commission applied the remainder life theory and we affirmed such action. Pittsburgh v. Pennsylvania Public Utility Commission,
(4) For like reasons, we are not concerned, as the majority assumes, with questions of fairness, prejudice, estoppel, or change in Commission policy. The Commission’s refusal to continue to accept at face value self-serving book entries of a utility would not be a prejudicial change of policy.
The majority directs the Commission to make adjustment for a wage increase, not in the record, since the Commission made an adjustment to reflect the elimination of the excess profits tax. Admittedly, the Commission should consider the latest available relevant evidence in computing expenses and income, but, at the same time, it is given discretion as to what adjustments shall be made to base year figures. Duquesne Light Co. v. Pennsylvania Public Utility Commission,
The majority opinion affirms the Commission in directing modification of the fuel clause. However, throughout the majority opinion language is used which treats this order of the Commission modifying the fuel clause as making a reduction in basic rates or revenues therefrom. Under the principles announced in Magee Carpet Co. v. Pennsylvania Public Utility Commission,
“Broadly speaking, depreciation is the loss, not restored by current maintenance, which is due to all the factors causing the ultimate retirement of the property.” Lindheimer v. Illinois Bell Telephone Co.,
The Commission in its brief (pp. 77-83) gives a convincing illustration of tbe inequitable results from tbe application of tbe remainder life theory solely on tbe mere presence of a deficiency or an excess in a utility’s book reserve for depreciation.
In Harrisburg Steel Corporation v. Pennsylvania Public Utility Commission,
In Pennsylvania Public Utility Commission v. Equitable Gas Co., C. 15581, August 11, 1953, the Commission refused to amortize an excess in book reserve by decreasing the depreciation expense allowance.