60 Mo. App. 134 | Mo. Ct. App. | 1894
The defendant Eidpath was the original contractor for the construction of a building belonging to his eodefendant, the St. Louis School of Pharmacy, The plaintiffs furnished and put in the glass for the building under a contract with Eidpath. The present action is against Eidpath for the amount of the bill, and to enforce a mechanics’ lien against the building. The cause was submitted to the court without a jury, and judgment was entered in favor of the plaintiffs against Eidpath for the debt, but the finding was against them as to the lien. The plaintiffs have appealed.
The defendants introduced evidence tending to prove that the St. Louis School of Pharmacy moved into the building during the first week of October, 1892; that at that time'Ridpath was still at work on the building; that he failed to complete it in accordance with his contract, and that the St. Louis School of Pharmacy caused the same to be finished in October and November.
This being the proof, the court, of its own motion, gave the following instruction: •
“If the court, sitting as a jury, finds from the evidence that all the materials charged for under date September 26, 1892, in the lien account read in evidence were furnished, and that all the work charged for under said date in said account was performed, and that all the material plaintiffs had contracted or agreed with defendant Ridpath to furnish and put in the house described in petition had been furnished and put*138 in said house, and that all the labor plaintiffs had contracted as agreed with said Ridpath to perform on or in connection with said house had been fully performed by the plaintiffs on or before September 26, 1892, and more than four months prior to the filing of said lien account) and that the account of the plaintiffs against the defendant Ridpath for said materials and work so furnished and performed and charged for accrued and actually became payable fro,m said Ridpath to the plaintiffs on September 26, 1892; that subsequently three of the lights or panes of glass included in said materials were broken, not on account of inherent defects, or imperfect putting in, or fault on part of plaintiffs; that thereupon said Ridpath refused to pay plaintiffs for said work and materials until plaintiff should first replace said three lights or panes of glass by others which were sound; that thereupon the plaintiffs, in order to avoid dispute and to obtain their pay without delay, did, on October 26 and 27, 1892, and less than four months before the filing of said lien account, replace said.three lights or panes by others which were sound; then the replacing of said three lights or panes, under these circumstances, did not serve to extend the time of the plaintiffs for filing said lien account, and the court, sitting as a jury, will accordingly find that the plaintiffs are not entitled to the lien herein claimed and sought to be enforced by them.”
The objections made by counsel for appellants to this instruction are that, according to it, the circuit court i,can determine when the contract of a subcontractor is completed independently of the conclusion reached in good faith by the parties to the contract, and, further, when the contract is once completed, it is not within the power of the parties to the contract to enlarge it by stipulations for additional work. We do
Neither does the instruction embody or the evidence raise the proposition, that the contract of a subcontractor can not under any circumstances be enlarged by additional work.
It was not claimed by plaintiff, nor does the evidence justify the inference, that the additional panes of glass were furnished and put in as extra work. In fact, no additional charge was made for it, as the lien account shows. We do not doubt the proposition, if the contract with the owner provides for changes and alterations and the owner agrees to pay what they are equitably worth, and charges are agreed on, and the extra work is performed by a subcontractor, that the subcontractor may include the additional work in his original account, and the account will be considered as having “accrued” from the date of the last item. But, as we have stated, we have no such case here.
With the concurrence of the other judges, the judgment of the circuit, court will be affirmed. It is so ordered.