8 La. 147 | La. | 1835
delivered the opinion of the court.
. The plaintiff sues to recover the value of certain carpenters’ work, done for the defendant. The defence set up is, that the work was done under a contract, for a stipulated price by the job, to be done within a limited time, and that the defendant, finding that the plaintiff was unable to complete the job, requested him to desist from the wrorb, before the
The only question of law presented for our consideration arises on a bill of exceptions taken by the appellant, to the charge of the judge to the'jury. The jury were instructed that if the defendant had sufficient reason to discharge the plain tiff, then the amount of the contract was to be considered by them as the whole value of the work; but if, on the contrary, he had not good reason to do it, the contract was at an end, and they were to value the work according to a quantum, meruit. The defendant contended that article 2736 of the Louisiana Code makes no distinction, and that whether he had good reasons or not, the estimation of the work was to be made according to the contract, and not otherwise. The article relied on, declares that “the proprietor has a right to cancel at pleasure the bargain he has made, even in case the work has already been commenced, by paying the undertaker for the expense and labor already incurred, and such damages as the nature of the case may require.” We do not discover in this article the,distinction laid down by the court, much less the principle contended for by the appellant, that the contract, though cancelled is to be the exclusive standard of the value of the work done. . Whether the undertaker be discharged for good cause or. arbitrarily, the contract is not the less at an end. It ceases to be the standard by which the value of the wqrk is necessarily to be tested, although this court has held that it may be given in evidence to the jury, to show the estimate which the parties had themselves made, of .the work to be' done. We think, therefore, that the court did not state the law with entire accuracy; but if the appellant complains that his own construction of the article in question, was not given in
Upon the merits, we cannot discover by a careful examination of the evidence, that the jury was misled. The defendant himself does not deny the extra work charged, nor does he pretend that the work done under the contract, was unskilfully executed. According to his own principle, the verdict, in our opinion, was correct.
It is, therefore, ordered, adjudged and decreed, that the judgment of the District Court be affirmed, with costs