38 Iowa 281 | Iowa | 1874
— The judgment of the Circuit Court was rendered upon the following facts, which are disclosed by the record before us.
“ Resolved, That it is hereby ordered that the public square be graded and put in a proper condition; the grade tobe made subject to the approval of the City Council.” The Council and Mayor, with the plaintiff, inspected the ground at the time and agreed upon the work to be done, which was at once commenced, and prosecuted under direction of. one of the Council,
It is not denied that the city possesses the power to improve the public square in the manner it was done, under the arrangement with plaintiff, nor that the agreement with him, whereby he advanced the money and took warrants, exceeds its authority. No question of this kind is presented in the case. The defense made by the city is based upon the position that plaintiff’s contract with the city is to be controlled by the resolution last adopted, and as his claim exceeds the limit of expenditure therein prescribed, he cannot recover.
It is insisted that the first resolution is not a contract; that •the contract made with plaintiff was verbal and not adopted in the manner provided in Rev., § 1134 This statement 'may be admitted in as broad a sense as it is made. But the resolution was an expression of the will of the city that the work contemplated be done, and a sufficient authority for its .officers and committeemen to undertake its performance. It .was intended to direct the commencement and completion of the work, and was ample authority for a verbal contract -between those charged with such duty, and plaintiff, or others, who should be employed to make the improvement. It differs in effect from the second resolution only in the matter of the limitation. Neither are to be regarded as contracts with the parties doing the work, both confer authority for the making .of such contracts.
In the absence of evidence establishing an express agreement, there is no difficulty in finding facts upon which the law will imply a contract on the part of the city to repay plaintiff for his outlay. As we have seen, the first resolution authorized the work to be done by the city officers. Any contract made by them with workmen, within the scope of their authority, was binding upon the city. ' A payment to the workmen by plaintiff with the consent of the city officers, the law will esteem a payment upon request of the city, and will imply a promise by the city to reimburse plaintiff.
We have held that a municipal corporation may contract by parol, through its agents, and that Eev. § 1134, does not take away this power. The City of Indianola v. Jones, 29 Iowa, 282. And it is plain that, in proper cases, the law implies contracts binding xxpon such corporations. See Dillon’s Municipal Corporations, §§ 383, 384,.750,.751, and authorities cited. The defendant, having authorized', the work, by the first resolution, which plaintiff paid for,- ought, ex equo et bono, tó reimburse him, and the law will .imply a- contract on its part to that effect.
It may be remarked that it is not pretended that the money paid by plaintiff was improperly-applied, or that the work was not done to the approval and satisfaction of the city government.
It is needless to add that the subsequent resolution limiting the expenditure for the improvement could not affect plaintiff’s rights arising under the priox-aetionof.the City-Council. Corporations, no moi’e than natnx’al pex’sons,, can change their contracts withoxxt the assent of the parties to be affected thereby-.
In our opinion the judgment of the Cix'cuit Coux’t is in conflict with the law; it is therefore
Ee VERSED.