Dr. Dale B. DUBIN, Appellant,
v.
DOW CORNING CORPORATION, Appellee.
Dr. Dale B. DUBIN, Appellant,
v.
WARE CONSTRUCTION COMPANY, INC., Appellee.
District Court of Appeal of Florida, Second District.
David C. Park of Register and Park, P.A., Tampa, for appellee Ware Const. Co., Inc.
*72 Edward M. Chew of de la Parte & Gilbert, P.A., Tampa, for appellant.
J. Brent Walker and John J. Cunningham, Jr. of Carlton, Fields, Ward, Emmanuel, Smith & Cutler, P.A., Tampa, for appellee Dow Corning Corp.
RYDER, Chief Judge.
Dr. Dale Dubin appeals a trial court's order which granted final summary judgment for Dow Corning Corporation and Ware Construction Company, Inc. We affirm.
In February of 1977, Ware entered into a written contract to construct an office for Dubin. Ware installed a roof allegedly made by Dow, which allegedly had a five-year warranty.
Dubin took possession of the new building in January of 1978. During the summer of 1978, the roof began to blister and leak, and caused damage to the interior of the building. Although Ware attempted to fix the leaks, the roof continued leaking through 1978 and new leaks appeared in the summer of 1979. Later that year, Ware's subcontractor replaced one-third of the roof under the five-year Dow warranty. Thereafter, despite those attempted repairs, the roof continued to leak and caused substantial damage to the interior of the building.
In December of 1982, Dubin filed complaints against Ware and Dow alleging, among other things, breach of written warranty. In October of 1983, the trial court granted Ware and Dow's motions for summary judgment on the ground that Dubin's cause of action was barred by the four-year statute of limitations for actions founded on the design, planning or construction of an improvement to real property. § 95.11(3)(c), Fla. Stat. (1981).
On appeal, Dubin argues that the trial court should have applied the five-year statute of limitations on contracts to his breach of warranty claim. § 95.11(2)(b), Fla. Stat. (1981). We disagree.
Several Florida courts have interpreted the four-year statute, however, those interpretations have been within the context of other issues such as when notice occurs to trigger the running of the statute. Kelley v. School Board of Seminole County,
Subsection 95.11(3)(c), Florida Statutes (1981), provides for a four-year statute of limitations for:
(c) An action founded on the design, planning, or construction of an improvement to real property, with the time running from the date of actual possession by the owner, the date of the issuance of a certificate of occupancy, the date of abandonment of construction if not completed, or the date of completion or termination of the contract between the professional engineer, registered architect, or licensed contractor and his employer, whichever date is latest; except that, when the action involves a latent defect, the time runs from the time the defect is discovered or should have been discovered with the exercise of due diligence... . (emphasis added)
We read this language to mean "any" action arising out of improvements to real property, whether founded on contract or on negligence. To read the statute otherwise would render it meaningless, because section 95.11(3)(a), Florida Statutes (1981), already provided for a four-year statute of limitations for actions founded on negligence.
*73 Further, section 95.11(3)(c) is a specific statute relating to real property improvements. A special statute of limitations which addresses itself to specific matters takes precedence over a general statute. Carcaise v. Durden,
Appellant also argues that because the Dow warranty on the roof provided for performance over a period of five years, one or more breaches of this "continuing obligation" can occur during the five-year period. Based on this reasoning, he then argues that the four-year statute of limitations for the leaks which appeared during the summer of 1979 did not expire until the summer of 1983. Appellant did not present this argument to this court until we requested briefing on the subject at oral argument. However, his argument still must fail.
The Florida Supreme Court has already rejected the "continuing treatment" doctrine which is, in essence, the same as appellant's "continuing obligation" theory. Kelley,
Affirmed.
DANAHY, J., concurs.
GRIMES, J., concurs in part and dissents in part.
GRIMES, Judge, concurring in part and dissenting in part.
I fully agree that the four-year statute of limitations under section 95.11(3)(c), Florida Statutes (1981), is applicable to this case. However, in view of the existence of the written warranties to repair for specified periods of time, I do not believe that the four-year statute had run with respect to all of Dubin's claims at the time he filed his complaint.
Dubin asserted that upon completion of construction and final payment in January of 1978, Dow had given him a written warranty to make all repairs made necessary by manufacturing defects in Dow's roofing product for a period of five years. Thus, as noted in the majority opinion, if a defect first appeared shortly before the end of the five-year warranty period, Dubin would have had an additional four years to bring suit. The majority concludes, however, that since the defects first appeared in the summer of 1978, the limitations period began to run at that time and thereby expired several months before this suit was filed in December of 1982. Ironically, this means that Dubin lost his right to sue under the five-year warranty at a time when the five-year period had not yet run out.
In Kelley v. School Board of Seminole County,
The Kelley case would be entirely controlling here if Dubin's only claims were predicated on breaches of implied warranties of fitness and merchantability. Warranties of that nature pertain to existing defects, McCarthy v. Florida Ladder Co.,
In a sense, Dow's obligation under the five-year warranty is analogous to obligations payable in installments under which the statute of limitations begins to run against each installment as it becomes due. 51 Am.Jur.2d Limitations of Actions § 133 (1970). Significantly, none of the cases cited in the majority opinion considered the statute of limitations from the standpoint of an express warranty to make repairs during a specified period of time. On the other hand, the court in Bulova Watch Co. v. Celotex Corp.,
Nevertheless, plaintiff's rights under the bonds enable its suit to weather the storm of defendants' attacks. The bonds embody an agreement distinct from the contract to supply roofing materials. The former expressly promise to furnish whatever labor and materials are required for future repairs; the latter deals only with those provided at the time of the installation. The period during *75 which performance may be required under the bonds is expressly stipulated to be 20 years; the only time specified for the performance of the sales contract was that of the original installation... .
On the limitations question, it is clear the [sic] the separate bond obligations, as agreements contemplating services, were subject to a six-year statute (CPLR 213, subd. 2; 1 Weinstein-Korn-Miller, N.Y. Civ.Prac., par. 213.13) running separately for the damages occasioned each time a breach of the obligation to repair the bonded roof occurred (see Putnam's Sons v. Owens,51 A.D.2d 527 ,378 N.Y.S.2d 637 [1976]; Colpan Realty Corp. v. Great Amer. Ins. Co.,83 Misc.2d 730 , 731-732,373 N.Y.S.2d 802 , 803-804 [1975]). For this reason, the bond claims arising within six years of the commencement of this suit are timely, provided they also arose during the 20-year period to which the guarantee relates.
The court in Krueger v. V.P. Christianson Silo Co.,
Dubin also made a claim against Ware which was based upon the same theory as his claim against Dow. Dubin alleged that Ware breached that portion of the written construction contract which requires the contractor at his own cost to remedy "any and all defects due to faulty materials or workmanship which shall appear within a period of one (1) year from the date of final payment." Since Dubin's suit was filed three years and eleven months after the expiration of the one-year period, the suit should not be entirely barred by the four-year statute of limitations, although his recovery would necessarily be limited to breaches for the failure to repair which occurred during the last month of the warranty period.
I would reverse the judgment with respect to Dubin's claim against Dow under the five-year warranty and his claim against Ware under the one-year warranty.
