102 Neb. 184 | Neb. | 1918
This is a law action, on contract, tried to the court without a jury. Plaintiff sued to recover $2,961.30 ■claimed to be due by way of bonus for superior efficiency of a pumping apparatus installed for the defendant. For answer defendant alleged that, as one of the considerations for entering into the contract, plaintiff had waived its right to a bonus. It also- asserted that, in event any sum was due under the bonus clause of the contract, the amount was only $1,666.07, and, by way of counterclaim, pleaded a provision of the contract which provided that, in case of delay in installing the apparatus
Appellant’s brief treats the- judgment as if the court had found that plaintiff was entitled to recover on its cause of action the sum demanded, less one trifling item, and allowed the plaintiff’s claim for stipulated damages of $50 a day for 25' days, but the record itself is silent as to the specific items which the court took into account in its finding.
The contract is long and complicated, and each party finds much therein to support the claim it makes. It is conceded that the provision for a bonus was a legitimate one; the greater the efficiency the greater the amount of the bonus, but the district would be compensated by the decreased cost of operation. Appellant claims that plaintiff, through its proper representative, had waived its right to insist upon this provision of the written contract, and its first assignment of error is that the court erred in failing to hold that this provision was waived. The question was submitted on.conflicting evidence, and the finding of the court in favo of plaintiff is amply sustained, and will not be disturbed.
The contract provided for certain-tests of the apparatus. In making the tests “the contractor may be represented by his own expert, * * * and it shall be understood and agreed that a. third expert, who shall be appointed by the district and approved by the contractor, -shall conduct that particular test which shall determine the economical duty performed by the pumping unit.” The tests were made by -experts thus selected, and the expert selected by defendant found the amount to which plaintiff would be entitled as a bonus, if the bonus had not been waived, to
There is still the question of defendant’s right to recover the stipulated damages. Inferentially defendant’s brief says that the court found in favor of the defendant •on this counterclaim in the sum of $1,250. Brief of plaintiff and cross-appellant is to the same effect, but the record is silent. There is a conflict in the evidence on the question of the number of days’ delay properly chargeable to plaintiff, if any. On this question of fact the finding of the court has the same effect as the verdict of a jury.The cross-appellant claims that the amount stipulated for delay in completion of the instalment is a penalty, and not liquidated damages; that defendant proved no damages and cannot recover. This point is disputed by defendant, but it is not necessary to discuss or to decide the question.
Plaintiff has taken a cross-appeal, but doe's not ask a reversal. It seeks to have us add $1,250 to the judgment; the basis of this request being that the trial court erroneously allowed' this amount to defendant on its counterclaim. The court made no special findings. The finding is a general one, and, curiously enough 'it is for the exact amount defendant admits is due under plaintiff’s cause
If either party desired special findings, it ought to have asked for them. The evidence fully sustained the judgment entered; and as plaintiff and cross-appellant does not seek a reversal, but prays only for relief we cannot give, the judgment is
Affirmed.