DTE Energy Co. v. Federal Energy Regulatory CommissionDTE Energy Co. v. Federal Energy Regulatory Commission
The DTE Energy Company and the Detroit Edison Company (“Detroit Edison”) petition for. review of three orders of the Federal Energy Regulatory Commission ruling that certain distribution and interconnection facilities are transmission facilities subject to the Commission’s exclusive jurisdiction. DTE’s petition is not properly before the court because it failed to seek
I.
A.
Section 201 of the Federal Power Act (“FPA”),
Accordingly, the Commission has applied Order No. 888’s seven-factor test to determine jurisdictional authority over utilities providing unbundled retail services.
3
See TAPS,
B.
The instant appeal arises in the context of the Commission’s efforts to establish a regional transmission organization (“RTO”) to integrate the Midwest wholesale electricity market. In response to rising energy costs in the Midwest, the Commission, facilitated the development of a Midwest RTO and the integration of for-profit transmission companies to operate under the RTO umbrella.
See generally Pub. Util. Dist. No. 1 v. FERC,
Detroit Edison and International Transmission. (“IT”) were both wholly owned subsidiaries of DTE Energy. Detroit Edison operates as DTE Energy’s public utility, engaged in the generation, transmission, and distribution of energy in Michigan.
DTE Energy Co.,
Pursuant to the Commission’s approval of Midwest ISO as the regional RTO, IT applied for and received by Order of December 20, 2001, the Commission’s authorization to transfer to Midwest ISO functional control over IT’s jurisdictional transmission facilities. When IT thereafter submitted an updated list of jurisdictional facilities to be transferred to Midwest ISO, CMS Marketing, Services and Trading Company (“CMS”) protested, arguing that the list should include Detroit Edison’s facilities interconnecting Dear-born Industrial Generation, LLC (“DIG”) with IT — specifically, the 230 kV Navarre-DIG line (“Navarre line”), the 230 kV Baxter-DIG line (“Baxter line”), and the Baxter substation (collectively, “DIG facilities”) — because these are the facilities by which DIG sells electric energy to wholesale purchasers, and therefore are Commission jurisdictional transmission facilities.
Int’l Transmission Co.,
By Order of May 22, 2002, the Commission found that the Navarre and Baxter lines appear to perform a jurisdictional transmission function because they are part of the interconnection facility connecting DIG to the transmission grid, and sought additional information from IT to inform the Commission’s jurisdictional decision. Id. at 61,889. The Commission found the Baxter substation should be included in an updated list of IT’s transmission facilities as it had already been included in the FERC Docket No. EC00-86 list of facilities that Detroit Edison was transferring to IT, incorporated into the December 20, 2001 Order. Id.
Detroit Edison moved to intervene and responded on July 16, 2002, conceding that the DIG facilities are, in part, interconnection facilities used in wholesale sales from the DIG Plant, but contending they nevertheless were part of Detroit Edison’s local distribution system. Noting that the Baxter and Navarre lines had been developed and historically used to provide retail distribution service to electric loads located in or near the Rouge Industrial Complex in Dearborn pursuant to retail tariffs and contracts, Detroit Edison maintained the facilities were “dual-use” and should be subject to the shared jurisdiction of Michigan and the Commission. Concerned that classifying the facilities as transmission rather than local distribution facilities would cause it to incur stranded costs, Detroit Edison offered alternatively to transfer limited operational control over the DIG facilities to Midwest ISO to the extent necessary to effectuate wholesale sales. CMS again protested, arguing the Navarre line serves as the primary point of interconnection between DIG and IT from DIG’s inception, and the Baxter line had been reconfigured to serve as a secondary point of interconnection with IT; it appended an analysis of power flows on the two lines.
Then, on October 4, 2002, Detroit Edison submitted an executed Agency Agreement between it and Midwest ISO that sought to transfer limited functional control over the DIG facilities to enable Midwest ISO to ensure the DIG generator receives non-discriminatory service when using the facilities for wholesale sales. In responding to a deficiency letter from Commission staff, Detroit Edison explained that retail-load customers must obtain retail-delivery service over the Detroit Edison facilities under the state Retail Access Service Tariff (“RAST”), and that ceding complete operational control to Midwest ISO would render Detroit Edison unable to recover its costs under the RAST, including the costs of the Baxter
By Order of March 13, 2003, the Commission found that the DIG facilities perform a transmission, not a state-jurisdictional local distribution function.
Detroit Edison Co.,
Finally, by Order of November 17, 2003, the Commission denied, in relevant part, DTE’s and Detroit Edison’s petitions for rehearing of the March 13, 2003 and April 11, 2003 Orders, stating that both parties had presented the same arguments as before without offering any new evidence.
Detroit Edison Co.,
II.
On appeal, DTE and Detroit Edison challenge the Commission’s May 22, 2002 and March 13, 2003 Orders and the November 17, 2003 Rehearing Order. We first address two jurisdictional issues.
A.
Section 313(a) of the FPA provides that “[a]ny person ... aggrieved by an order issued by the Commission ... may apply for a rehearing ...,” but “[n]o proceeding to review any orders of the Commission shall be brought by any person unless such a person shall have made application to the Commission for a rehearing thereon.”
DTE Energy petitions for review of the Commission’s May 22, 2002 Order, for which it did not seek rehearing before the Commission, but fails to challenge the April 11, 2003 Order, by which it is aggrieved. Hence, DTE Energy is not a proper party to these proceedings. In the May 22 Order, the Commission conditionally accepted the compliance filing by DTE Energy and IT submitted pursuant to the Commission’s December 20, 2001 Order, but directed DTE Energy to submit further information in response to CMS’s protest regarding the exclusion of the Navarre and Baxter lines as transmission facilities in the filing. It was not until the April 11 Order, in which Detroit Edison intervened, that the Commission accepted DTE Energy’s compliance filing with modifications directing DTE Energy, IT, and Detroit Edison to revise their filings to include the DIG facilities as jurisdictional transmission facilities to be transferred to Midwest ISO for operational control. April 11, 2003 Order, 103 F.E.R.C. at 61,-666-67.
DTE’s failure to seek rehearing of the May 22, 2002 Order is fatal to its challenge of that Order in its petition for review.
B.
Section 313(b) of the FPA provides that “[n]o objection to the order of the Commission shall be considered by the court unless such objection shall have been urged before the Commission in the application for rehearing unless there is reasonable ground for failure to do so.”
While Detroit Edison sought rehearing of the March 13, 2003 Order, by which it is aggrieved, it did not argue in its petition for rehearing before the Commission that the Commission misapplied the seven-factor test. Instead, it raises the argument for the first time in its reply brief to the court. Detroit Edison fails to offer any grounds, let alone reasonable grounds, under section 313(b) of the FPA to excuse its failure to raise this argument before the Commission on rehearing. See
OMYA, Inc. v. FERC,
llFF.3d 179, 181 (D.C.Cir.1997). However, while the Commission argues in its brief on appeal that it applied the seven-factor test in the analysis of the March 13, 2003 Order, it did not expressly reference the test until the Rehearing Order. Even then the Commission did not state it was applying the seven-factor test, commenting only that its factual conclusions are “consistent with the seven-factor test.”
November 17, 2003 Rehearing Order,
105 F.E.R.C. at 62,084. This language is hardly consistent with the Commission’s statement in Order No. 888 that it “will apply” its jurisdictional test. Order No. 888 at 31,980. Nevertheless, Detroit Edison acknowledged the applicability of the seven-test in footnote 42 of its petition for rehearing and could have challenged the Orders on that ground, citing
Detroit Edison
as support; instead it argued that, contrary to the Commission’s findings, the evidence showed the DIG facilities were “dual-use” facilities and not subject to the Commission’s exclusive jurisdiction. Detroit Edison’s failure to challenge the seven-factor analysis earlier is understandable, in part, because, as counsel for the Commission stated during oral argument, Detroit Edison is not seeking to have the Commission apply the seven-factor test but to have the Commission classify the facilities as “dual-use” subject to shared jurisdictional control. But the Commission’s single-jurisdictional approach, identifying the primary function of a facility, has been judicially approved as a reasonable means of resolving regulatory ambiguity under section 201 of the FPA,
see New York v. FERC,
535 ILS. 1,
Accordingly, the only issue within the court’s jurisdiction is Detroit Edison’s contention that the Commission’s findings in support of its exclusive jurisdictional determination are unsupported by the record evidence and that the Commission therefore acted arbitrarily and capriciously in asserting exclusive jurisdiction over the facilities.
III.
The court will uphold the Commission’s orders unless they are arbitrary and capricious, an abuse of discretion, or otherwise not in accordance with the law.
In the March 13, 2003 Order, the Commission found that “the [facilities perform a transmission function and not a state-jurisdictional local distribution function because: (1) the [facilities are at a high-voltage level; (2) the Navarre-DIG line and the Baxter-DIG line are both 230 kV lines, and along with the DIG ring bus, form a 230 kV loop configuration; and (3) power flows into and out of the loop configuration.” 102 F.E.R.C. at 61,906. The Commission found that the DIG, which is interconnected by the facilities to IT, is selling all its output at wholesale. It affirmed these findings on rehearing, explaining that:
Although local distribution lines may exist within the Rouge Industrial Complex where Detroit Edison states that it serves retail customers, the record demonstrates that the [facilities are not local distribution facilities.... Power flows into and out of the [facilities, making them looped transmission facilities, i.e., not radial in character like those of local distribution facilities. With the DIG facility interconnected to the grid and given the network configuration, the [facilities have the capacity to transmit energy to other markets outside the geographical area.
November 17, 2003 Rehearing Order, 105 F.E.R.C. at 62,084. The Commission noted that Detroit Edison had previously characterized the Baxter 230 kV switch as transmission and that the Navarre line connects to the IT systems and thus to the transmission grid, such that it also operates as a looped 230 kV transmission line. Id. at 62,085.
As on appeal, Detroit Edison argued in its petition for rehearing that the Commission’s jurisdictional conclusion was wrong in two respects: First, the facilities per
In fact, on rehearing the Commission acknowledged that “local distribution lines may exist within the Rouge Industrial Complex where Detroit Edison states that it serves retail customers.” Id. at 62,084. Critical to the Commission was that “the record,” described in its March 13, 2003 Order, which was affirmed on rehearing, “demonstrates that the [facilities are not local distribution facilities.” Id. Moreover, “neither Detroit Edison nor DTE has proffered any additional evidence on rehearing that shows otherwise,” id.; nor did Detroit Edison dispute the factual findings on which the Commission relied for its jurisdictional conclusion. For these reasons, the Commission explained it disagreed with Detroit Edison’s view that the facilities are “dual-use,” rather than transmission facilities.
On appeal, Detroit Edison’s reliance on the historical distribution function performed by the facilities is misplaced because the historical purpose or alleged intended use of the' facilities does not speak to the issue at hand, which is their present primary function. Detroit Edison’s further contention that the looped nature of the facilities arises only because of the configuration of third-party facilities is forfeited because it failed to raise this argument before the Commission.
See supra
Part II B. Although Detroit Edison cites its rehearing request of the March 13, 2003 Order, its request never argued that the Commission should have found the DIG facility lines radial because the facilities were owned by others; rather, its argument was that if the Commission found the DIG facilities to be jurisdictional, the Commission should also find the Ford and Rouge facilities completing the loop jurisdictional as well to avoid discriminatory impact on Detroit Edison. In any event, whether Detroit Edison owns all the facilities in the loop is beside the point as the determinative question is whether the facilities it does own, as presently configured, perform a transmission function. Nothing in
Detroit Edison,
Finally, there is no mérit to Detroit Edison’s contention that the Commission erred by failing to reopen the proceedings to consider the order of the Michigan Public Service Commission. - In accordance with Order No. 888, the Commission defers to a state commission classification of
Accordingly, we deny the petition for review.
So ordered.
Notes
.
See Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Seivices by Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities,
Order No. 888, 61 Fed. Reg. 21,540 (May 10, 1996), FERC Stats. & Regs. ¶ 31,036 at 31,783-84 (1996),
order on reh'g,
Order No. 888-A, 62 Fed. Reg. 12,-274 (March 14, 1997), FERC Stats. & Regs. 1131,048 at 30,336 (1997),
order on reh’g,
Order No. 888-B,
. The seven factors, which the Commission stated it "will evaluate in determining whether particular facilities are transmission or local distribution in the case of vertically integrated transmission and distribution facilities,” are:
(1) Local distribution facilities are normally in close proximity to retail customers.
(2) Local distribution facilities are primarily radial in character.
(3) Power flows into local distribution systems; it rarely, if even, flows out.
(4) When power enters a local distribution system, it is not reconsigned or transported on to some other market.
(5) Power entering a local distribution system is consumed in a comparatively restricted geographical area.
(6) Meters are based at the transmission/local distribution interface to measure flows in the local distribution system.
(7) Local distribution systems will be of reduced voltage.
Order No. 888 at 31,981.
.
E.g., Am. Serv. Co.,