129 Neb. 273 | Neb. | 1935
This is a compensation case. The employer appeals from the award made by the trial court. The employer was the contractor to construct a bridge over the Loup river south of Columbus. It was a federal aid project and the contract provided that certain provisions of the emergency relief and construction act should be applicable to the work. One of the provisions both of the federal law and the contract was that skilled labor should not be per
The important consideration here, however, is the contract of employment between the employer and the employee. The only significance to be attached to the construction contract is the help it will give us, if any, to determine the contract of employment. There is no question that the employee was injured in the course of his employment. As a result of the injury, he lost his thumb and injured his index finger on his left hand. The trial court awarded compensation on the basis of a weekly wage of $30. The only complaint registered here is that this finding is erroneous. The employer contends that the weekly wage should be $15 a week and has paid compensation. The employee insists that he was working part time and that his weekly wage for an entire week would be $30. The emergency relief and construction act of 1932 provided that public works constructed under the provisions of the act should employ men only for 30 hours a week. It was the idea that this would provide some employment for a greater number of men. While this federal enactment does not abrogate the provisions of the workmen’s compensation law of the state, the federal government could provide that the contract should contain the same conditions. The contract in this case between the state of Nebraska and the Omaha Steel Works did contain these provisions.
The controversy here arises over the method of computing the weekly wage of the employee at the time of the injury. Compensation is awarded solely according to the provisions of the statutes. Section 48-117, Comp. St. 1929, provides: “Compensation shall be calculated with reference to the wage the workman was receiving from the person by whom he was immediately employed at the time of the' injury.” The wage the employee was receiving at the time is computed under the provisions of section 48-126, Comp. St. 1929, which says: “Wherever in this article the term ‘wages’ is used, it shall be construed to mean the money
There was a very earnest discussion by the attorney for the appellee relative to the beneficient purposes of the workmen’s compensation act. This court has always given the workmen’s compensation act a liberal interpretation that it might accomplish the purpose and intention of the legislature. But, after all, the relief available must be provided by the statute. The statute fixes the liability of the employer. The evidence determines the contract of hiring in force at the time of the accident. It was for a thirty-hour week at 50 cents an hour.
Two Nebraska cases are cited by the employee. Davis v. Lincoln County, 117 Neb. 148, is not helpful in solving this problem. Davis was employed by the county to do the necessary work to keep some bridges in order, including reparation of damage from floods. There it was said: “The nature and surroundings of the transaction and which were necessarily in contemplation of the parties to the contract were such as to support the further conclusion
Several cases from other jurisdictions have been cited to support the employee’s position. In Modin v. City Land Co., 189 Minn. 517, it is apparent that the court applied the Minnesota statute to determine the weekly wage. There the weekly wage was calculated by multiplying the daily wage by five and one-half, as provided by the statute. Our statute does not so provide.
Lastly, we are cited to several Louisiana cases. In Rylander v. T. Smith & Son, 177. La. 716, the weekly wage was computed by “adhering to the plain words of the statute and fixing the compensation on the basis of the ‘daily rate of pay.’ ” At the time of the accident the employee was not working full time on account of lack of business, but was subject to work all the time. In Calhoon v. Meridian Lumber Co. (1934) 151 So. (La. App.) 778, the employee had been working about half time for several months due to economic conditions. This conclusion was reached with reference to the Louisiana statute. An examination of the statute apparently in effect at the time the above cases were decided reveals that the term “wages” is defined as the daily rate of pay under the contract of hiring in force at the time, instead of the weekly rate under such a contract as here. However, in a later case, also decided in 1934, Suire v. Union Sulphur Co., 155 So. (La.
The judgment of the district court is reversed and the cause remanded, with directions that the trial court compute the weekly wage at $15 a week and award compensation accordingly.
Reversed.