96 Ga. App. 187 | Ga. Ct. App. | 1957
On June 4, 1955, the plaintiff Leroy Doyle purchased an automobile from Southwest Motors, Inc., and the purchase price was financed with the defendant United Finance Company. On May 17, 1956, the defendant foreclosed its conditional-sale contract through foreclosure proceedings in the Civil Court of Fulton County. On June 4, 1956, the automobile was sold at a public judicial sale by the Marshal of the Civil Court of Fulton County. On June 30, 1956, the plaintiff and the defendant entered into the following contract: “To whom it may concern. As an inducement to and consideration of the sum of $350, to United Finance Company, I hereby agree to pay the
The only reasonable construction that can be placed on the above quoted contract is that the plaintiff and the defendant agreed thereby that the plaintiff would pay the defendant the balance due under the original contract on the day of the foreclosure and that such balance would be paid by the cash payment of $350 payable in three instalments and that thereafter the remaining balance would be paid by one cash payment. We think that it was also understood between the parties that the cost of repossession and sale under the foreclosure proceeding would be added to the balance due. Under the new contract the defendant waived its right of any deficiency arising by reason of the foreclosure and sale but retained the right to sell the automobile at public sale if the plaintiff failed to perform under the new contract and the plaintiff would be liable to the defendant for any difference between what the automobile would bring at such a sale and the remaining unpaid balance owed by the plaintiff, minus any credits due the plaintiff by reason of any unused insurance benefits and financing charges.
The defendant’s cross-action was based on its deficiency under the first contract resulting from the foreclosure and judicial sale and it was on this basis that the court directed a verdict in the defendant’s favor on the cross-action. As has been stated above,
The plaintiff failed to show that the defendant owed him any money by reason of any payments he made under either the original conditional-sale contract or under the new contract entered into on July 30, 1956; therefore, the court did not err in directing a verdict for the defendant in the main action.
The court did not err in denying that portion of the motion for new trial relating to the direction of a verdict in favor of the defendant in the main action. The court erred in denying that portion of the motion for new trial which complained of the direction of a verdict for the defendant in the cross-action.
Judgment affirmed in part and reversed in part.