30 Wash. 530 | Wash. | 1902
The opinion of the court was delivered by
This was an action instituted by the respondents against the defendants Rief and Sehiefer, as principals, and the American Surety Company of New York, as surety, on a bond executed by said principals and said surety for the faithful performance of a contract which the said principals had entered into with the respondents for the construction of a certain building in the city of Spokane. The bond in question is in the sum of $4,000, and the respondents (plaintiffs below) by this action seek to recover the damages alleged to have been sustained by them by reason of the failure of the said con
The respondents alleged in their complaint, in substance, among other things: That they were the owners of certain land in the city of Spokane, which they specifically described. That on July 27, 1899, they entered into a contract in writing with the defendants Kief and Schiefer, whereby the said defendants agreed to erect and construct a four-story building upon said real estate for the plaintiffs, which contract was attached to and made a part of the complaint. That on the 29th day of July, 1899, the said defendant, the American Surety Company of New York, for the purpose of guarantying the performance of said contract by the said Kief and Schiefer, executed and delivered to the plaintiffs its bond of indemnity, which bond is set out in extenso in the complaint, and contains the following recitals:
“The condition of this obligation is such that whereas, a contract and agreement has been made and entered into between the above bounden principals and J. L. Drumheller and A. A. Barnett, for the construction of a four-story and basement brick and stone building situated on part of lots one (1) and two (2), block two (2), Resurvey and Addition to Spokane, Washington, including everything to complete the building, except the heating and plumbing, a true copy of which said agreement is hereto annexed and made a part hereof; now, therefore, if the said above bounden principals shall and will fully and completely perform all the conditions of said contract hero-to annexed faithfully in every respect, and shall pay for all materials furnished and labor performed in the execution of said contract, to the parties entitled thereto, and all*535 damages, expenses, and charges dne to J. L. Drumheller and A. A. Barnett under said contract by reason of the non-performance thereof strictly and literally as in said contract provided, then this obligation to be void; otherwise to be and remain in full force and effect.”
That defendants, Bief and Schiefer, duly entered upon the performance of said contract, and completed the building, but failed to complete the same within the time required by said contract, and did not complete it until the first day of March, 1900. “That by the terms of said building contract these plaintiffs were to pay said Bief and Schiefer for the construction of said building, including the laying of an asphalt sidewalk around said building, in accordance with the plans and specifications prepared by J. E. Dow, architect, the total sum of $14,900. That after-wards these plaintiffs determined to construct a cement sidewalk around said building, instead of said asphalt sidewalk, and by agreement then entered into between these plaintiffs and the said A. Bief and Drank Schiefer, with the consent of said American Surety Company of New York, it was agreed that these plaintiffs should construct said cement sidewalk themselves at their own expense, and that, said Bief and Schiefer, by reason of being relieved from constructing said asphalt sidewalk, should allow plaintiffs the sum of $375 on said contract price for said building;” that during the progress of the construction of said building the plaintiffs from time to time made payments to said Bief and Schiefer upon estimates made by J. E. Dow, architect, aggregating the sum of $12,464. That when said building was completed the plaintiffs learned that the contractors, Bief and Schiefer, had incurred large bills and liabilities for labor performed upon and materials used in the construction of said building, which plaintiffs
The defendants, in their answers, admit the execution of the contract and bond as alleged in the complaint; ad
The respondents (plaintiffs below) move to strike the brief of appellant, and to dismiss $he appeal, for the alleged reason that the appellant has utterly failed to comply with the requirement of subdivision 1 of rule 8 of this court in that it has failed to make a clear statement of the case, and has also failed to refer to the pages of the transcript for verification. Subdivision 1 of rule 8, which respondents contend has not been complied with by appellant, reads as follows:
“Briefs shall be printed throughout in plain, clear type, and shall contain a clear statement of the case so far as deemed material by the party, with reference to the pages of the transcript for verification.”
The manifest object of this rule is to apprise this court, and the opposite party of the real nature and character of the case presented for determination, as understood by
The learned counsel for the appellant earnestly insist that the court below erred (1) in overruling their motion, made at the close of respondents’ evidence, to take the case from the jury, and for judgment, on the ground of insufficiency of the evidence, and (2) in refusing to instruct the jury, as requested by appellant at the close of
Numerous authorities ai*e cited in the brief of the appellant in support of the proposition that changes in a contract, the faithful performance of which the surety has guarantied, if made without the consent of the surety discharges him, even though the changes may be beneficial to the surety; that the liability of the surety does not extend beyond the very terms of his contract, and that no equitable considerations can be permitted to operate against a surety. That the doctrine announced and contended for by appellant as to the rights and liabilities of a surety is uniformly maintained by the courts, and is well founded in reason, is frankly conceded by the learned counsel for the respondents; but they insist that it has no application to this case for the alleged reason that it is abundantly shown by the record that the appellant did in fact consent to the alteration of the contract of which it now complains. It is not claimed, however, by counsel that such consent was shown by the testimony of any witness who testified at the trial of the case. Their contention is that the change in the contract was provided for in the contract itself, as well as in the bond, both of which were introduced in evidence by the respondents, and was, therefore, consented to by the appel
In DeMattos v. Jordan, 15 Wash. 378 (46 Pac. 402), this court held that sureties on the bond of a building contractor are not discharged by deviations from the specifications in the construction of the building, nor even by material alterations, when the contract itself permits such deviations or alterations to be made. American Surety Company v. Lauber, 22 Ind. App. 326 (53 N. E. 793), was an action on a bond for the faithful performance of a contract entered into between one Hutton and the board of education of South Bend, Indiana, for the construction of a certain school house. In that case, as in this, the contract and the bond in question were made a part of the complaint, and their execution admitted. The surety claimed that it was discharged by reason of a change in the contract. The provisions of the contract as to changes and alterations in the work were, in substance, the same as the provisions incorporated into the contract here under consideration; and in that case the court said:
“The third article of the contract between Hutton and the board provides that ‘no alteration shall be made in the work shown or described in the drawings and specifications, except upon a written order of the architects.’ Provision is also made for estimating the value of the work added or omitted, and for reference to arbitration in case the architect and contractor cannot agree as to the value of the changes. The contract thus contemplated that changes may be made as the work progresses, and provides therefor. The sureties, in the execution of the*543 bond, consented in advance to changes that might be made properly within the scope of the contract. The answer does not aver that the changes were not made in the manner provided by the building contract. If Hutton, for purposes of his own, made the changes, his sureties would not be thereby relieved. It is averred, as to one item of change, that the change so stated was carried out and performed by the said Hutton -under the instruction of the architect of said building. It will be presumed, in the absence of an averment to the contrary, that the changes were made conformably to the provisions of the contract. The sureties consented in advance to changes that might be made conformably to the terms of the contract.”
The decision in the above cited case fully supports the respondents’ contention, and is directly in line with the ruling of this court in DeMattos v. Jordan, supra. And the question, then, is, was the change in the work, of which the appellant complains, contemplated and provided for by the agreement between the contractor and the respondents? We think that a proper construction of the contract warrants the conclusion that it was. It must be borne in mind that it is admitted in the pleadings that the appellant consented to the substitution of cement for asphalt in the construction of the sidewalk. And it is argued by appellant’s counsel that this substitution of one material for another constituted the only real change made “in the work,” so far as the sidewalk was concerned, and that the agreement permitting the respondents themselves to construct it simply effected a change “in the workers,” and not in the work, and that no such change was ever consented to by appellant, or authorized by the contract between its principal and the respondents. It is admitted that the sidewalk was actually built in conformity with the specifications of the architect, except as
“I instruct you, gentlemen of the jury, that, under the admitted facts in the pleadings in this case, you must find a verdict for the plaintiffs for the delay in completing this building, for the period of ninety days, of $900, unless you find the defense or excuse for that, which is set up by defendant in his answer, is sustained by the testimony. The defendants allege with reference to that matter several defenses. The only defense, however, which the court submits to you, and which, as a matter of law, you are entitled to consider under the facts and testimony in this case, is the following: That the plaintiffs orally agreed with the defendants, Rief and Schiefer, after the making of the said building contract, and so modified said building contract that these defendants, Rief and Schiefer might and should have until the first day of March, 1900, within which to fully perform said building contract and complete said building, and consented to such extension of time and said building was completed within such extended time. As to that defense, I charge you that if you find from the testimony in this case that there was an oral agreement between Mr. Drumheller and either Mr. Rief or Mr. Schiefer, by which they should have an extension of time until March 1st in which to complete this building, your verdict as to that item of $900 must be for the defendants.”
The appellant claims that the court erred in thus instructing the jury, for the reason that the respondents were not entitled, under the contract, to recover any damages for delay in completing the building, without alleging and proving that such damages had been fixed and determined by the architect, or by arbitration, in accordance with articles three and eight of the contract, and that the court should have so instructed the jury. But we are of the opinion that the provisions of the contract invoked
“While courts of equity afford relief against penalties, they cannot relieve against liquidated damages.”
As we have already said, the defendants, in their answer, set up a claim amounting to $231.50, for extra work upon or about the foundation of the building. There was no averment in the pleadings of the respondents as to the value of this extra work, but at the trial the architect was called as a witness, and testified that the value of the
“They [meaning defendants] claim that it is two hundred and thirty-one dollars and a half. The plaintiffs here as to that item claim that it was not worth so much. Their claim with respect to it, as shown by the testimony in the case, is that it was not worth more than $120.”
The appellant insists that the court, in making this statement to the jury, violated that provision of the constitution which prohibits judges from charging juries with respect to matters of fact, or commenting thereon. But we do not think that these remarks of the judge fall within the spirit of the constitutional inhibition. It was the province of the judge to tell the jury what the claims of the respective parties were as to the particular matter in question; and, although in so doing he incidentally referred to the testimony, his statement, in our judgment, did not amount to a comment upon the evidence, within the meaning of the constitution. It certainly did not indicate to the jury that the evidence established, or tended to establish, the claim of either party. The court did not state, as the judge did in effect, in State v. Hyde, 20 Wash. 234 (55 Pac. 49), cited by appellant, what testimony had been given in the case. The statement made by the judge in the Hyde Case, which was disapproved by this court, was as follows: “My notes show that Con-cannon testified that appellant on the way to the station admitted to him (Ooncannon) that he struck the prosecuting witness the blow.” The distinction between that case and this is apparent. In the recent case of French v. Seattle Traction Co., 26 Wash. 264 (66 Pac. 404), we held that, when references to the evidence, made by the court in its charge to the jury, do not amount to an explanation or criticism of the evidence, nor assume or assert
It seems that there was some controversy between the respondents and the contractors as to the value of an extra door which had been placed in the building, and for which, it was admitted, the contractors should be paid. The court, in charging the jury, omitted to mention the item of the door until its attention was called to it by counsel for the respondents. At that time one of the jurors asked the court what kind of a door it was that was furnished, and the judge replied: “I think the testimony is silent as to that point, as to the kind of door it was. You will simply have to determine that matter from the testimony in the ease. I do not think there is any testimony about it.” It is also claimed by appellant that this reply of the court to the interrogatory of the juror constituted a further comment upon the evidence, but we are not of that opinion. It is always proper for the court to state to the jury that there is no evidence as to a certain matter, when, as in this case, such is the fact. But it is for the jury alone to determine the weight of the evidence submitted to them, without interference or suggestion on the part of the court.
Some other objections are made to the court’s instructions to the jury, but, inasmuch as they are not discussed in appellant’s brief, we shall content ourselves by simply saying that we do not deem them well taken.
We find no error in the record and the judgment must, therefore, be affirmed, and it is so ordered.
Beavis, O. J., and Dunbar, Fullerton and Mount, JJ., concur.