delivered the opinion of the court:
Dеfendant and counterplaintiff Lauretta Cannon (Defendant) appeals from the judgment of the circuit court in favor of plaintiff and counterdefendant (Plaintiff) in the amount of $9,600, which represents the unpaid contract price of $1,900 for work performed and $7,700 for “extra” work. Defendant raises three issues on appeal: (1) whether plaintiff was entitled to additional payment for alleged extra work; (2) whеther plaintiff’s failure to file plans pursuant to the Chicago Building Code (Ordinance) precludes him from recovering for extra work; and (3) whether the circuit court erred in denying defendant’s request for a continuance.
The record reveals that defendant owns a three-flat apartment building in Chicago. In March 1986 defendant entered into a contract with plaintiff to modify the single
Shortly thereafter, the parties entered into a second contract which modified their original agreement and stated:
“Building is a 3-flat building. Boiler is now heating the entire building. Present boiler will be cut down and only used for 1st floor and present radiators. Other 2 floors will be heated with 260,000 BTU boilers steam with lo-cut offs and automatiс water feeders. Use present radiators and hook up all three boilers to separate gas meters. 3 gas meter connections. Price includes all labor and material and work to be done in a workmanlike manner.”
The contract amount was listed as $7,000, “one half xk down payment on delivery — balance to be paid on completion.”
After the work was completed, plaintiff brought this cause of action. Defendant asserted a number of affirmative defenses and filed a counterclaim alleging that plaintiff had performed faulty work.
On August 29, 1988, the case was set final for trial. However, on that date defense counsel presented an oral motion for a continuance on the ground that defendant’s expert witness was suddenly and unexpectedly unavailable. The trial court denied defendant’s motion and proceeded with trial. Following the trial, the court entered judgment on behalf of plaintiff on counts I and II of his complaint and judgment for the defendant on her counterclaim in the amount of $450.
We first address defendant’s argument that because the work in question was required by the original contract it could not be considered as extra work. In order for a contractor to recover additional рayment from an owner for extra work, he must establish by clear and convincing evidence each of the essential elements in his case. He must establish that: (1) the work was outside the scope of the original contract; (2) the extra items were ordered at the direction of the owner; (3) the owner agreed either expressly or impliedly to pay extra; (4) the extra items were not voluntarily furnished by the contractor; and (5) the extra items were not rendered necessary by any fault of the contractor. (Watson Lumber Co. v. Guennewig (1967),
Defendant argues that plaintiff failed to establish by clear and convincing evidence that the work in question was extra. She urges that the trial' court’s judgment for plaintiff was against the manifest weight of the evidence.
It is well established that “clear and convincing evidence is considered to be more than a preponderance while not quite approaching the degree of proof necessary to convict a рerson of a criminal offense.” (In re Estate of Ragen (1979),
At the trial below, 1 four witnesses testified. Plaintiff testified, inter alia, that the extra work included installation of 12 new steam pipe lines, which were run from the new boilers in the basement to 12 radiators in the second- and third-floor apartments, and work on the walls and floors of the premises to accommodate the lines; defendant orally requested the new steam lines and promised to pay for them; the work was outside the scope of the contract since it was always his intent to use the existing pipe lines to hook up the boilers to the radiators; he did not submit plans to the city because he did not believe the Ordinance applied to the job; and the boiler installation was subcontracted out to a third party.
Mr. Poulas, an expert witness for plaintiff, testified that he was not a licensed plumber but had been in the heating business in the Chicago area for over 35 yeаrs. He stated “that he did not know how many lines were run from the basement to the *** floors” but, “individual lines were run from the basement to the radiators in the second and third floor apartments.” However, Mr. Poulas offered no other testimony to establish that the work was extra, and what he did testify to was based on his visit to the second floor only.
Defendant testified on her counterclaim as to the faulty work provided by plaintiff as well as the case in chief. The record reflects that defendant testified that “other than the boiler change for which she agreed to pay an extra $1,000, she never requested that any extra work be done by plaintiff.” She conceded that “individual lines were run from the basement to the radiators on the second floor” but denied requesting this “configuration as an extra.” Defendant further stated that she considered the running of pipes from each boiler to the floor that boiler was to heat as incidental and necessary to the work required under the written contract, and that the configuration proposed by plaintiff, i.e., connecting the existing pipe lines in the basement to the new boilers and then through the original boiler, which already had pipe lines extending from the basement to the individual floors, would not give rise to separate heating systems and hence separate billings.
Mr. Cannon, husband of defendant, corroborated her testimony when he testified “that [although] individual lines were run from the basement to the second floor through his apartment (on the first floor), no lines were run from the basement to the third floor.” When asked on cross-examination “how does heat get to the third floor apartment if there are no pipеs from the basement to the third floor radiators[?]” Mr. Cannon replied “that the new boiler for the third floor was connected to the original boiler by piping in the basement, and the heat was sent to the third floor through the original pipes in the old heating system.”
As noted previously, the law in Illinois applicable to the subject of extras is specifically enunciated. (Watson Lumber Co. v. Mouser (1975),
Plaintiff further argues that he presented some evidence on each element, and consequently, we are to disregard the fact that defendant presented conflicting evidence on the ground that as a reviewing court we must accept the finding of the trier of fact. It is well established that where the evidence presented is conflicting, it is the duty of the trial court to listen to the testimony of the witnesses and resolve any conflicts therein on the grounds that credibility of witnesses and the weight to be given to conflicting evidence are solely matters for the trier of fact. (In re Marriage of Ligas (1982),
In the case at bar, while it is arguable that the contradictory evidence presented goes to the matter of the credibility of the witnesses, we find that the evidence presented as to the first element, whether the work was outside the scope of the original contract between the parties or necessary to the contract, is controlling. Labor and materials which are incidental and necessary to the execution of the contract generally cannot be regarded as extra work for which a contractor or builder may recover. 17A C.J.S. Contracts §371(6), at 412 (1963). Mayer Paving & Asphalt Co. v. Carl A. Morse, Inc. (1977),
Furthermore, the only evidence before the trial court was allegations of general discussions between the parties. However, it is well settled that the burden of establishing these matters is the plaintiffs burden, and evidence of general discussion will not supply all of these elements. (Guennewig,
Moreover, the determination of this issue was required to be resolved by mоre than mere assertions or denials by the parties. The trial court had an obligation to do more than weigh the testimony of the witnesses; rather, the court had a duty to consider the contract itself, and the intent of the parties at the time they entered into the contract. A contract must be enforced according to its terms. (Sweeting v. Campbell (1956),
We have scrutinized the contract here and determine that it is ambiguous in as much as it fails to specify the number of
Because the contract is ambiguous, it was incumbent upon the trial court to look to the intent of the parties at the time they entered into the contract. In this manner, the court could have properly determined whether the work was within the bounds of the contractual agreement or outside of the scope of the contract. However, the record is devoid of any indication of the trial сourt having made such an assessment. We have reviewed the contract and believe that the intent of the parties thereunder is clear, that intent being to produce three separate heating systems. The contract specifies that the “present boiler will be cut down” to heat the “1st floor” and that “the other 2 floors will be heated with steam boilers.” It clearly states that all three boilers will be hooked up to separate gas meters and provides for “3 gas meter connections.” Similarly, it states that “present radiators” will be used.
Conversely, neither the contract language, the actions of the parties, nor the testimony of plaintiff’s expert witness sheds any light on the technical issue of whether new pipe lines were necessary to the contract:
“In order to recover for items as ‘extras,’ they must be shown to be items not required to be furnished under plaintiff’s original promise as stated in the contract, including the items that the plans and specifications reasonably implied even though not mentioned. A promise to do or furnish that which the promisor is already bound to do or furnish, is not consideration for even an implied promise to pay additional for such performance or the furnishing of materials.” Guennewig,79 Ill. App. 2d at 391 .
Accordingly, we hold that on this record, it is manifestly against the weight of the evidence to find that the work was outside the scope of the original contract between the parties. As to the testimony presented by plaintiff, he offered no evidence of the specific time, place or nature of any discussions with, or conduct of, defendant involving installation of the 12 steam pipe lines. The evidеnce, to the contrary, discloses that plaintiff may not have used separate lines for the third floor at all. There was no expert testimony or authority presented to the court to explain how various plumbing configurations render different results. Yet, such specific evidence is required for the recovery of extras, particularly where, in addition, no bill or documentation of labor and materiаls provided for extra work is ever submitted.
It is the plaintiff’s burden to prove each and every element by clear and convincing evidence, which he has here failed to do. Thus, we conclude that the evidence presented by plaintiff is insufficient to sustain the judgment, and we reverse the trial court’s judgment and remand this matter for further proceedings not inconsistent with this opinion.
Furthermore, the contract here, which was drafted by plaintiff, provides that all extra work be in writing. The contract states in pertinent part: “Any alteration or deviation from specifications below involving extra costs will be executed only upon written orders, and will become an extra charge over and above the estimate.” However, there is no evidence of a written order. Plaintiff correctly asserts that oral modifications to written contracts are allowed. The rule is that a condition that all extra work be performed only upon written orders can be waived orally by the owner; but, before the contractor is entitled to compensation for extras, the waiver must be proved by clear and convincing evidence. See Atlee Electric Co. v. Johnson Construction Co. (1973),
Ordinarily, because of our disposition on the first issue, we would not consider the remaining issues. However, as the question regarding the applicability of the Ordinance may resurface on remand, we will briefly discuss it.
"We summarily conclude that defendant’s argument, which propоses that a party’s failure to strictly abide by the Ordinance, assuming it is applicable to the contract,
2
operates as a bar to recovery in a cause of action for extra work, is unsupported by law. See generally Abingdon Bank & Trust Co. v. Bulkeley (1945),
Assuming the Ordinance was applicable to the instant matter, we find the strikingly similar case of South Center Plumbing & Heating Supply Co. v. Charles (1968),
In the instant case, the Ordinance merely provides, inter alia, that the failure of the owner or agent to file plans and specifications with the Department and to obtain a permit therefrom for “installation” of any boiler or unfired pressure vessel subjects him or her to pay a “fine of twenty-five dollars for each day on which he shall have prosecuted such installation *** without said permit.” Chicago Building Code §17 — 2B.5 (1979).
Accordingly, we conclude that although a municipal ordinance which is applicable to the contract becomes by operation of law an implied term of the contract (Burns v. Regional Transportation Authority (1982),
For the foregoing reasons, the judgment of the circuit court of Cook County is affirmed in part; reversed in part and remanded for further proceedings consistent with the views expressed herein.
Affirmed in part; reversed in part and remanded.
CAMPBELL and O’CONNOR, JJ., concur.
Notes
The record on appeal does not contain a transcription of the trial proceedings that were held on August 29, 1988, since no court reporter was present on that day. However, pursuant to Supreme Court Rule 323(c) (107 Ill. 2d R. 323(c)), the trial judge certified a report of proceedings based upon the parties’ proposed report of proceedings, objections, answer and amended proposal.
Seetion 17 — 2B.1 of the City of Chicago Building Code provides in pertinent part that “[t]he provisions of this chapter [chapter 17] *** shall not apply to single dwellings nor to any multiple dwelling having not more than three apartments.” Chicago Building Code ch. 17, §17 — 2B.1 (1979).
