168 Iowa 129 | Iowa | 1914
Plaintiff and wife own the south half of the south half of a certain section of land in Webster county and defendant owns the north half of the same half-section. Prior to the time of the alleged contract in suit the two tracts of land had been to some extent drained by a joint or common system of tiling which had been constructed by the mutual agreement and at the mutual expense of the owners who were grantors of the parties to this suit. In this system were about 2,500 rods of drain of which 1,000 rods were upon the north tract and 1,500 rods on the south tract. The entire drainage was discharged through an outlet of large tile extending from or near the line between the two tracts southwesterly upon
Upon the issues thus joined there was trial to a jury and verdict for plaintiff for $146.35. Motion for new trial was overruled and from the judgment entered on the verdict defendant appeals.
The negative of this question is very vigorously asserted by counsel for appellant but the position is not well grounded. The plaintiff as a witness on the trial swears quite positively and definitely that the old outlet did not sufficiently discharge the surface waters from the land covered by the joint system of tiling and that a portion of his land and of the land of defendant was thereby flooded at times. He further swears that' he and defendant discussed the matter of putting in a new outlet and plaintiff mentioned to defendant the fact that one Stewart who had constructed the original system could be procured to put in an additional outlet provided he could have the job at once, and to this he says defendant responded, “If you will go ahead and put in that ditch and haul the tile I will pay my part and if we can’t agree you can pick a man and I will pick a man and let them settle it.” To this proposition plaintiff replied, “All right, that is good enough for me.” It is upon the strength of this agreement plaintiff claims to have done the work and incurred the expense. He further swears that the place or point from which the outlet should
That an alleged or attempted agreement may be void and unenforcible because of lack of definiteness and certainty will be readily admitted but this rule is to be applied with due regard to that other elementary principle of the law of contracts, cerium est qtiod cerium reddi potest, or, “that is certain which can be made certain.” The courts are daily enforcing contracts which require proof to make some of their obligations sufficiently certain to support a recovery. If A says to B, “Come, reap my field of wheat and I’ll pay you what is right” and B thereupon does the required work counsel would not for a moment contend there is in such transaction no enforcible
We have no quarrel whatever with the many cases cited upon this point by appellant for in our judgment they are in no wise inconsistent with our conclusion.
Whether defendant’s farm was in fact materially benefited by the additional outlet is a question of fact on which the witnesses are not agreed and this question also was properly submitted to the jury.
What may be their respective rights in this respect and whether plaintiff by enforcing the contract estops himself from denying defendant the right to make such connection we do not attempt to decide. As we understand the record there is such connection of the new outlet with the old system of tiling as to relieve the old outlet to a material extent and afford a more rapid and efficient removal of the surface water from both farms. This we think affords sufficient consideration for the alleged agreement and if it be thought to come within the statute of frauds the performance thereof by one party renders it enforeible against the other.
For the purposes of this case the appellant’s proposition of law may be conceded, but it in no manner affects the principal agreement by which plaintiff was authorized to proceed with the work and defendant undertook to pay his proper share of the cost. The agreement if any as to arbitration, so-called, goes only to a remedy for a settlement of the rights of the parties under the contract by which the outlet was to be constructed, and if it be true that the remedy so contemplated is not available it does not close the door of the courts against a hearing in the ordinary course of legal procedure.
V. Exception is taken to the court’s instruction upon the measure of plaintiff’s damages.
Had the offer been limited to the simple proposition that
The ruling was correct. Proof that the witness did make such a statement concerning a former trial would have no tendency to rebut or disprove any statement of fact which he made on this trial. The matter sought to be elicited from him
Without extending this discussion further it may be said that the issues in this case are purely of fact upon which the evidence was such as to entitle the parties to the verdict of a jury and we find no prejudicial error in the conduct of the trial, rulings or instructions. The case has been contested with a fierceness and pertinacity out of all proportion to the sum in controversy. It has been three times tried in the court below with the result that the accumulated costs to say nothing
No sufficient ground for reversal being shown the judgment of the district court is — Affirmed.