Lаfarge Corporation and the city of Sugar Creek, Missouri, executed a lease agreement in October 1998. Lafarge eon- *427 tracted with Dunn Industrial Group, Inc. (DIG) for the design and construction of a new cement plant, known as the Sugar Creek II Cement Plant. Lafarge and DIG agreed to design and build the cement plant. Dunn Industries, Inc. (Dunn), DIG’s parent company, signed a contract guaranty guaranteeing DIG’s performance of its obligations under the construction contract with Lafarge. The construction contract between Lafarge and DIG contained an arbitration clause. The parties agreed to an October 4, 2000, change order.
Disputes arose, and litigation followed. In March 2001, DIG filed three separаte mechanic’s lien claims against the property. Shortly thereafter, DIG filed its petition against Lafarge and the city of Sugar Creek, which included counts to foreclose its mechanic’s hen claims. Kansas City Electrical Supply Company then filed an equitable mechanic’s hen action in Jackson County Circuit Court concerning the same property on June 4. Upon a joint motion by the parties, the trial court properly consolidated the case filed by DIG with the equitable mechanic’s hen action under section 429.300. 2 Lafarge sought arbitration and filed a motion to stay htigation and compel arbitration. Dunn and DIG sought to stay arbitration. The trial court overruled Lafarge’s motion to compel аrbitration, sustained Dunn and DIG’s joint motion to stay arbitration, and overruled Lafarge’s motion to stay htigation.
The appeal of that portion of the judgment overruling the motion to stay htigation is dismissed as moot. Otherwise, the judgment is affirmed in part and reversed in part, and the case is remanded.
Jurisdiction to Appeal Orders Denying or Staying Arbitration
Lafarge appeals the trial court’s judgment denying its motion to compel arbitration and granting Dunn and DIG’s joint motion to stay arbitration. It also appeals the trial court’s overruling of its motion to stay htigation.
The right to appeal is purely statutory, and where a statute does not give a right to appeal, no right exists.
Farinella v. Croft,
Arbitrability of Claims Raised in DIG’s Petition Against Lafarge
Lafarge claims that the trial court erred in denying its motion to compel arbitration because: (1) ah of the disputes and claims asserted by DIG fall within the scope of the broad, mandatory arbitration provision of the construction contract; (2) the parties’ October change order did not modify, rescind, or otherwise change the arbitration provision of the construction contract; and (3) enforcement of the arbitration provision is not barred by Missouri’s equitable mechanic’s lien statutes.
Arbitration Provision of Construction Contract
The Federal Arbitration Act (FAA) evinces a liberal pohcy favoring arbitration agreements so that disputes might be resolved without resort to the courts.
Greenwood v. Sheffield,
The usual rules and canons of contract interpretation govern the subsistence and validity of an arbitration clause.
Village of Cairo v. Bodine Contracting Co.,
In construing arbitration clauses, courts have categorized such clauses as “broad” or “narrow.”
McCarney v. Nearing, Stoats, Prelogar & Jones,
The June 1999 construction contract between Lafarge and DIG contained a broad arbitration clause:
Any controversy or claim arising out of or relating to this contract, or the breach thereof, shall be settled by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association, and judgment upon the award rendered by the arbitrator(s) may be entered in any court having jurisdiction thereof.
All of the claims in DIG’s petition arise out of or relate to the construction contract. The counts involve allegations of extra work or additions or changes to DIG’s scope of work under the construction contract. The underlying claims sought to be enforced by mechanic’s lien also arise out of the parties’ construction contract. Resolution of DIG’s claims requires an examination of Lafarge and DIG’s respective obligations and performance under the construction contract. DIG’s claims against Lafarge fall within the substantive scope of the parties’ arbitration agrеement.
October Change Order
DIG concedes that the original construction contract between it and La-farge contained an arbitration agreement. The parties dispute the effect of the October 2000 change order.
The cardinal principle of contract interpretation is to ascertain the intention of the parties and to give effect to that intent.
Butler v. Mitchell-Hugeback, Inc.,
A contract is ambiguous only if its terms are susceptible to fair and honest differences.
Helterbrand,
The October change order incorporated all terms and conditions of the June 1999 construction contract to the extent those terms did not conflict with terms of the change order. Paragraph III.D. of the change order also provided:
Lafarge and DIG agree to first attempt to resolve the items marked on the PCO List by negotiation; however, either party, at any time, may resort to their respective contract remedies or remedies as provided by law.
DIG claims that the provision permitting a party to pursue its “remedies as provided by law” permits a party to proceed with a civil action in a court of law, thereby modifying or partially rescinding the arbitratiоn provision in the original construction contract.
Mutual rescission of a contract must be clear, positive, unequivocal, and decisive, and it must manifest the parties’ actual intent to abandon contract rights.
AAA Uniform and Linen Supply, Inc. v. Barefoot, Inc.,
Paragraph III.D. of the October change order is not ambiguous and can be interpreted consistently with the broad mandatory arbitration provision of the original construction contract. The “contract remedies” clause requires Lafarge or DIG to submit any controversy or claim arising out of or relating to the construction contract to arbitration. The “remedies as provided by law” clause indicates that the parties reserve other unspecified rights or remedies that do not nullify or are not inconsistent with their obligation to arbitrate.
See, e.g., Dickson County v. Bomar Constr. Co.,
If DIG’s interpretation were adopted, the “remedies at law” clause would be given effect, but the “contract remedies” or arbitration clause would fail. The compulsory nature of the broad arbitration provision of the construction contract would be rendered ineffective at the option of either party. Such interpretation would be contrary to the principles that a contrаct should be construed as a whole, that all provisions should be harmonized if possible, and that a construction that would render a provision meaningless should be avoided. It would also conflict with the principle that doubts as to arbitrability should be resolved in favor of coverage.
*430 Under the broad arbitration clause of the construction contract, Lafarge and DIG manifested their intent that all disputes arising under the contract would be submitted to arbitration. Paragraph III.D. of the October change order does not clearly, positively, unequivocally, or decisively state that the right and obligation to arbitrate was modified, limited, or rescinded. The provision, and particularly the clause “remedies аs provided by law,” does not expressly exclude the marked change orders from arbitration. The paragraph does not give the parties an option to proceed under the contract or by remedies available under the law. Instead, it preserves the parties’ agreement to arbitrate and other unspecified rights or remedies that are not inconsistent with that obligation.
Equitable Mechanic’s Lien Action
Finally, Lafarge claims that the trial court erred in denying its motion to compel arbitration because Missouri’s equitable lien statutes do not bar enforcement of the arbitration provision.
Sections 429.270 to 429.340 govern the enforcement and adjudication of the rights of multiple lienholders in an equitable action.
McCarney,
[A]h other suits that may have been brought on any mechanic’s hen claim or demand shah be stayed and no further prosecuted, and the parties in any such other suit shall be made parties to such equitable action as in the foregoing sections provided.... After the institution of such equitable action no separate suit shall be brought upon any mechanic’s hen or claim against said property, or any of it, but the rights of all persons shah be adjusted, adjudicated and enforced in such equitable suit.
Thus, once an equitable mechanic’s hen action is brought, it is the exclusive method of htigating hens and other claims pertaining to particular property.
Meiners Co. v. Clayton Greens Nursing Ctr.,
The trial court erred in denying La-farge’s motion to compel arbitratiоn between Lafarge and DIG. That part of the trial court’s judgment is, therefore, reversed, and the case is remanded to the trial court to compel arbitration of those claims.
Arbitrability of Claims Raised by Lafarge in Its Demand for Arbitration
Lafarge contends that the trial court erred in granting Dunn and DIG’s joint motion to stay arbitration because: (1) its claims against both DIG and Dunn fall within the scope of the arbitration agreement of the construction contract, and (2) the written guaranty executed by Dunn inures to the benefit of Lafarge and incorporated the construction contract and arbitration agreement.
In Lafarge’s demand for arbitration, it claimed damages for DIG’s failure to timely complete the construсtion contract and for failure to properly perform and coordinate the construction work. Lafarge sought similar damages from Dunn as guarantor of the construction contract. Thereafter, DIG and Dunn filed a joint motion to stay arbitration, which was eventually granted by the trial court.
Claims Against DIG
Lafarge contends that its claims against DIG in its demand for arbitration fall within the scope of the parties’ arbitration agreement and, therefore, must be arbitrated. As discussed previously, the June 1999 construction contract contained a broad arbitration provision that mandated arbitration of “[a]ny controversy or claim arising out of or relating to [the] contract.” Clearly, Lafarge’s claim for damages agаinst DIG for DIG’s “failure to timely complete” the construction contract and for its “failure to properly perform and coordinate the construction work” arise out of or relate to the construction contract. Lafarge’s claims against DIG fall within the substantive scope of the parties’ arbitration agreement.
Once again, DIG asserts that the October change order “freed [it] from its obligation to arbitrate.” The October change order does not modify or rescind the arbitration provision in the construction contract but preserves the parties’ agreement to arbitrate as well as other unspecified rights or remedies that are not inconsistent "with that obligation.
Finally, DIG asserts that since Lafarge’s claims against it are compulsory counterclaims to its claims against Lafarge that were properly raised in the equitable mechanic’s hen action in the circuit court proceedings, the trial court’s judgment staying the arbitration proceedings was correct. Missouri has a compulsory counterclaim rule that compels a party to state any claim it has against its adversary that arises out of the transaction or occurrence that is the subject matter of the suit.
Rule 55.32(a); Evergreen Nat’l Corp. v. Killian Constr. Co.,
The preclusion effect of the compulsory counterclaim rule, however, is subject to contractual adjustment by the parties.
Publicis Communication v. True N. Communications Inc.,
In this case, Lafarge and DIG agreed that any dispute arising out of the construction contract shall be settled by arbitration. DIG cannot now seek to bаr arbitration of Lafarge’s claims against it because those claims were not presented as compulsory counterclaims in its suit against Lafarge in circuit court, which, as previously discussed, was itself subject to arbitration.
See also Sokkia Credit Corp. v. Bush,
The trial court erred in staying arbitration of Lafarge’s claims against DIG. That part of the judgment is, therefore, reversed, and the case is remanded to the trial court to enter an order compelling arbitration of Lafarge’s claims against DIG.
Motion to Stay Litigation
The trial court also overruled La-farge’s motion to stay litigation pending arbitration. Lafarge argues that this ruling is appealable under The Missouri Uniform Arbitration Act and under the FAA. It further argues that, because its claims are subject to arbitration, thosе acts require the court to stay the litigation pending arbitration.
As discussed above, Missouri’s Uniform Arbitration Act expressly permits an appeal from judgments relating to arbitration. It does not expressly provide for a right of appeal from an order denying a motion to stay litigation pending arbitration.
Sec. 435.440.
But, Lafarge argues, the FAA applies to transactions involving commerce. Section 2 of the FAA creates federal substantive rights that must be enforced by the state courts.
Moses H. Cone Hospital v. Mercury Const. Corp.,
Dunn and DIG counter by noting that the cited Missouri cases assume rather than decide this issue and do not closely analyze the language of section 3 of the *433 FAA, which they say provides for an appeal only of actions filed in federal court. Section 3 of the FAA provides:
If any suit or proceeding be brought in any of the courts of the United States upon any issue referable to arbitration under an agreement in writing for such arbitration, the court in which such suit is pending, upon being satisfied that the issue involved in such suit or proceeding is referable to arbitration under such agreement, shall on application of one of the parties stay the trial of the action until such arbitration has been had in accordance with the terms of the agreement, providing the applicant for the stay is not in default in proceeding with such arbitration.
9 U.S.C. sec. 3 (1999).
In support, Dunn and DIG cite
Volt Information Sciences, Inc. v. Bd. of Trustees of Leland Stanford Junior Univ.,
This Court also finds it unnecessary to resolve this issue on the facts of this case. Lafarge’s argument is that the trial court was obligated to stay the litigation because it was obligated to grant the motion compel arbitration. Since the trial court overruled the motion to compel arbitration, the motion to stay litigation effectively became moot.
This Court has reversed the determination of the trial court not to compel arbitration and has remanded with directions to grant the motion to compel arbitration. Although section 435.440 does not provide for appeal of denial of a motion to stay litigation, by its terms section 435.355.4 states in pertinent part:
4. Any action or proceeding involving an issue subject to arbitration shall be stayed if an order for arbitration or an application therefor has been made under this sectiоn or, if the issue is severa-ble, the stay may be with respect thereto only. When the application is made in such action or proceeding, the order for arbitration shall include such stay.
Sec. I35.355.Jp
(emphasis added). On remand, the trial court will comply with all relevant statutory provisions, including section 435.355.4. Unless and until it fails to do so, there is no basis to request relief from the appellate courts.
Cf. State ex rel. PaineWebber v. Voorhees,
Claims Against Dunn
Next, Lafarge contends that its claims against Dunn in its demand for arbitration require arbitration. Dunn claims that La-farge is not the obligee under the plain terms of the guaranty and, therefore, cannot invoke the guaranty’s рrovisions. It also claims that it has no agreement to arbitrate any dispute with Lafarge because the guaranty does not incorporate the arbitration provision in the construction contract.
Lafarge as the Obligee Under the Guaranty
Dunn’s contract guaranty guarantees DIG’s prompt and satisfactory performance of the construction contract between Lafarge and DIG. If DIG defaulted on the construction contract’s performance, Dunn had the option to complete the work of the contract or to pay to obligee *434 all damages, costs, and expenses that the obligee is entitled to recover from DIG by reason of the default. The guaranty names as the obligee Lafarge Canada, Inc., a wholly controlled subsidiary of La-farge.
A guaranty, a species of contract, is a collateral agreement for another’s undertaking and is an independent contract that imposes responsibilities different from those imposed in the agreement to which it is collateral.
Jamieson-Chippewa Inv. Co., v. McClintock,
A guaranty agreement may be construed together with any contemporaneously executed agreements dealing with the same subject matter as an aid in ascertaining the intention of the parties.
McClintock,
Guaranties are divided into two types — general and special.
Gateway Frontier Properties, Inc. v. Selner, Glaser, Komen, Berger & Galganski, P.C.,
In this case, Lafarge, not Lafarge Canada, was intended by the parties to be the obligee of the contract guaranty. Lafarge Canada is a wholly controlled subsidiary of Lafarge and is extensively involved in and responsible for the managеment of the construction project on behalf of Lafarge. The guaranty itself demonstrates that La-farge was the entity the guaranty was intended to benefit. The guaranty explains that the obligee “has executed a Contract” with DIG for construction work at the Sugar Creek plant project. The contract for the design and construction of the cement plant, which was attached to
*435
and was specifically referenced throughout the guaranty, was executed between DIG and Lafarge — not Lafarge Canada. The notation “Lafarge Corporation c/o Lafarge Canada-CTS” is typed at the top of every page of the construction contract. Throughout the guaranty, refеrence is made to Dunn’s guarantee of DIG’s obligations to the obligee under the construction contract. The construction contract between Lafarge and DIG and the guaranty agreement were executed contemporaneously and concern the same subject matter. Construing the agreements together, Dunn’s obligations under the guaranty were intended to run to the party with whom DIG contracted for the construction of the cement plant — Lafarge, not Lafarge Canada. Nothing in the guaranty excludes Lafarge as a party.
Cf. Rush Presbyterian St. Luke’s Med. Ctr. v. Safeco Ins. Co.,
Lafarge may enforce its rights under the guaranty.
Whether Arbitration Provision was Incorporated into Dunn’s Guaranty
Dunn next contends that it has no agreement to arbitrate any disputе with Lafarge because it, as guarantor, is not a signatory to a contract containing an arbitration agreement and the guaranty does not incorporate the arbitration provision of the construction contract between Lafarge and DIG.
Arbitration is a matter of contract, and a party cannot be required to arbitrate a dispute that it has not agreed to arbitrate.
AgGrow Oils, L.L.C. v. Nat’l Union Fire Ins. Co. of Pittsburgh, PA,
The instant case is distinguishable from
Jim Carlson Construction, Metro Demoli
*436
tion,
and
Sheffield.
In those cases, documents containing arbitration provisions were specifically incorporated by reference into other contracts. In this case, Dunn’s guaranty refers to the construction contract between Lafarge and DIG, and the contract is attached to the guaranty. The guaranty also provides that Dunn “guarantees prompt and satisfactory performance of the attached Contract in accordance with all its terms and conditions.” The guaranty does not, however, incorporatе by reference the construction contract. Mere reference to the construction contract in the guaranty is insufficient to establish that Dunn bound itself to the arbitration provision of the construction contract.
See Grundstad,
Estoppel
Lafarge claims that Dunn should be es-topped from avoiding its obligation to arbitrate because its claims against Dunn under the guaranty are inextricably intertwined with its claims against DIG under the construction contract and because Dunn has previously sought the benefit of other provisions of the construction contract.
Lafarge cites two cases,
J.J. Ryan & Sons, Inc. v. Rhone Poulenc Textile, S.A.,
Furthermore, the cases cited by Lafarge involved claims that were integrally related to the contract containing the arbitration provision.
J.J. Ryan & Sons,
Finally, Lafarge argues that Dunn should be estopped from avoiding its obligation to arbitrate because Dunn has previously sought the benefit of other provisions of the construction contract. By accepting benefits, a party may be es-topped from questioning the existence, validity, and effect of a contract.
Dubail v. Medical West Building Corp.,
Lafarge’s reliance on Dubail and its general estoppel rule is misplaced. In that case, the defendant corporation undoubtedly received and accepted benefits of the contract. It not only accepted the legal services and advancements of the attorney, but it also pleaded in a separate lawsuit the provision in the contract whereby the attorney agreed to hold it harmless against any claims made by the other corporation. Id. In this case, however, it cannot be said that Dunn has accepted the benefits of the construction contract between Lafarge and DIG. Lafarge argues that Dunn accepted the benefits of the construction contract when, after it notified Dunn of DIG’s default under the construction contract, Dunn sought to avoid its responsibilities to Lafarge by citing a provision of the October change order, which is part of the construction contract. The provision in the change order cited by Dunn purportedly limits Lafarge’s damages against DIG if DIG fails to complete a specific aspect of the construction contract on or before a particular date. The provision is a possible defense of DIG’s against a claim by Lafarge. Dunn’s citation of the provision in response to Lafarge’s notification of DIG’s default was, therefore, not inconsistent with its argument that the arbitration provisiоn of the construction contract does not apply to its guaranty because it was never incorporated by reference into the guaranty. Thus, Dubail’s estoppel principle does not apply in this case.
Dunn did not agree to arbitrate its liability as guarantor. The trial court did not err in staying Lafarge’s arbitration against Dunn. That part of the trial court’s judgment is affirmed.
The appeal is dismissed in part as moot; the judgment of the trial court is otherwise affirmed in part and reversed in part; and the case is remanded.
Notes
. This Court transferred this case after an opinion by the Court of Appeals, Western District, authored by the Honorable Robert G. Ulrich. Mo. Const, article V, section 10. Portions of the court of appeals opinion are incorporated without further attribution.
. All statutory references are to RSMo 2000 unless otherwise indicated.
. Dunn and DIG contend that McCamey did not determine the effect of the statutory equitable mechanic's lien provisions on a contractual agreement to arbitrate because no equitable mechanic’s lien action had been filed in that case at the time the motion to compel arbitration and the motion to stay arbitration were considered. While an equitable mechanic’s lien action had not been filed in the case, the owner argued on appeal that the claims asserted by the architect and the contractor in their mechanic’s liens and arbitration demands must be adjudicated in one equitable mechanic’s lien proceeding. The court determined that issuе, and the holding is, therefore, applicable in this case.
.
See, e.g., Getz Recycling, Inc. v. Watts,
. In Missouri, matters incorporated into a contract by reference are as much a part of the contract as if they had been set out in the contract in haec verba.
Metro Demolition & Excavating Co. v. H.B.D. Contracting, Inc.,
. Whether Dunn is ultimately bound by the results of the arbitration between Lafarge and DIG is not addressed in this opinion.
