449 Pa. 573 | Pa. | 1972
Lead Opinion
Opinion By
On October 25, 1966, the Borough of Monroeville [Borough] enacted Ordinance No. 557, which created an underground wire district pursuant to Sections 2301 through 2305 of the Pennsylvania Borough Code.
Appellants, Duquesne Light Company [Duquesne], Bell Telephone Company [Bell] and the American Telegraph and Telephone Company [A. T. & T.], all maintain overhead wire facilities within the district. After passage of the ordinance in 1966, the appellants were notified by the Borough that they had approximately three years and two months to remove their overhead wires and supporting poles and relocate their facilities, either in the rear of the serviced properties or underground. The time limit was set so that the relocation of the wires could coincide with a proposed widening of the William Penn Highway by the Pennsylvana Department of Highways.
Duquesne filed an appeal with the Allegheny County Quarter Sessions Court within the thirty-day statutory appeal period. However, by mutual consent, no further activity regarding this appeal was taken by
The numerous specific assignments of error which the several appellants have presented for our consideration resolve themselves into the basic question whether the Borough of Monroeville appropriately applied Section 2301 of the Borough Code in enacting an ordinance prohibiting the introduction of new overhead wires, cables and supporting poles and requiring the removal of existing overhead facilities by relocating or under-grounding, or whether the power to compel the under-grounding of electric wires is preempted by the Public Utility Code.
We have recognized that the Legislature enacted the Public Utility Code and created the PUC for the express purpose of standardizing the construction, operations and services of public utilities throughout Pennsylvania, Chester County v. Philadelphia Electric Co., 420 Pa. 422, 218 A. 2d 331 (1966). Had the Borough
When faced with an apparent conflict between statutes, our primary concern is to determine, if possible, the intent of the legislature. Act of May 28, 1937, P. L. 1010, art. IV, §51 (46 P.S. §551).
The precursor of Section 2301 of the Borough Code in its earliest form predates the Public Utility law by approximately ten years. The Act of April 28, 1903, P. L. 335, granted boroughs the power to define underground wire districts and to regulate the use of underground conduits. This language was re-enacted in the Act of June 12, 1913, P. L. 488, which also extended the Borough’s power to include telephone and telegraph companies. In that same year the legislature enacted the Public Service Company Law
The relevance of this historical exposition is that the specific language of Article XXIII of the Borough Code has been re-enacted four times since the original Public Service Company Law and twice since the Public Utility Law of 1937. We do not see how this continuum reflects an intent on the part of the Legislature to impliedly repeal Article XXIII.
The determination that §2301 has not been preempted by the Public Utility Code comports with our established principle of construing two apparently conflicting statutes to give effect, if possible, to both. Act of May 28, 1937, P. L. 1019, art. IV, 46 P.S. §563. To harmonize Section 2301 of the Borough Code with the Public Utility Code, the Borough Code must be read so that, although the borough may define reasonable underground wiring districts, the Public Utility Commission has the ultimate authority to determine the particulars of implementation, including timing, feasibility and cost of the project. This statutory construction is supported by the enactment of Borough Code Section 3501:
“nothing in this Act shall be construed to repeal: * * * *
“(2) Any of the provisions of the Public Utility Law.”
In the absence of Public Utility Code provisions on the subject, we would be inclined to hold that the six
That the General Assembly in enacting the Borough Code intended it to be applied harmoniously with the Public Utility Law is evidenced by Lansdale Borough v. Philadelphia Electric Co., 403 Pa. 647, 170 A. 2d 565 (1961), where this Court was called upon to construe another provision of the Borough Code.
That the Public Utility Commission is the appropriate forum for the adjudication of rates, services and facilities of public utilities within the Commonwealth was recognized in Duquesne Light Co. v. Upper St. Clair, 377 Pa. 323, 105 A. 2d 287 (1954) : “It is clear that the proposed transmission line is necessary for the rendition of efficent service to the public and that that necessity transcends the legitimate objectives of any one of the political subdivisions of the Commonwealth. We believe this is the reason why the General Assembly entrusted the regulation of public utilities to a commission of state-wide jurisdiction. Local authorities not only are ill-equipped to comprehend the needs of the public beyond their jurisdiction, but, and equally important, those authorities, if they had the power to regulate, necessarily would exercise that power with an eye toward the local situation and not with the best interest of the public at large. . . .” Id. at 335-36, 105 A. 2d at 293. State-wide public welfare dictates that the
Decrees reversed and remanded for further proceedings consistent with this opinion. Each party shall pay its own costs.
The former Mr. Chief Justice Bell and the late Mr. Justice Cohen took no part in the decision of this case.
The ordinance in question was enacted pursuant to the Borough Code of 1947 (Act of May 4, 1927, P. L. 519, art. XXIII, §301, as amended, Act of July 10, 1947, P. L. 1621, §66), which has since been superseded by The Borough Code of 1966 (Act of February 1,
Prior to oral argument before tbis Court, we allowed Pennsylvania Power and Light Company [P. P. & L.] to intervene as amicus curiae.
The Court’s determination here that the Borough Code may not be relied upon to justify the Borough ordinance to the exclusion of Public Utility Commission approval obviates the necessity to pass upon the questions of Whether the ordinance comports with the statutory requirement of reasonableness and whether the en
Article XXIII is labeled “Underground Conduits” in the 1966 re-enactment.
Act of May 28, 1937, P. L. 1053, art. I, §1 et seq., 66 P.S. §1101 et seq.
Appellants cite Sections 401, 412 413, 420, 507, 905, 906, 908, 1001, 1008 and 1009 (66 P.S. §§1172, 1182, 1183, 1190, 1217, 1345, 1346, 1348, 1391, 1398 and 1399 respectively).
Act of July 26, 1913, P. L. 1374.
Act of May 4, 1927, P. L. 519.
Of., footnote 1 of this opinion.
Act of February 1, 1966, P. Ij. (1965) 1656.
Act of May 28, 1937, P. Ii. 1053.
The Borough, was seeking to exercise its express authority-under the Act of May 4, 1927, P. L. 519, as aménded, 53 P.S. §47471, to sell electricity in areas annexed by it.
Concurrence Opinion
Concurring Opinion by
I join in the Court’s opinion with the understanding that “implementation” by the Public Utility Commission of the Borough’s defined reasonable underground wiring district means that the Public Utility Commission has the initial and exclusive authority to first determine, as it does in any other public utility regulatory matter, whether the Borough’s defined district should become operative. Once the Public Utility Commission has affirmatively decided to implement the Borough’s underground wiring district, the Commission then additionally assumes exclusive control over the physical details of the project, such as timing, rates, service and construction.
The Court’s adoption of the language in Lansdale Borough v. Philadelphia Electric Co., 403 Pa. 647, 170 A. 2d 565 (1961), leads inescapably to the requirement of Public Utility Commission approval: “Although the Borough is armed with the provisions of the Borough Code, it can only effectuate its purpose by initially proceeding before the P.U.C. . . .” Id. at 651, 170 A. 2d at 567.
Duquesne Light in its brief at page 26, and at oral argument, asserted that the costs of- the proposed Monroeville under-grounding project would exceed $400,000 per mile, with the project extending approximately two and one-half miles. Further, appellant Bell, in its brief, at page 9, alleges that its costs, based on 1967 undergrounding estimates, will be approximately $275,000.