CHRISTOPHER DOWNEY & another1 vs. CHUTEHALL CONSTRUCTION CO., LTD.
No. 14-P-1062.
Appellate Court of Massachusetts, Suffolk
September 14, 2015. - January 6, 2016.
88 Mass. App. Ct. 795 (2016)
Present: CYPHER, GREEN, & HANLON, JJ.
Consumer Protection Act, Unfair or deceptive act, Waiver. State Building Code. Waiver. Practice, Civil, Consumer protection case, Summary judgment, Instructions to jury, Waiver.
This court concluded that, in the circumstances of a civil action, a homeowner’s oral waiver of State building code requirements did not preclude the contractor’s liability for the building code violation under
CIVIL ACTION commenced in the Superior Court Department on July 2, 2010.
Motions for summary judgment were heard by Judith Fabricant, J., and the case was tried before Thomas A. Connors, J.
Alicia L. Downey for the plaintiffs.
John D. Fitzpatrick for the defendant.
HANLON, J. After a trial, the jury returned a verdict for the defendant, Chutehall Construction Co., Ltd. (Chutehall). The plaintiffs, Christopher and Mairead Downey, appeal from the resulting judgment. Their appeal presents a narrow issue — whether a contractor’s potential liability for a violation of the relevant building code, which, pursuant to
Background.
The jury could have found the following facts. The Downeys hired Chutehall in 2005 to replace the roof and a roof deck on their townhouse in the Beacon Hill section of Boston. It is undisputed that the building code permits no more than two layers of roofing on the building. See
A few years after Chutehall put on the roof, the Downeys sought to install heating, ventilation, and air conditioning (HVAC) equipment. The HVAC contractor cut a hole through the roof and discovered four layers of roofing materials and evidence of leaking (that is, wet insulation). The Downeys then hired a new roofing contractor to strip the roofing materials, put on a new roof, and reinstall the deck.
Thereafter, the Downeys filed this action against Chutehall seeking to recover the costs of replacing the roof and the deck.4 The only claim at issue is the
At trial, the Downeys filed a motion in limine, seeking to exclude evidence of Christopher Downey’s alleged representations concerning the roof as well as his instructions to Chutehall not to strip the roof, on the ground that a consumer’s oral waiver of building code requirements cannot be a defense to liability. The trial judge denied the motion, referring to the earlier ruling on summary judgment as the law of the case.6 In addition, over the Downeys’ objections, the judge instructed the jurors that they could proceed to determine damages only if they found that the building code was violated and that the violation was not done at the insistence of the Downeys.7 That question also was included
In response to special questions, the jury found that installation of a new roof over three preexisting layers violated the building code, but that the violation was the result of directions given by the Downeys. Accordingly, they did not assess damages. The Downeys’ complaint was dismissed (as was Chutehall’s counterclaim).
Discussion.
The Downeys argue that the trial judge, misinterpreting this court’s comments in Reddish, erred when he instructed the jury that a contractor may assert as a defense to
However, because the parties in Reddish failed to raise the issue, we declined to consider whether the contractual provisions and waivers of liability could operate as a defense to the homeowner’s
This case presents that issue, that is, whether the jurors properly were instructed that, if Chutehall violated the building code “only . . . because the Downeys expressly told Chutehall to do the job in that particular way,” then the Downeys’ waiver is a complete defense to liability under
However, “[a] statutory right or remedy may be waived when the waiver would not frustrate the public policies of the statute. . . . A statutory right may not be disclaimed if the waiver could ‘do violence to the public policy underlying the legislative enactment.’” Canal Elec. Co. v. Westinghouse Elec. Corp., 406 Mass. 369, 377-378 (1990), quoting from Spence v. Reeder, 382 Mass. 398, 413 (1981). See Garrity v. Conservation Commn. of Hingham, 462 Mass. 779, 785-786 (2012) (permitting waiver of conservation commission deadline does not interfere with pur-poses
We note first that “ordinarily [we] would not effectuate a consumer’s waiver of rights under
Finally, the purpose of the building code as in effect during the relevant time period, with which all contractors must comply pursuant to
On balance, we are persuaded that, at least on the facts of this case, where Chutehall’s violation of the building code is clear, where the written agreements specify that the “existing roof system” would be “strip[ped] off and dispose[d] of,” and where
Here, the trial judge instructed the jurors that, in addition to determining whether there was a violation under the specified subsections of the building code, they must also find whether that violation “came in response and a reliance on something [Chutehall was] asked to do, specifically, by the Downeys.” Later, in response to a question by the deliberating jury, the judge instructed that the jurors must answer “an additional question, . . . ‘Was the conduct which violated the Code the result of directions of the [Downeys] for [Chutehall]?’” In the circumstances of this case, the instructions and special question submitted to the jury were erroneous concerning the defense to liability.
“Having determined error, the next step in our analysis is to determine whether the [Downeys have] made a plausible showing that the trier of fact might have reached a different result.” Campbell v. Cape & Islands Healthcare Servs., Inc., 81 Mass. App. Ct. 252, 258-259 (2012) (quotation and citation omitted). The jury found, by special verdict, that Chutehall’s violation of the building code was “the result of directions of the [Downeys].” In response to a question from the jury, they were further instructed that, if they found that the violation was the result of the Downeys’ directions, they need not proceed further and need not assess damages. Given the error in the instruction and special verdict question, there is no doubt that the jury would have reached a different result — indeed, they would have been compelled to do so upon their finding of the building code violation. As a result, reversal is required.10 In addition, because the jury found that Chutehall violated the building code and we have concluded that Chutehall was not entitled to a waiver defense in the circumstances of this case, judgment on the
Accordingly, the judgment for Chutehall on the Downeys’
So ordered.
Notes
“The following acts are prohibited by contractors or subcontractors: . . .
“(10) violation of the building laws of the commonwealth or of any political subdivision thereof; . . .
“Violations of any of the provisions of this chapter shall constitute an unfair or deceptive act under the provisions of chapter ninety-three A.”
