22 Ala. 409 | Ala. | 1853
The principal legal questions presented in this case, arise out of a contract executed between the parties on the 21st May, 1849. By its terms, the defendants in error agreed to do certain carpenter’s work, the specifications of which are set forth in the contract, in a neat and workmanlike manner; in consideration of which carpenter’s work, “ the party of the first part (the plaintiff in error) agreed to pay, on the first day of January, 1851, to the party
There can be no question, that if it appeared upon the face of the contract, that it was the intention of the party stipulating for the payment of the money, to pay it either upon the completion of the work, or on a day certain, without reference to its completion by that day, in such case, his stipulation would be independent; and this we understand to be the principle asserted in the ease of Thorpe v. Thorpe, 1 Salk, 171. The rule is there laid down, that if, by the terms of the contract, the money is to be paid by a day certain, which must or may happen before the doing of the act which constitutes the consideration of the payment, the performance is not a condition precedent; and in such case, the party may sue for his money without averring or proving performance; and we do not well understand how there can be an exception to this rule. The law, in the construction of written contracts, must arrive at the intention of the parties from the terms which they themselves have used; and whenever they appoint the day of payment on a day certain, which may arrive before the service contracted for- is performed, they show conclusively that they did not intend to refer the payment of the money to the performance of the service. The rule is one of construction simply, and, so far as we have been able to discover, has been steadily adhered to by the courts of Westminster since the time of Lord Holt.' — Terry v. Duntze, 2 H. Black. 889 ; Campbell v. Jones, 6 Term R. 572; and has also been recognized by our own tribunals. Cunningham v. Morrell, 10 John. 203; Allen v. Sanders, 7 B. Mon. 593.
While, however, we defend the rule to which we have referred, as a correct one, in determining from the face of the contract the intention of the parties, in the particular cases
We cannot, however, as a matter of law, determine from the face of this contract whether its stipulations are dependent or independent. The undertaking of the defendants in error, as we have already seen, was to complete the work specified within a reasonable time; and although there may be cases, in which the court, in the construction of a written instrument, might properly determine a question of this character, there must also necessarily be many eases in which it would be impossible to arrive at any certain or definite conclusion. The contract may relate to the time required for the making of an article, the process of which is known only to those actually engaged in its manufacture ; to a thousand matters
In the present case, the work to be performed appertains to a trade; the specifications are in relation to matters which the court cannot be presumed to have any knowledge of, and the question of reasonable time, applied either to the delivery of articles, or the doing of work, is, generally speaking, one of fact, and to be determined by the jury under all the circumstances which surrounded the case at the time the contract was made. Watts v. Sheppard, and Burnett v. Stanton, supra; Cocker v. Franklin Man. Co., 3 Sum. 530; S. C. 1 Story 332. The proper course would, therefore, have been, to have referred the contract to the jury, with the necessary instructions. The question of construction upon the evidence would be simply as to the intention of the parties, as to whether the performance of the work was to jrrecede the payment of the money, in which event the stipulations would be dependent; while on the other hand, if the payment was fixed on a day which would or might happen before the completion of the work, it would be evidence that the parties did not intend to refer the payment of the money to the performance of the work; and in such a case, as we have already seen, the stipulations would be independent.
It results from these views, that the charge of the court, that the stipulation for the payment of the money was independent, was erroneous; and for the same reasons, there was no error in the refusal of the court to give the first charge asked for, which was, in legal effect, that the same stipulation,, as it appeared upon the face of the contract, was dependent.
The second charge should have been given; as, under the
In relation to the last charge requested, taken in connection with the evidence on which it was based, we understand it simply to assert the proposition, that if, while the contract was executory, the party who had stipulated to perform the work did an act which showed conclusively that hefdid not intend to perform his undertaking, the law would authorize the other party to put an end to the contract; and viewed in that aspect, we regard the proposition as a correct one. It would not, we apprehend, be insisted, that if the parties, by mutual agreement, had rescinded the contract, a recovery could be had ; and we are now unable to perceive any difference, so far as the rights of the parties are concerned, between a rescission proper and the termination of the contract in the way mentioned. In either case, the defence to an action brought upon the contract would be full. Apply these principles to the case before us. 'The accidental burning of the house, without the fault of the plaintiff in error, did not ex. onerate the other party from the legal obligation which rested upon him. The rights of the plaintiff in error were not affected by this circumstance; and if, while the contract was executory, the defendants in error did any act which showed clearly they did not intend to perform their portion of the contract, it would have justified the other party in terminating it.
Eor the error we have noticed, the judgment is reversed, and the cause remanded.