Appellant-plaintiff Wade Driggers d/b/a Falcon Construction Company brought the instant damages action against appelleedefendant Julia A. Campbell, for breach of contract as to renovation work done on her Savannah home. The plaintiff sought damages in the amount of $146,375, the balance due on a $186,375 renovation contract the defendant signed on December 13, 1997 (“December 13 contract”). 1 The defendant timely filed her answer averring, among other things, that the December 13 contract was unenforceable as supported only by past consideration. Following a hearing on cross-motions for summary judgment, the superior court issued its order denying each of the parties summary judgment, finding that jury issues remained as to: (1) whether the December 13 contract was supported by consideration adequate to create an enforceable agreement; and (2) if not, whether there should be recovery in quantum meruit. Upon the trial of the case, the jury returned its verdict finding the December 13 contract to be an invalid contract and awarded quantum meruit damages in the amount of $16,482. The plaintiff now appeals the judgment of the superior court entered upon the jury’s verdict, contending that the superior court erred in: (1) granting defendant’s motion to amend the pretrial order at the close of plaintiff’s evidence for the purpose of adding the affirmative defenses of unconscionability, illegality, and fraud; (2) denying his motion for directed verdict as to the validity of the December 13 contract as supported by valid consideration; (3) failing to give his request to charge on “bad bargain” as not relieving a party of the duty to perform under a contract; and (4) granting defendant’s motion for directed verdict on his claim for attorney fees under OCGA § 13-6-11. Held:
1. The plaintiff claims that defendant’s belated motion to amend the pretrial order waived her affirmative defenses in that she offered no explanation for her delay.
Ostroff v. Coyner,
At the close of his case-in-chief, the plaintiff moved in limine, as he had done by his trial brief, to foreclose defendant’s introduction of any evidence pertinent to her affirmative defenses as waived for her failure to amend her answer to reflect these defenses before the entry of the pretrial order. The record shows that the defendant moved to amend the pretrial order in response to plaintiff’s renewed motion in limine, arguing there was no surprise in that she had raised the affirmative defenses complained of two and a half months earlier by her brief in support of motion for summary judgment and response to plaintiff’s motion for summary judgment.
Affirmative defenses are pleaded to prevent surprise and give
the opposing party fair notice of what to defend.
Mayer v. Wylie,
In determining whether leave to amend a pretrial order should be allowed after entry thereof, see OCGA § 9-11-15 (a), trial courts must balance “possible unfair prejudice to the nonmoving party with the movant’s reasons for delay. [Cit.]”
Rowe Dev. Corp. v. Akin & Flanders, Inc.,
2. Neither did the superior court err in denying plaintiff’s motion for directed verdict predicated on the claims that the December 13 contract was enforceable as supported by valid consideration under OCGA § 13-3-42, assented to by the defendant’s signature, and not subject to modification upon parol evidence.
A directed verdict is proper only if there is no conflict in the evidence as to any material issue and the evidence introduced, with all reasonable deductions therefrom, shall demand a verdict. OCGA § 9-11-50 (a). In determining whether any conflict in the evidence exists, the court must construe the evidence most favorably to the party opposing the motion for directed verdict. The standard used to review the grant or denial of a directed verdict is the any evidence test. Evans Timber Co. v. Central of Ga. R. Co.,239 Ga. App. 262 (1) (519 SE2d 706 ) (1999).
Griffith v. Med. Rental Supply
&c.,
Pretermitting plaintiff’s arguments urging the enforceability of the December 13 contract, it is undisputed that the plaintiff did not provide the contract to the defendant for signature until after all the work performed thereunder had been done. “To constitute consideration, a promise or a return promise must be bargained for by the parties to a contract.” OCGA § 13-3-42 (a). The December 13 contract was submitted to the defendant only after the additional work had been completed which vitiated any claim that the contract was bargained for and a meeting of the minds reached thereon. See
Mullinax v. Doughtie,
3. Plaintiff also contends that the superior court’s instruction upon the affirmative defenses of unconscionability and fraud, while refusing to give the bad bargain charge he requested, erroneously suggested to the jury that a party’s bad bargain is a defense to its failure to perform thereunder. This claim of error is likewise without merit.
In Georgia, the power of the courts to shield contracting parties from unconscionable contractual provisions and the duty of the courts to protect the freedom of parties
4. Finally, the superior court did not err in granting defendant’s motion for directed verdict on plaintiff’s claim for litigation expenses pursuant to OCGA § 13-6-11.
OCGA § 13-6-11 allows recovery of litigation expenses when defendant has acted in bad faith, has been stubbornly litigious, or has caused the plaintiff unnecessary trouble and expense. With respect to bad faith, the elements of bad faith that will support a claim for expenses of litigation must relate to [defendant’s] acts in the transaction itself prior to this litigation, not to the motive with which it defended the litigation. Kemira, Inc. v. Williams Investigative &c. Svcs.,215 Ga. App. 194 , 200 (3) (450 SE2d 427 ) (1994). A recovery for stubborn litigiousness or causing unnecessary trouble and expense is authorized if no bona fide controversy or dispute existed as to the defendant’s liability.
King Indus. Realty v. Rich,
Judgment affirmed.
Notes
The December 13 contract incorporated amounts owing on two home renovation con tracts executed earlier in 1997 and included $153,000 for the additional work which was done. A third contract executed between the parties in 1997 was for the replacement of defendant’s roof. Such contract was not in issue because the defendant had paid it out in full in the amount of $18,800.
The superior court instructed the jury that “[a]n unconscionable contract is one abhorrent to good morals and conscience. It is one where one of the parties takes a fraudulent advantage of the other. Unconscionability is directly related to fraud and deceit; which, in turn, may be found where there is a great inadequacy of consideration or where one party to a contract is not as thoroughly knowledgeable as to the subject matter as the other.”
