447 S.W.2d 96 | Ky. Ct. App. | 1969
Driggers Construction Company, Inc. subcontracted to grade the original site of the London Low Income Housing Project at London, Kentucky. After performing part of the contract, Driggers employed E. R. Hopper by telephone to perform its remaining duties. Both parties agree that initially Driggers told Hopper that there was about $500.00 work to be done. Approximately ten days later Hopper informed Driggers that it would run much more and Driggers told him to go ahead and do the best he could. $500.00 was paid by Driggers and after the work was completed Hopper demanded an additional $3,580.36. Driggers refused to pay and Hopper sued. Without the intervention of the jury the trial court awarded Hopper the amount of his claim and from that judgment this appeal arose.
Appellant contends that the evidence conclusively showed that the compensation to be paid on the express oral contract was an agreed sum of $500.00. The trial court found that “the minds of Driggers and Hopper did not meet with respect to the amount of compensation to be paid for the work to be performed by Hopper, or at least the amount of such compensation was not certainly fixed and agreed upon by the parties.” Although this court, if trying initially, might have reached a different conclusion it will not impose its will unless the findings of the trial court were clearly erroneous. Long v. Howard, 311 Ky. 66, 223 S.W.2d 376 (1949) and Hatfield v. Hatfield, Ky., 417 S.W.2d 218 (1967). We are unable to say that they were. The findings were supported by the evidence, therefore, appellant can have no comfort from Massachusetts Bonding & Insurance Company v. Huffman, Ky., 340 S.W.2d 447 (1960), and Yates v. Wilson, Ky., 339 S.W.2d 458 (1960).
Appellant’s final contention is that the evidence conclusively showed that Hopper performed services which Driggers was not obligated to perform under its contract with the general contractor, therefore, all of Hopper’s work should not be paid for by Driggers. It appeared that there was excess material on the site which had been taken from certain excavated areas and pipes, the clean-up of which was not included in Driggers’ contract. The •evidence indicated and the trial court found that Driggers had employed Hopper to remove the earth to a specific level or grade and had not informed him that the removal of this excess material was not his responsibility. We find no merit in this argument that Hopper performed services for anyone except Driggers.
The judgment is affirmed.